ROADWORKS SUMMARY
Repton Avenue, WEMBLEY, HA0 3DL
Introduction
View current and future planned roadworks and road closures for Repton Avenue, HA0 3DL and the surrounding area.
Our roadwork details are constantly updated and reflect the current situation and we offer both a map view and a listing. We also highlight the major and significant roadworks occuring near to you help you avoid the worst of the delays to your journey.
The roadworks shown below show all current and proposed works during the next 90 days and historical data is recorded since July 2020.
Please note that we re-publish this data and cannot provide any additional information pertaining to a roadwork event. If you require more information, please contact the organisation carrying out the work.
Data are provided by the Department for Transport.
Have we helped today?
If we have helped you today, please consider buying us a quick coffee to keep us going!
Major Roadworks near to Repton Avenue, WEMBLEY, HA0 3DL
Details of major roadworks, currently in progress or starting soon and resulting in road closures and/or traffic signal management for Repton Avenue are shown here covering a 5 mile radius. See further down for details of all roadworks in your area.
18 May 2025
London Borough Of Ealing are carrying out Highway improvement works on Friary Road, Acton.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 1 April 2021 at 00:00 and could run through until 18 May 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Ealing on 8 Apr 2024 at 08:28.
9 Dec 2023 and 10 Dec 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Du Cane Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2023 and could run through until 10 December 2024. The works will impact the carriageway only.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Thames Water on 2 Nov 2023 at 14:09.
1 Mar 2025
London Borough Of Barnet are carrying out Highway improvement works on Charcot Road, Colindale, London.
These works are categorised as Major.
The works started on 8 February 2024 at 00:00 and could run through until 1 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 22 Apr 2024 at 14:30.
1 Mar 2024 and 1 Sep 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Colindale Avenue, Colindale, London.
These works are categorised as Major.
The works will start on or after 1 March 2024 and could run through until 1 September 2025. The works will impact the carriageway only.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by London Borough Of Barnet on 26 Mar 2024 at 08:17.
4 Dec 2024
HS2 are carrying out Utility asset works on Ruskin Gardens, Ealing.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 2 April 2024 at 07:00 and could run through until 4 December 2024. The works will impact the carriageway and parking place.
This roadwork event was last updated by HS2 on 20 Nov 2024 at 14:54.
4 Dec 2024
HS2 are carrying out Utility asset works on Brentham Way, Ealing.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 2 April 2024 at 07:00 and could run through until 4 December 2024. The works will impact the carriageway and parking place.
This roadwork event was last updated by HS2 on 19 Nov 2024 at 16:12.
4 Dec 2024
HS2 are carrying out Utility asset works on Brunswick Road, Ealing.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 2 April 2024 at 07:00 and could run through until 4 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by HS2 on 20 Nov 2024 at 14:54.
3 Mar 2025
Transport for London (TfL) are carrying out Highway repair and maintenance works on Westway, London.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 17 April 2024 at 22:00 and could run through until 3 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 18 Nov 2024 at 11:34.
10 Oct 2025
London Borough Of Barnet are carrying out Highway improvement works on Golders Green Road, Golders Green, London.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 20 May 2024 at 07:27 and could run through until 10 October 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 20 May 2024 at 06:31.
24 Dec 2024
London Borough Of Barnet are carrying out Highway improvement works on Colindale Avenue, Colindale, London.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 19 May 2024 at 23:00 and could run through until 24 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 22 May 2024 at 10:16.
4 Jun 2024 and 31 Mar 2026
London Borough Of Barnet are proposing to carry out Highway improvement works on Colindale Avenue, Colindale, London.
These works are categorised as Major.
The works will start on or after 4 June 2024 and could run through until 31 March 2026. The works will impact the carriageway only.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by London Borough Of Barnet on 8 Feb 2024 at 08:15.
Monday
Thames Water are carrying out Utility asset works on Acton Lane, London.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 10 June 2024 at 08:00 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 6 Nov 2024 at 16:27.
1 Jan 2025
London Borough Of Ealing are carrying out Highway improvement works on Church Road, Northolt.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 10 June 2024 at 09:30 and could run through until 1 January 2025. The works will impact the footway, carriageway, verge and cycleway.
This roadwork event was last updated by London Borough Of Ealing on 13 Jun 2024 at 16:23.
1 Jan 2025
London Borough Of Ealing are carrying out Highway improvement works on Mandeville Road, Northolt.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 10 June 2024 at 09:30 and could run through until 1 January 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by London Borough Of Ealing on 13 Jun 2024 at 16:22.
31 May 2025
London Borough Of Barnet are carrying out Highway improvement works on Station Road, The Hale, Edgware.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 10 June 2024 at 08:57 and could run through until 31 May 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 10 Jun 2024 at 08:05.
13 Mar 2025
Cadent Gas are carrying out Utility asset works on Harrow View, Harrow.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 17 June 2024 at 09:11 and could run through until 13 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 17 Jun 2024 at 08:14.
31 Jan 2025
Transport for London (TfL) are carrying out Highway repair and maintenance works on Wood Lane, London.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 7 July 2024 at 07:30 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Transport for London (TfL) on 7 Jul 2024 at 17:53.
31 Jan 2025
Transport for London (TfL) are carrying out Highway repair and maintenance works on South Africa Road, London.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 7 July 2024 at 07:30 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Transport for London (TfL) on 7 Jul 2024 at 17:54.
Friday
HS2 are carrying out Utility asset works on Lynwood Road, Ealing.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 8 July 2024 at 07:00 and could run through until 29 November 2024. The works will impact the carriageway and parking place.
This roadwork event was last updated by HS2 on 20 Nov 2024 at 14:54.
Monday
Thames Water are carrying out Utility asset works on Greenhill Park, London.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 15 July 2024 at 14:35 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 6 Nov 2024 at 16:28.
9 Dec 2024
London Borough Of Harrow are carrying out Highway improvement works on Greenhill Way, Harrow.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 12 August 2024 at 09:30 and could run through until 9 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Harrow on 29 Oct 2024 at 14:57.
15 Aug 2024 and 24 Dec 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Whitefield Avenue, Cricklewood, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 15 August 2024 and could run through until 24 December 2025. The works will impact the carriageway only.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by London Borough Of Barnet on 10 Jun 2024 at 08:12.
25 Feb 2025
London Borough Of Harrow are carrying out Highway improvement works on College Road, Harrow.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 19 August 2024 at 08:00 and could run through until 25 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Harrow on 19 Aug 2024 at 08:23.
19 Sep 2025
Transport for London (TfL) are carrying out Highway repair and maintenance works on Cooper Road, Hendon, London.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 19 September 2024 at 11:00 and could run through until 19 September 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 2 Oct 2024 at 14:17.
27 Sep and 13 Dec 2024
London Borough Of Hounslow are proposing to carry out Highway improvement works on High Street, Brentford.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 27 September 2024 and could run through until 13 December 2024. The works will impact the carriageway only.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by London Borough Of Hounslow on 1 Oct 2024 at 14:55.
Sunday
Thames Water are carrying out Utility repair and maintenance works on Mount Road, London.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 30 September 2024 at 13:40 and could run through until 1 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 11 Nov 2024 at 08:46.
6 Oct and 7 Dec 2024
Transport for London (TfL) are proposing to carry out Highway improvement works on North Circular Road, Brent Cross, London.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 October 2024 and could run through until 7 December 2024. The works will impact the carriageway only.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Transport for London (TfL) on 1 Aug 2024 at 13:37.
Monday
Thames Water are carrying out Utility asset works on Connaught Road, London.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 14 October 2024 at 10:00 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 6 Nov 2024 at 16:28.
14 Oct and 20 Dec 2024
London Borough Of Barnet are proposing to carry out Highway improvement works on Station Road, The Hale, Edgware.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 14 October 2024 and could run through until 20 December 2024. The works will impact the footway, carriageway and footpath.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by London Borough Of Barnet on 11 Oct 2024 at 14:10.
Tomorrow
UK Power Networks Eastern & London were proposing to carry out New service connection on Hale Lane, Mill Hill, London.
These works were categorised as Major.
Two-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 18 October 2024 and run through until 28 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 2 Oct 2024 at 10:37.
19 Oct and 21 Dec 2024
Network Rail are proposing to carry out Works for Rail Purposes on Acton Lane, London.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 19 October 2024 and could run through until 21 December 2024. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Network Rail on 10 Oct 2024 at 16:26.
21 Dec 2024
Network Rail are carrying out Works for Rail Purposes on Acton Lane, London.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 19 October 2024 at 22:00 and could run through until 21 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Network Rail on 20 Oct 2024 at 09:21.
21 Oct and 6 Dec 2024
Cadent Gas were proposing to carry out Utility asset works on Windmill Avenue, Southall.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 21 October 2024 and run through until 6 December 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 3 Oct 2024 at 13:30.
21 Oct and 6 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Windmill Lane, Southall.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 21 October 2024 and could run through until 6 December 2024. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Cadent Gas on 4 Oct 2024 at 14:16.
6 Dec 2024
Cadent Gas are carrying out Utility asset works on Windmill Lane, Southall.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 21 October 2024 at 09:24 and could run through until 6 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 21 Oct 2024 at 09:42.
21 Oct and 20 Dec 2024
London Borough Of Brent are proposing to carry out Highway repair and maintenance works on Kilburn Lane, Kilburn, London.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 October 2024 and could run through until 20 December 2024. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by London Borough Of Brent on 18 Oct 2024 at 22:19.
20 Dec 2024
London Borough Of Brent are carrying out Highway repair and maintenance works on Kilburn Lane, Kilburn, London.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 21 October 2024 at 08:00 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Brent on 22 Oct 2024 at 08:55.
21 Oct 2024 and 28 Mar 2025
London Borough Of Brent are proposing to carry out Highway repair and maintenance works on High Road, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 October 2024 and could run through until 28 March 2025. The works will impact the carriageway only.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by London Borough Of Brent on 16 Sep 2024 at 09:54.
21 Oct 2024 and 28 Mar 2025
London Borough Of Brent are proposing to carry out Highway repair and maintenance works on Harrow Road, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 October 2024 and could run through until 28 March 2025. The works will impact the carriageway only.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by London Borough Of Brent on 16 Sep 2024 at 09:55.
21 Oct 2024 and 28 Mar 2025
London Borough Of Brent are proposing to carry out Highway repair and maintenance works on Wembley Hill Road, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 October 2024 and could run through until 28 March 2025. The works will impact the carriageway only.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by London Borough Of Brent on 16 Sep 2024 at 09:55.
21 Oct and 12 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Cheney Street, Eastcote.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 October 2024 and could run through until 12 December 2024. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Cadent Gas on 25 Jul 2024 at 10:00.
12 Dec 2024
Cadent Gas are carrying out Utility asset works on Cheney Street, Eastcote.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 21 October 2024 at 13:05 and could run through until 12 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 21 Oct 2024 at 13:28.
6 Dec 2024
UK Power Networks Eastern & London are carrying out New service connection on Downhurst Avenue, Mill Hill, London.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 29 October 2024 at 09:30 and could run through until 6 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 8 Nov 2024 at 13:28.
29 Oct 2024 and 21 Jan 2025
Electricity Network Company are proposing to carry out Utility asset works on Booth Road, Colindale, London.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 29 October 2024 and could run through until 21 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Electricity Network Company on 6 Aug 2024 at 13:20.
Friday
Thames Water are carrying out Utility repair and maintenance works on London Road, Stanmore.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 29 October 2024 at 12:00 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 18 Nov 2024 at 14:58.
Sunday
London Borough Of Hillingdon are proposing to carry out Highway repair and maintenance works on Glencoe Road, Hayes.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 November 2024 and could run through until 1 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 2 Aug 2024 at 07:58.
Sunday
London Borough Of Hillingdon are proposing to carry out Highway repair and maintenance works on Barnhill Lane, Hayes.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 November 2024 and could run through until 1 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 25 Sep 2024 at 10:57.
Sunday
London Borough Of Hillingdon are proposing to carry out Highway repair and maintenance works on Greenway, Hayes.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 November 2024 and could run through until 1 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 2 Aug 2024 at 07:55.
Sunday
London Borough Of Hillingdon are proposing to carry out Highway repair and maintenance works on Kingshill Avenue, Hayes.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 November 2024 and could run through until 1 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 2 Aug 2024 at 07:50.
Sunday
London Borough Of Hillingdon are proposing to carry out Highway repair and maintenance works on Owen Road, Hayes.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 November 2024 and could run through until 1 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 2 Aug 2024 at 07:49.
Sunday
London Borough Of Hillingdon are proposing to carry out Highway repair and maintenance works on Ayles Road, Hayes.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 November 2024 and could run through until 1 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 1 Aug 2024 at 11:37.
Sunday
London Borough Of Hillingdon are proposing to carry out Highway repair and maintenance works on Greenway, Hayes.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 November 2024 and could run through until 1 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 2 Aug 2024 at 07:56.
Sunday
London Borough Of Hillingdon are proposing to carry out Highway repair and maintenance works on Station Approach, South Ruislip, Ruislip.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 November 2024 and could run through until 1 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 22 Oct 2024 at 08:55.
Sunday
London Borough Of Hillingdon are proposing to carry out Highway repair and maintenance works on Station Approach, South Ruislip, Ruislip.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 November 2024 and could run through until 1 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 24 Oct 2024 at 10:53.
Sunday
London Borough Of Hillingdon were proposing to carry out Highway repair and maintenance works on Field End Road, Ruislip.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 1 November 2024 and run through until 1 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 8 Aug 2024 at 15:54.
Sunday
London Borough Of Hillingdon were proposing to carry out Highway repair and maintenance works on West End Road, Ruislip.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 1 November 2024 and run through until 1 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 20 Aug 2024 at 15:01.
Sunday
London Borough Of Hillingdon are proposing to carry out Highway repair and maintenance works on High Road, Eastcote.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 November 2024 and could run through until 1 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 2 Aug 2024 at 07:53.
Friday
UK Power Networks Eastern & London are proposing to carry out New service connection on High Street, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 4 November 2024 and could run through until 29 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by UK Power Networks Eastern & London on 25 Oct 2024 at 16:02.
Friday
UK Power Networks Eastern & London are proposing to carry out New service connection on High Street, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 4 November 2024 and could run through until 29 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by UK Power Networks Eastern & London on 5 Nov 2024 at 10:22.
4 Nov 2024 and 31 Jan 2025
Thames Water are proposing to carry out Utility asset works on Lydford Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 4 November 2024 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 22 Oct 2024 at 09:27.
Tomorrow
London Borough Of Hillingdon are carrying out Highway repair and maintenance works on Kings College Road, Ruislip.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 4 November 2024 at 08:00 and could run through until 28 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 4 Nov 2024 at 08:53.
Friday
London Borough Of Harrow are proposing to carry out Highway improvement works on Station Road, Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 5 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 18 Oct 2024 at 09:46.
Saturday
UK Power Networks Eastern & London are proposing to carry out New service connection on Downhurst Avenue, Mill Hill, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 5 November 2024 and could run through until 30 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 8 Oct 2024 at 08:17.
6 Nov 2024 and 13 Mar 2025
London Borough Of Barnet were proposing to carry out Highway improvement works on Shirehall Lane, Hendon, London.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 November 2024 and run through until 13 March 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 6 Nov 2024 at 09:37.
7 Nov 2024 and 13 Jan 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Cool Oak Lane, Colindale, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 7 November 2024 and could run through until 13 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 17 Jul 2024 at 10:56.
8 Nov 2024 and 3 Feb 2025
Transport for London (TfL) are proposing to carry out Highway improvement works on Westway, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 8 November 2024 and could run through until 3 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 26 Jul 2024 at 13:18.
8 Nov 2024 and 3 Mar 2025
Transport for London (TfL) are proposing to carry out Highway improvement works on Westway, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 8 November 2024 and could run through until 3 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 22 Aug 2024 at 20:12.
17 Feb 2025
Transport for London (TfL) are carrying out Highway improvement works on Westway, London.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 8 November 2024 at 22:00 and could run through until 17 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 18 Nov 2024 at 12:59.
8 Nov 2024 and 3 Feb 2025
Transport for London (TfL) are proposing to carry out Highway improvement works on West Cross Route, London.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 8 November 2024 and could run through until 3 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 26 Jul 2024 at 11:07.
8 Nov 2024 and 3 Mar 2025
Transport for London (TfL) are proposing to carry out Highway improvement works on West Cross Route, London.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 8 November 2024 and could run through until 3 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 22 Aug 2024 at 20:09.
17 Feb 2025
Transport for London (TfL) are carrying out Highway improvement works on West Cross Route, London.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 8 November 2024 at 22:00 and could run through until 17 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 18 Nov 2024 at 12:59.
8 Nov 2024 and 3 Mar 2025
Transport for London (TfL) are proposing to carry out Highway improvement works on West Cross Route, London.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 8 November 2024 and could run through until 3 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 22 Aug 2024 at 20:11.
17 Feb 2025
Transport for London (TfL) are carrying out Highway improvement works on West Cross Route, London.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 8 November 2024 at 22:00 and could run through until 17 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 18 Nov 2024 at 12:58.
8 Nov 2024 and 3 Mar 2025
Transport for London (TfL) are proposing to carry out Highway improvement works on Westway, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 8 November 2024 and could run through until 3 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 22 Aug 2024 at 20:09.
17 Feb 2025
Transport for London (TfL) are carrying out Highway improvement works on Westway, London.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 8 November 2024 at 22:00 and could run through until 17 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 18 Nov 2024 at 12:58.
11 Nov and 22 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Ealing Road, Brentford.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 22 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 4 Nov 2024 at 15:43.
Monday
Cadent Gas are proposing to carry out Utility asset works on Ealing Road, Brentford.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 8 Nov 2024 at 11:57.
Monday
Cadent Gas are carrying out Utility asset works on Ealing Road, Brentford.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 11 November 2024 at 15:07 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 11 Nov 2024 at 15:17.
Today
UK Power Distribution are carrying out Utility asset works on Warwick Road, Ealing.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 11 November 2024 at 08:00 and could run through until 27 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by UK Power Distribution on 26 Nov 2024 at 10:49.
11 Nov and 6 Dec 2024
UK Power Networks Eastern & London are proposing to carry out New service connection on High Street, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 6 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by UK Power Networks Eastern & London on 22 Aug 2024 at 09:26.
28 Feb 2025
London Borough Of Ealing are carrying out Highway improvement works on Greenford Road, Greenford.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 11 November 2024 at 08:00 and could run through until 28 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Ealing on 13 Nov 2024 at 09:00.
Friday
London Borough Of Brent are proposing to carry out Highway repair and maintenance works on Park Lane, Wembley.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 29 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Brent on 31 Oct 2024 at 23:12.
20 Dec 2024
London Borough Of Brent are carrying out Highway repair and maintenance works on Park Lane, Wembley.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 11 November 2024 at 08:00 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Brent on 25 Nov 2024 at 12:53.
Friday
London Borough Of Harrow are proposing to carry out Highway improvement works on Station Road, Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 25 Oct 2024 at 09:41.
Friday
London Borough Of Harrow are carrying out Highway improvement works on Station Road, Harrow.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 11 November 2024 at 08:26 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 11 Nov 2024 at 08:31.
11 Nov and 6 Dec 2024
London Borough Of Barnet are proposing to carry out Highway improvement works on Eaton Road, Hendon, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 6 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Barnet on 16 Oct 2024 at 14:45.
Friday
UK Power Networks Eastern & London are carrying out Utility asset works on Moss Lane, Pinner.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 11 November 2024 at 10:00 and could run through until 29 November 2024. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by UK Power Networks Eastern & London on 21 Nov 2024 at 15:49.
Saturday
UK Power Networks Eastern & London are proposing to carry out New service connection on The Broadway, Mill Hill, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 30 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 30 Sep 2024 at 15:13.
Saturday
UK Power Networks Eastern & London are proposing to carry out New service connection on The Broadway, Mill Hill, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 30 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 18 Oct 2024 at 09:43.
Saturday
UK Power Networks Eastern & London were proposing to carry out New service connection on The Broadway, Mill Hill, London.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 11 November 2024 and run through until 30 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 23 Oct 2024 at 09:19.
Saturday
UK Power Networks Eastern & London are carrying out New service connection on The Broadway, Mill Hill, London.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 11 November 2024 at 20:15 and could run through until 30 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 22 Nov 2024 at 09:24.
Saturday
London Borough Of Barnet are proposing to carry out Highway improvement works on Wessex Gardens, Golders Green, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 12 November 2024 and could run through until 30 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 11 Jul 2024 at 14:30.
12 Dec 2024
Thames Water are carrying out Utility repair and maintenance works on Abbey Road, London.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 14 November 2024 at 12:50 and could run through until 12 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 14 Nov 2024 at 13:38.
12 Dec 2024
Thames Water are carrying out Utility repair and maintenance works on Cumberland Avenue, London.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 14 November 2024 at 12:50 and could run through until 12 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 14 Nov 2024 at 13:38.
6 Dec 2024
London Borough Of Barnet are carrying out Highway improvement works on Eaton Road, Hendon, London.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 15 November 2024 at 14:00 and could run through until 6 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Barnet on 15 Nov 2024 at 14:37.
20 Dec 2024
Scottish Hydro Electric Power Dis are carrying out Utility repair and maintenance works on Hunt Road, Southall.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 18 November 2024 at 09:00 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Scottish Hydro Electric Power Dis on 18 Nov 2024 at 09:57.
Monday
UK Power Networks Eastern & London were proposing to carry out Statutory Infrastructure Works on Old Oak Common Lane, London.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 18 November 2024 and run through until 2 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 21 Oct 2024 at 10:11.
18 Nov and 6 Dec 2024
Murphy Power Distribution are proposing to carry out New service connection on Central Way, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 6 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Murphy Power Distribution on 21 Aug 2024 at 16:25.
6 Dec 2024
Murphy Power Distribution are carrying out New service connection on Central Way, London.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 18 November 2024 at 11:53 and could run through until 6 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Murphy Power Distribution on 18 Nov 2024 at 11:59.
18 Nov and 9 Dec 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Chatsworth Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 9 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 13 Nov 2024 at 13:24.
9 Dec 2024
Thames Water are carrying out Utility repair and maintenance works on Chatsworth Road, London.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 18 November 2024 at 08:00 and could run through until 9 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 18 Nov 2024 at 08:25.
31 Jan 2025
Thames Water are carrying out Utility asset works on Lydford Road, London.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 18 November 2024 at 08:00 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 18 Nov 2024 at 08:24.
18 Nov and 6 Dec 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Bolton Road, Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 6 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 18 Oct 2024 at 09:19.
Friday
UK Power Networks Eastern & London are proposing to carry out Utility asset works on Burnt Oak Broadway, Edgware.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 29 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by UK Power Networks Eastern & London on 3 Sep 2024 at 15:44.
Friday
UK Power Networks Eastern & London are proposing to carry out Utility asset works on Burnt Oak Broadway, Edgware.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 29 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by UK Power Networks Eastern & London on 13 Sep 2024 at 16:02.
Friday
UK Power Networks Eastern & London were proposing to carry out Utility asset works on Burnt Oak Broadway, Edgware.
These works were categorised as Major.
A lane was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 18 November 2024 and run through until 29 November 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by UK Power Networks Eastern & London on 8 Oct 2024 at 08:12.
4 Dec 2024
Cadent Gas are carrying out Utility repair and maintenance works on High Road, Wembley.
The works started on 19 November 2024 at 14:18 and could run through until 4 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 25 Nov 2024 at 13:32.
Friday
Cadent Gas are carrying out Utility repair and maintenance works on Pound Lane, London.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 21 November 2024 at 05:39 and could run through until 29 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 21 Nov 2024 at 09:39.
22 Nov and 17 Dec 2024
UK Power Networks Eastern & London were proposing to carry out New service connection on High Street, London.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 22 November 2024 and run through until 17 December 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by UK Power Networks Eastern & London on 12 Aug 2024 at 17:23.
Tomorrow
Affinity Water are carrying out Utility repair and maintenance works on Court Drive, Stanmore.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 22 November 2024 at 09:07 and could run through until 28 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 25 Nov 2024 at 10:59.
Friday
Thames Water are proposing to carry out Statutory Infrastructure Works on Chiswick High Road, Chiswick, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 23 November 2024 and could run through until 29 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 14 Nov 2024 at 07:57.
Friday
Thames Water are carrying out Statutory Infrastructure Works on Chiswick High Road, Chiswick, London.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 23 November 2024 at 08:37 and could run through until 29 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 23 Nov 2024 at 09:02.
Tuesday
Cadent Gas are carrying out Utility repair and maintenance works on Lovett Way, London.
The works started on 23 November 2024 at 09:54 and could run through until 3 December 2024. The works will impact the footway, carriageway and footpath.
This roadwork event was last updated by Cadent Gas on 23 Nov 2024 at 09:56.
Tomorrow
London Borough Of Ealing are proposing to carry out Highway improvement works on Greenford Road, Greenford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 24 November 2024 and could run through until 28 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Ealing on 13 Nov 2024 at 09:11.
20 Dec 2024
Scottish Hydro Electric Power Dis are carrying out Utility repair and maintenance works on Swift Road, Southall.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 25 November 2024 at 09:15 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Scottish Hydro Electric Power Dis on 25 Nov 2024 at 09:37.
Monday
Thames Water are proposing to carry out New service connection on Enfield Road, Acton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 18 Sep 2024 at 10:04.
Monday
Thames Water are carrying out New service connection on Enfield Road, Acton.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 25 November 2024 at 12:24 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 25 Nov 2024 at 13:15.
Friday
Thames Water are proposing to carry out New service connection on Hatfield Road, West Ealing.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 29 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 11 Sep 2024 at 12:58.
Friday
Thames Water are carrying out New service connection on Hatfield Road, West Ealing.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 25 November 2024 at 10:45 and could run through until 29 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 25 Nov 2024 at 11:05.
Tomorrow
Thames Water are proposing to carry out New service connection on Oxford Gardens, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 28 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 21 Aug 2024 at 14:48.
Tomorrow
Thames Water are carrying out New service connection on Oxford Gardens, London.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 25 November 2024 at 10:22 and could run through until 28 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 25 Nov 2024 at 10:28.
9 Dec 2024
UK Power Networks Eastern & London are carrying out Statutory Infrastructure Works on Old Oak Common Lane, Acton.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 25 November 2024 at 13:30 and could run through until 9 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 25 Nov 2024 at 14:47.
Friday
London Borough Of Ealing are proposing to carry out Highway improvement works on Copley Close, Hanwell.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Ealing on 24 Oct 2024 at 09:49.
24 Dec 2024
London Borough Of Ealing are carrying out Highway improvement works on Rowdell Road, Northolt.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 25 November 2024 at 09:30 and could run through until 24 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Ealing on 25 Nov 2024 at 10:21.
Today
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Eliot Drive, South Harrow.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 25 November 2024 and run through until 27 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 23 Oct 2024 at 09:15.
25 Nov 2024 and 5 Jan 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on West Hendon Broadway, Colindale, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 5 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Barnet on 6 Nov 2024 at 09:20.
25 Nov 2024 and 16 Jun 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on West Hendon Broadway, Colindale, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 16 June 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Barnet on 6 Nov 2024 at 11:15.
Today
London Borough Of Harrow are proposing to carry out Highway improvement works on East Towers, Pinner.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 27 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 17 Jul 2024 at 11:55.
Today
London Borough Of Harrow are carrying out Highway improvement works on East Towers, Pinner.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 25 November 2024 at 08:12 and could run through until 27 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 25 Nov 2024 at 08:17.
Today
London Borough Of Harrow are proposing to carry out Highway improvement works on West End Lane, Pinner.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 27 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 17 Jul 2024 at 11:55.
Tomorrow
London Borough Of Harrow are carrying out Highway improvement works on West End Lane, Pinner.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 25 November 2024 at 08:12 and could run through until 28 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 25 Nov 2024 at 08:17.
Today
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Manor Park Drive, North Harrow.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 25 November 2024 and run through until 27 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 31 Oct 2024 at 08:34.
25 Nov 2024 and 17 Jan 2025
London Borough Of Barnet were proposing to carry out Highway improvement works on Burnt Oak Broadway, Edgware.
These works were categorised as Major.
Two-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 25 November 2024 and run through until 17 January 2025. The works were due to impact the footway only.
This roadwork event was last updated by London Borough Of Barnet on 23 Aug 2024 at 13:41.
Today
Affinity Water are proposing to carry out Utility repair and maintenance works on Parkfield Avenue, Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 27 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 6 Sep 2024 at 10:19.
Today
Affinity Water are carrying out Utility repair and maintenance works on Parkfield Avenue, Harrow.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 25 November 2024 at 10:03 and could run through until 27 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 25 Nov 2024 at 10:03.
25 Nov 2024 and 17 Jan 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Stockwell Close, Edgware.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 17 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Barnet on 23 Aug 2024 at 16:05.
Today
London Borough Of Barnet are proposing to carry out Highway improvement works on Great Field, Colindale, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 27 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Barnet on 18 Nov 2024 at 10:26.
Today
London Borough Of Barnet are proposing to carry out Highway improvement works on Great Field, Colindale, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 27 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Barnet on 18 Nov 2024 at 10:26.
25 Nov and 20 Dec 2024
London Borough Of Barnet are proposing to carry out Highway improvement works on Great Field, Colindale, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 21 Aug 2024 at 13:52.
Today
London Borough Of Harrow are proposing to carry out Highway repair and maintenance works on The Chase, Stanmore.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 27 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 15 Aug 2024 at 17:44.
Monday
Thames Water were proposing to carry out New service connection on Kingsdown Avenue, West Ealing.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 26 November 2024 and run through until 2 December 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 11 Oct 2024 at 09:55.
Monday
Thames Water are proposing to carry out New service connection on Kingsdown Avenue, West Ealing.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 26 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 17 Oct 2024 at 09:07.
Monday
Thames Water are carrying out New service connection on Kingsdown Avenue, West Ealing.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 26 November 2024 at 10:49 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 26 Nov 2024 at 11:43.
Monday
Cadent Gas are carrying out Utility repair and maintenance works on Uxbridge Road, Southall.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 26 November 2024 at 11:00 and could run through until 2 December 2024. The works will impact the carriageway and verge.
This roadwork event was last updated by Cadent Gas on 26 Nov 2024 at 11:34.
Monday
UK Power Networks Eastern & London are proposing to carry out Utility repair and maintenance works on Wood End Avenue, South Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 26 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by UK Power Networks Eastern & London on 2 Sep 2024 at 09:39.
Monday
UK Power Networks Eastern & London are carrying out Utility repair and maintenance works on Wood End Avenue, South Harrow.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 26 November 2024 at 10:07 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by UK Power Networks Eastern & London on 26 Nov 2024 at 10:07.
Tomorrow
London Borough Of Harrow are proposing to carry out Highway repair and maintenance works on Rayners Lane, Rayners Lane.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 26 November 2024 and could run through until 28 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 15 Aug 2024 at 17:49.
Tomorrow
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Elmcroft Crescent, North Harrow.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 26 November 2024 and run through until 28 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 29 Oct 2024 at 08:54.
Tomorrow
London Borough Of Barnet are proposing to carry out Highway improvement works on Stockwell Close, Edgware.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 26 November 2024 and could run through until 28 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 15 Oct 2024 at 15:19.
Saturday
London Borough Of Ealing are proposing to carry out Highway improvement works on Uxbridge Road, Ealing.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 November 2024 and could run through until 30 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Ealing on 26 Nov 2024 at 16:36.
Friday
London Borough Of Ealing are proposing to carry out Highway improvement works on The Broadway, Ealing.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Ealing on 26 Nov 2024 at 16:26.
Friday
London Borough Of Ealing are proposing to carry out Highway improvement works on The Mall, Ealing.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Ealing on 26 Nov 2024 at 16:18.
Friday
London Borough Of Ealing are proposing to carry out Highway improvement works on Ruislip Road, Greenford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Ealing on 13 Nov 2024 at 13:56.
Friday
London Borough Of Ealing are proposing to carry out Highway improvement works on Ruislip Road, Greenford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Ealing on 20 Nov 2024 at 08:12.
Friday
London Borough Of Harrow are proposing to carry out Highway repair and maintenance works on Sandringham Crescent, South Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 15 Aug 2024 at 17:50.
Friday
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Alexandra Avenue, Rayners Lane.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 27 November 2024 and run through until 29 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 15 Aug 2024 at 17:27.
Friday
London Borough Of Harrow are proposing to carry out Highway repair and maintenance works on Exeter Road, South Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 15 Aug 2024 at 17:44.
Friday
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Eastcote Avenue, South Harrow.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 27 November 2024 and run through until 29 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 24 Oct 2024 at 08:54.
Friday
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Coles Crescent, South Harrow.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 27 November 2024 and run through until 29 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 21 Oct 2024 at 10:10.
Friday
London Borough Of Harrow are proposing to carry out Highway repair and maintenance works on Capthorne Avenue, Rayners Lane.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 15 Aug 2024 at 17:46.
Friday
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Alfriston Avenue, North Harrow.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 27 November 2024 and run through until 29 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 25 Oct 2024 at 08:20.
Friday
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Rosecroft Walk, Pinner.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 27 November 2024 and run through until 29 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 7 Oct 2024 at 08:42.
Friday
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on West End Avenue, Pinner.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 27 November 2024 and run through until 29 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 7 Oct 2024 at 08:49.
Friday
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Broadcroft Avenue, Stanmore.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 27 November 2024 and run through until 29 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 28 Aug 2024 at 09:41.
Friday
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Woodhall Avenue, Pinner.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 27 November 2024 and run through until 29 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 28 Oct 2024 at 08:55.
Friday
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Woodhall Drive, Pinner.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 27 November 2024 and run through until 29 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 7 Oct 2024 at 08:56.
Friday
London Borough Of Harrow are proposing to carry out Highway repair and maintenance works on Wolverton Road, Stanmore.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 15 Aug 2024 at 17:45.
Friday
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Hathaway Close, Harrow Weald.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 27 November 2024 and run through until 29 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 16 Oct 2024 at 10:36.
Saturday
London Borough Of Harrow are proposing to carry out Highway repair and maintenance works on Queensbury Circle Parade, Kenton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 November 2024 and could run through until 30 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 17 Jul 2024 at 12:25.
Sunday
London Borough Of Harrow are proposing to carry out Highway repair and maintenance works on Queensbury Circle Parade, Kenton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 November 2024 and could run through until 1 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 16 Oct 2024 at 13:13.
Monday
London Borough Of Harrow are proposing to carry out Highway repair and maintenance works on The Ridgeway, Stanmore.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 November 2024 and could run through until 2 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 15 Aug 2024 at 17:45.
29 Nov and 24 Dec 2024
Thames Water were proposing to carry out Utility repair and maintenance works on Station Road, The Hale, Edgware.
These works were categorised as Major.
The works were originally planned to start 29 November 2024 and run through until 24 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Thames Water on 22 Oct 2024 at 12:39.
2 and 9 Dec 2024
Thames Water are proposing to carry out Disconnection or alteration of supply on Boston Road, Hanwell.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 9 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 10 Oct 2024 at 14:14.
2 and 4 Dec 2024
Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Westway, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 4 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 7 Nov 2024 at 11:12.
2 and 4 Dec 2024
Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Westway, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 4 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 7 Nov 2024 at 11:03.
2 and 4 Dec 2024
Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Wood Lane, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 4 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 7 Nov 2024 at 10:21.
2 and 16 Dec 2024
UK Power Networks Eastern & London are proposing to carry out Statutory Infrastructure Works on Braybrook Street, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 16 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 17 Oct 2024 at 18:14.
2 and 16 Dec 2024
UK Power Networks Eastern & London were proposing to carry out Statutory Infrastructure Works on Braybrook Street, London.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 16 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 25 Oct 2024 at 08:10.
2 and 16 Dec 2024
UK Power Networks Eastern & London were proposing to carry out Statutory Infrastructure Works on Old Oak Common Lane, London.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 16 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 21 Oct 2024 at 10:09.
2 and 16 Dec 2024
UK Power Networks Eastern & London are proposing to carry out Statutory Infrastructure Works on Old Oak Common Lane, Acton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 16 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 11 Oct 2024 at 11:31.
2 and 18 Dec 2024
London Borough Of Hillingdon are proposing to carry out Highway repair and maintenance works on Kingshill Avenue, Hayes.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 18 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 9 Aug 2024 at 09:50.
2 and 25 Dec 2024
Electricity Network Company are proposing to carry out Utility asset works on Fernhead Road, Harrow Road, London.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 25 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity Network Company on 27 Sep 2024 at 16:01.
2 and 4 Dec 2024
Affinity Water are proposing to carry out Utility repair and maintenance works on Manor Farm Road, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 4 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 16 Sep 2024 at 06:16.
2 and 4 Dec 2024
Affinity Water are proposing to carry out Utility repair and maintenance works on Manor Farm Road, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 4 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 15 Oct 2024 at 09:59.
2 and 6 Dec 2024
UK Power Networks Eastern & London are proposing to carry out New service connection on Monks Park, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 6 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 23 Aug 2024 at 14:32.
2 and 22 Dec 2024
Thames Water are proposing to carry out Utility asset works on Buxton Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 22 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 22 Oct 2024 at 09:27.
2 and 22 Dec 2024
Thames Water are proposing to carry out Utility asset works on Buxton Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 22 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 29 Oct 2024 at 08:16.
2 Dec 2024 and 25 May 2025
Thames Water are proposing to carry out Utility asset works on Chapter Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 25 May 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 22 Oct 2024 at 09:27.
2 Dec 2024 and 25 May 2025
Thames Water are proposing to carry out Utility asset works on Chapter Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 25 May 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 29 Oct 2024 at 08:16.
2 and 8 Dec 2024
Thames Water were proposing to carry out Utility asset works on Tenterden Grove, Hendon, London.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 8 December 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 15 Oct 2024 at 10:05.
2 and 4 Dec 2024
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Milman Close, Pinner.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 4 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 7 Oct 2024 at 08:50.
2 and 4 Dec 2024
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Marsworth Avenue, Hatch End.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 4 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 7 Oct 2024 at 08:55.
2 and 4 Dec 2024
London Borough Of Harrow are proposing to carry out Highway repair and maintenance works on Fallowfield, Stanmore.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 4 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 18 Jul 2024 at 09:08.
2 and 5 Dec 2024
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Fallowfield, Stanmore.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 5 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 5 Sep 2024 at 13:24.
2 and 5 Dec 2024
London Borough Of Harrow are proposing to carry out Highway repair and maintenance works on Fallowfield, Stanmore.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 5 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 24 Sep 2024 at 12:39.
3 and 7 Dec 2024
Royal Borough Of Kensington And Chelsea were proposing to carry out Highway improvement works on Southam Street, London.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 3 December 2024 and run through until 7 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Royal Borough Of Kensington And Chelsea on 14 Oct 2024 at 15:36.
3 and 7 Dec 2024
Royal Borough Of Kensington And Chelsea were proposing to carry out Highway improvement works on Adair Road, London.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 3 December 2024 and run through until 7 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Royal Borough Of Kensington And Chelsea on 14 Oct 2024 at 15:39.
3 and 7 Dec 2024
Royal Borough Of Kensington And Chelsea were proposing to carry out Highway improvement works on Kensal Road, London.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 3 December 2024 and run through until 7 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Royal Borough Of Kensington And Chelsea on 14 Oct 2024 at 15:32.
3 and 11 Dec 2024
Affinity Water were proposing to carry out Utility asset works on Borthwick Road, Colindale, London.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 3 December 2024 and run through until 11 December 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 20 Nov 2024 at 10:14.
4 and 6 Dec 2024
City Of Westminster are proposing to carry out Highway repair and maintenance works on Harrow Road, Westbourne, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 4 December 2024 and could run through until 6 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by City Of Westminster on 24 Jun 2024 at 13:27.
4 and 6 Dec 2024
City Of Westminster are proposing to carry out Highway repair and maintenance works on Harrow Road, Westbourne, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 4 December 2024 and could run through until 6 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by City Of Westminster on 26 Nov 2024 at 09:57.
4 and 6 Dec 2024
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Naresby Fold, Stanmore.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 4 December 2024 and run through until 6 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 5 Sep 2024 at 13:42.
4 and 6 Dec 2024
London Borough Of Harrow are proposing to carry out Highway repair and maintenance works on Naresby Fold, Stanmore.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 4 December 2024 and could run through until 6 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 12 Sep 2024 at 11:49.
5 and 9 Dec 2024
Electricity Network Company are proposing to carry out Utility asset works on Bollo Bridge Road, Acton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 5 December 2024 and could run through until 9 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity Network Company on 20 Nov 2024 at 12:45.
5 and 12 Dec 2024
Thames Water are proposing to carry out Disconnection or alteration of supply on Rosebank Road, Hanwell.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 5 December 2024 and could run through until 12 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 11 Oct 2024 at 15:51.
5 and 12 Dec 2024
Thames Water are proposing to carry out Disconnection or alteration of supply on Boston Road, Hanwell.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 5 December 2024 and could run through until 12 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 24 Oct 2024 at 11:39.
5 and 8 Dec 2024
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Pinner Road, North Harrow.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 5 December 2024 and run through until 8 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 25 Oct 2024 at 11:13.
6 and 9 Dec 2024
City Of Westminster are proposing to carry out Highway repair and maintenance works on Harrow Road, Westbourne, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 December 2024 and could run through until 9 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by City Of Westminster on 27 Sep 2024 at 15:58.
6 and 9 Dec 2024
City Of Westminster are proposing to carry out Highway repair and maintenance works on Harrow Road, Westbourne, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 December 2024 and could run through until 9 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by City Of Westminster on 26 Nov 2024 at 09:51.
6 and 15 Dec 2024
Last Mile Electricity (formerly Global Utility Connections) are proposing to carry out Utility repair and maintenance works on Downing Drive, Greenford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 December 2024 and could run through until 15 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Last Mile Electricity (formerly Global Utility Connections) on 18 Oct 2024 at 15:31.
6 and 15 Dec 2024
Last Mile Electricity (formerly Global Utility Connections) are proposing to carry out Utility repair and maintenance works on Downing Drive, Greenford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 December 2024 and could run through until 15 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Last Mile Electricity (formerly Global Utility Connections) on 24 Oct 2024 at 11:18.
6 and 8 Dec 2024
Last Mile Electricity (formerly Global Utility Connections) are proposing to carry out Utility repair and maintenance works on Downing Drive, Greenford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 December 2024 and could run through until 8 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Last Mile Electricity (formerly Global Utility Connections) on 6 Nov 2024 at 10:05.
6 and 15 Dec 2024
Last Mile Electricity (formerly Global Utility Connections) are proposing to carry out Utility repair and maintenance works on Ingram Way, Greenford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 December 2024 and could run through until 15 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Last Mile Electricity (formerly Global Utility Connections) on 25 Oct 2024 at 10:15.
6 and 8 Dec 2024
Last Mile Electricity (formerly Global Utility Connections) are proposing to carry out Utility repair and maintenance works on Ingram Way, Greenford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 December 2024 and could run through until 8 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Last Mile Electricity (formerly Global Utility Connections) on 6 Nov 2024 at 10:05.
9 Dec 2024 and 2 May 2025
Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Wood Lane, London.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 2 May 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 13 Jun 2024 at 11:21.
9 and 13 Dec 2024
Thames Water are proposing to carry out New service connection on Coronation Road, Park Royal.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 13 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 2 Oct 2024 at 09:08.
9 and 23 Dec 2024
London Borough Of Hillingdon are proposing to carry out Highway repair and maintenance works on Barnhill Lane, Hayes.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 23 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 2 Oct 2024 at 09:17.
9 and 23 Dec 2024
London Borough Of Hillingdon are proposing to carry out Highway repair and maintenance works on Barnhill Lane, Hayes.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 23 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 8 Oct 2024 at 13:52.
9 and 11 Dec 2024
Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Hendon Way, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 11 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 11 Nov 2024 at 12:02.
9 and 11 Dec 2024
Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Hendon Way, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 11 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 13 Nov 2024 at 12:19.
9 and 13 Dec 2024
London Borough Of Harrow are proposing to carry out Highway improvement works on Kymberley Road, Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 13 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 15 Oct 2024 at 14:54.
9 and 13 Dec 2024
London Borough Of Barnet are proposing to carry out Highway improvement works on Varley Parade Service Road, Colindale, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 13 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 4 Sep 2024 at 11:38.
9 and 12 Dec 2024
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Parkfield Gardens, Harrow.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 9 December 2024 and run through until 12 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 17 Oct 2024 at 11:29.
9 Dec 2024 and 15 Jan 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Stockwell Close, Edgware.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 15 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Barnet on 24 Sep 2024 at 14:32.
9 and 11 Dec 2024
Cornerstone Telecommunications Infrastructure were proposing to carry out Utility asset works on Weston Drive, Stanmore.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 9 December 2024 and run through until 11 December 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cornerstone Telecommunications Infrastructure on 3 Sep 2024 at 12:09.
9 and 12 Dec 2024
Cornerstone Telecommunications Infrastructure are proposing to carry out Utility asset works on Weston Drive, Stanmore.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 12 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cornerstone Telecommunications Infrastructure on 18 Oct 2024 at 09:24.
9 and 23 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Masefield Avenue, Stanmore.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 23 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 20 Nov 2024 at 09:04.
10 and 12 Dec 2024
London Borough Of Camden are proposing to carry out Highway repair and maintenance works on Fortune Green Road, Fortune Green, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 10 December 2024 and could run through until 12 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Camden on 19 Sep 2024 at 15:08.
11 and 18 Dec 2024
London Borough Of Harrow are proposing to carry out Highway improvement works on Station Road, Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 December 2024 and could run through until 18 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 19 Sep 2024 at 09:50.
11 and 22 Dec 2024
London Borough Of Harrow are proposing to carry out Highway improvement works on Greenhill Way, Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 December 2024 and could run through until 22 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 19 Sep 2024 at 09:48.
11 and 16 Dec 2024
London Borough Of Harrow are proposing to carry out Highway improvement works on Kymberley Road, Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 December 2024 and could run through until 16 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 19 Sep 2024 at 09:50.
11 and 18 Dec 2024
London Borough Of Harrow were proposing to carry out roadworks on Havelock Place, Harrow.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 11 December 2024 and run through until 18 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 30 Sep 2024 at 07:44.
11 and 13 Dec 2024
BT are proposing to carry out Utility asset works on Nibthwaite Road, Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 December 2024 and could run through until 13 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by BT on 18 Oct 2024 at 09:19.
11 and 13 Dec 2024
Affinity Water are proposing to carry out Utility asset works on Langland Crescent, Stanmore.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 December 2024 and could run through until 13 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Affinity Water on 17 Oct 2024 at 13:24.
11 and 13 Dec 2024
Affinity Water are proposing to carry out Utility asset works on Langland Crescent, Stanmore.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 December 2024 and could run through until 13 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Affinity Water on 20 Nov 2024 at 07:56.
12 and 16 Dec 2024
Affinity Water are proposing to carry out Utility repair and maintenance works on Manor Farm Road, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 12 December 2024 and could run through until 16 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 28 Aug 2024 at 11:48.
12 and 14 Dec 2024
London Borough Of Harrow are proposing to carry out Highway repair and maintenance works on Lower Road, Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 12 December 2024 and could run through until 14 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 16 Oct 2024 at 12:38.
13 and 15 Dec 2024
Last Mile Electricity (formerly Global Utility Connections) are proposing to carry out Utility repair and maintenance works on Alperton Lane, Perivale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 December 2024 and could run through until 15 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Last Mile Electricity (formerly Global Utility Connections) on 23 Oct 2024 at 12:01.
13 and 15 Dec 2024
Last Mile Electricity (formerly Global Utility Connections) are proposing to carry out Utility repair and maintenance works on Alperton Lane, Perivale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 December 2024 and could run through until 15 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Last Mile Electricity (formerly Global Utility Connections) on 24 Oct 2024 at 11:18.
13 and 15 Dec 2024
Last Mile Electricity (formerly Global Utility Connections) are proposing to carry out Utility repair and maintenance works on Alperton Lane, Perivale.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 December 2024 and could run through until 15 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Last Mile Electricity (formerly Global Utility Connections) on 13 Nov 2024 at 13:45.
16 and 19 Dec 2024
Thames Water are proposing to carry out New service connection on Hanbury Road, Acton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 19 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 24 Oct 2024 at 09:16.
16 and 19 Dec 2024
Thames Water are proposing to carry out New service connection on Hanbury Road, Acton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 19 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 24 Oct 2024 at 11:39.
16 and 18 Dec 2024
Thames Water are proposing to carry out Utility asset works on Beaufort Road, Ealing.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 18 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 22 Aug 2024 at 15:28.
17 and 22 Dec 2024
Affinity Water are proposing to carry out Utility asset works on Ealing Road, Northolt.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 December 2024 and could run through until 22 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 10 Oct 2024 at 14:47.
18 and 21 Dec 2024
London Borough Of Harrow were proposing to carry out Highway repair and maintenance works on Pinner Road, North Harrow.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 18 December 2024 and run through until 21 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 22 Oct 2024 at 15:34.
20 Dec 2024 and 20 Jan 2025
London Borough Of Hillingdon are proposing to carry out Highway repair and maintenance works on Barnhill Lane, Hayes.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 December 2024 and could run through until 20 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Hillingdon on 1 Oct 2024 at 07:22.
23 and 31 Dec 2024
Thames Water were proposing to carry out New service connection on Perryfield Way, Colindale, London.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 23 December 2024 and run through until 31 December 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 28 Aug 2024 at 15:48.
24 and 26 Dec 2024
London Borough Of Barnet carried out Highway improvement works on Rectory Lane, Edgware.
These works were categorised as Major.
The road was closed for some or all of the period.
The works were originally planned between 24 Dec 2024 and 26 Dec 2024 and were actually completed on between and . The works impacted the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 18 Oct 2024 at 12:56.
28 Dec 2024 and 6 Jan 2025
Thames Water are proposing to carry out Disconnection or alteration of supply on Rosebank Road, Hanwell.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 December 2024 and could run through until 6 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 10 Oct 2024 at 14:14.
28 Dec 2024 and 29 Mar 2025
Network Rail are proposing to carry out Works for Rail Purposes on Acton Lane, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 December 2024 and could run through until 29 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Network Rail on 10 Oct 2024 at 17:58.
28 Dec 2024 and 29 Mar 2025
Network Rail are proposing to carry out Works for Rail Purposes on Acton Lane, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 December 2024 and could run through until 29 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Network Rail on 15 Oct 2024 at 13:42.
1 and 17 Jan 2025
Scottish Hydro Electric Power Dis were proposing to carry out Utility repair and maintenance works on Bromyard Avenue, Acton.
These works were categorised as Major.
Two-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 1 January 2025 and run through until 17 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Scottish Hydro Electric Power Dis on 7 Nov 2024 at 10:14.
6 and 10 Jan 2025
City Of Westminster are proposing to carry out Highway repair and maintenance works on Tolhurst Drive, Regent's Park, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 10 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by City Of Westminster on 25 Oct 2024 at 17:09.
6 and 10 Jan 2025
City Of Westminster are proposing to carry out Highway repair and maintenance works on Tolhurst Drive, Regent's Park, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 10 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by City Of Westminster on 21 Nov 2024 at 12:39.
6 Jan and 2 Mar 2025
Thames Water are proposing to carry out Statutory Infrastructure Works on Twyford Abbey Road, Park Royal.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 2 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 20 Sep 2024 at 11:30.
6 Jan and 2 Mar 2025
Thames Water are proposing to carry out Statutory Infrastructure Works on Twyford Abbey Road, Park Royal.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 2 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 3 Oct 2024 at 11:39.
6 Jan and 21 Apr 2025
Thames Water are proposing to carry out Utility asset works on Willesden Lane, Willesden, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 21 April 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 25 Nov 2024 at 11:28.
6 Jan and 10 Mar 2025
Thames Water are proposing to carry out Utility asset works on Balmoral Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 10 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 14 Nov 2024 at 20:51.
6 and 17 Jan 2025
T-Mobile (UK) were proposing to carry out Utility repair and maintenance works on The Avenue, Wembley.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 17 January 2025. The works were due to impact the verge only.
This roadwork event was last updated by T-Mobile (UK) on 18 Oct 2024 at 13:15.
6 Jan and 30 Aug 2025
Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Tempelhof Avenue, Cricklewood, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 30 August 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Transport for London (TfL) on 17 Oct 2024 at 11:27.
6 Jan and 30 Aug 2025
Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Tempelhof Avenue, Cricklewood, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 30 August 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Transport for London (TfL) on 11 Nov 2024 at 10:34.
6 Jan and 30 Aug 2025
Transport for London (TfL) are proposing to carry out Highway improvement works on Tilling Road, Cricklewood, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 30 August 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Transport for London (TfL) on 8 Oct 2024 at 09:29.
6 Jan and 30 Aug 2025
Transport for London (TfL) are proposing to carry out Highway improvement works on Tilling Road, Cricklewood, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 30 August 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Transport for London (TfL) on 10 Oct 2024 at 13:12.
6 Jan and 30 Aug 2025
Transport for London (TfL) are proposing to carry out Highway improvement works on Claremont Road, Cricklewood, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 30 August 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Transport for London (TfL) on 8 Oct 2024 at 09:22.
6 Jan and 30 Aug 2025
Transport for London (TfL) are proposing to carry out Highway improvement works on Claremont Road, Cricklewood, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 30 August 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Transport for London (TfL) on 10 Oct 2024 at 13:13.
6 Jan and 17 Mar 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Cool Oak Lane, Colindale, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 17 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 21 Aug 2024 at 09:07.
6 Jan and 17 Mar 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Cool Oak Lane, Colindale, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 17 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 20 Sep 2024 at 09:27.
6 Jan and 17 Mar 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Cool Oak Lane, Colindale, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 17 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 21 Oct 2024 at 16:42.
6 Jan and 17 Mar 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Cool Oak Lane, Colindale, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 17 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 13 Nov 2024 at 13:35.
6 and 10 Jan 2025
Thames Water were proposing to carry out New service connection on Perryfield Way, Colindale, London.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 10 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 23 Sep 2024 at 13:05.
6 and 13 Jan 2025
London Borough Of Harrow are proposing to carry out Highway improvement works on Junction Road, Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 13 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 30 Sep 2024 at 07:50.
6 and 13 Jan 2025
London Borough Of Harrow are proposing to carry out Highway improvement works on Havelock Place, Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 13 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 30 Sep 2024 at 07:43.
6 and 8 Jan 2025
BT are proposing to carry out Utility asset works on Nibthwaite Road, Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 8 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by BT on 21 Nov 2024 at 10:18.
6 Jan and 7 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on Grove Park, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 7 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 14 Oct 2024 at 14:59.
6 Jan and 7 Feb 2025
Cadent Gas were proposing to carry out Utility asset works on The Hyde, Colindale, London.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 7 February 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 27 Sep 2024 at 13:30.
6 Jan and 7 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on Edgware Road, Kingsbury, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 7 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 14 Oct 2024 at 14:59.
6 Jan and 7 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on Grove Park, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 7 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 19 Sep 2024 at 09:52.
6 Jan and 14 Mar 2025
Affinity Water are proposing to carry out Utility asset works on Tewkesbury Gardens, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 14 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 10 Oct 2024 at 17:13.
6 Jan and 14 Mar 2025
Affinity Water are proposing to carry out Utility asset works on Tewkesbury Gardens, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 14 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 20 Nov 2024 at 16:05.
7 and 9 Jan 2025
Thames Water are proposing to carry out Utility asset works on Beaufort Road, Ealing.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 7 January 2025 and could run through until 9 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 28 Oct 2024 at 09:26.
7 Jan and 31 Mar 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Cool Oak Lane, Colindale, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 7 January 2025 and could run through until 31 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 29 Oct 2024 at 08:45.
11 and 18 Jan 2025
T-Mobile (UK) are proposing to carry out Utility repair and maintenance works on Corringham Road, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 January 2025 and could run through until 18 January 2025. The works will impact the verge only.
This roadwork event was last updated by T-Mobile (UK) on 22 Oct 2024 at 14:25.
11 and 18 Jan 2025
T-Mobile (UK) are proposing to carry out Utility repair and maintenance works on Corringham Road, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 January 2025 and could run through until 18 January 2025. The works will impact the verge only.
This roadwork event was last updated by T-Mobile (UK) on 23 Oct 2024 at 15:48.
13 and 15 Jan 2025
Affinity Water are proposing to carry out Utility repair and maintenance works on Sussex Road, Southall.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 15 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Affinity Water on 9 Oct 2024 at 10:51.
13 and 15 Jan 2025
Affinity Water are proposing to carry out Utility repair and maintenance works on Sussex Road, Southall.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 15 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Affinity Water on 14 Nov 2024 at 16:24.
13 and 23 Jan 2025
Cadent Gas are proposing to carry out Utility asset works on Costons Avenue, Greenford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 23 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 25 Nov 2024 at 13:30.
13 and 21 Jan 2025
Thames Water are proposing to carry out New service connection on Dudden Hill Lane, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 21 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 21 Oct 2024 at 13:36.
13 and 21 Jan 2025
Thames Water are proposing to carry out New service connection on Dudden Hill Lane, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 21 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 12 Nov 2024 at 07:31.
13 Jan and 30 May 2025
London Borough Of Brent are proposing to carry out Highway repair and maintenance works on High Road, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 30 May 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Brent on 24 Nov 2024 at 22:17.
13 Jan and 4 Apr 2025
London Borough Of Brent are proposing to carry out Highway repair and maintenance works on Harrow Road, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 4 April 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Brent on 4 Oct 2024 at 10:43.
13 Jan and 30 May 2025
London Borough Of Brent are proposing to carry out Highway repair and maintenance works on Wembley Hill Road, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 30 May 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Brent on 24 Nov 2024 at 22:17.
13 and 24 Jan 2025
Murphy Power Distribution are proposing to carry out Utility asset works on Field End Road, Ruislip.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 24 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Murphy Power Distribution on 18 Sep 2024 at 08:43.
13 and 24 Jan 2025
Murphy Power Distribution are proposing to carry out Utility asset works on Field End Road, Ruislip.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 24 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Murphy Power Distribution on 30 Oct 2024 at 09:44.
13 and 24 Jan 2025
Murphy Power Distribution are proposing to carry out Utility asset works on Field End Road, Ruislip.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 24 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Murphy Power Distribution on 6 Nov 2024 at 07:48.
13 and 17 Jan 2025
London Borough Of Barnet were proposing to carry out Highway improvement works on Leeside Crescent, Golders Green, London.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 13 January 2025 and run through until 17 January 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 24 Oct 2024 at 14:17.
13 and 31 Jan 2025
Thames Water are proposing to carry out Utility repair and maintenance works on Colin Park Road, Colindale, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 31 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 12 Nov 2024 at 15:59.
13 and 15 Jan 2025
Virgin Media were proposing to carry out Utility asset works on Aerodrome Road, Colindale, London.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 13 January 2025 and run through until 15 January 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Virgin Media on 15 Aug 2024 at 08:38.
14 and 17 Jan 2025
Affinity Water are proposing to carry out Utility asset works on Ealing Road, Northolt.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 14 January 2025 and could run through until 17 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 21 Nov 2024 at 16:33.
14 Jan and 31 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Stag Lane, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 14 January 2025 and could run through until 31 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 29 Oct 2024 at 08:16.
16 and 22 Jan 2025
Thames Water are proposing to carry out Disconnection or alteration of supply on Rootes Drive, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 January 2025 and could run through until 22 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 24 Oct 2024 at 11:37.
17 and 20 Jan 2025
City Of Westminster are proposing to carry out Highway repair and maintenance works on Harrow Road, Westbourne, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 January 2025 and could run through until 20 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by City Of Westminster on 24 Jun 2024 at 13:27.
20 Jan and 9 Feb 2025
Thames Water are proposing to carry out Utility repair and maintenance works on Fletcher Road, Chiswick.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 9 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 3 Sep 2024 at 14:07.
20 and 24 Jan 2025
Thames Water are proposing to carry out New service connection on Cherington Road, Hanwell.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 24 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 26 Sep 2024 at 15:29.
20 Jan and 2 Feb 2025
Thames Water are proposing to carry out Utility repair and maintenance works on Creffield Road, Acton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 2 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 13 Nov 2024 at 11:10.
20 Jan and 2 Feb 2025
Thames Water are proposing to carry out Utility repair and maintenance works on Creffield Road, Acton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 2 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 19 Nov 2024 at 12:14.
20 and 23 Jan 2025
Thames Water are proposing to carry out Utility repair and maintenance works on Longfield Avenue, Ealing.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 23 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 29 Oct 2024 at 16:25.
20 and 23 Jan 2025
Affinity Water were proposing to carry out Utility asset works on Eastcote Lane, Northolt.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 20 January 2025 and run through until 23 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 19 Nov 2024 at 12:25.
20 and 24 Jan 2025
Thames Water are proposing to carry out Utility repair and maintenance works on Llanover Road, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 24 January 2025. The works will impact the cycleway only.
This roadwork event was last updated by Thames Water on 14 Oct 2024 at 07:51.
20 and 24 Jan 2025
Thames Water are proposing to carry out Utility repair and maintenance works on Llanover Road, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 24 January 2025. The works will impact the cycleway only.
This roadwork event was last updated by Thames Water on 11 Nov 2024 at 08:38.
20 Jan and 5 Apr 2025
Transport for London (TfL) are proposing to carry out Highway repair and maintenance works on Tempelhof Avenue, Cricklewood, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 5 April 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Transport for London (TfL) on 8 Oct 2024 at 09:22.
20 Jan and 10 Feb 2025
London Borough Of Harrow are proposing to carry out Highway improvement works on Station Road, Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 10 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 20 Nov 2024 at 08:01.
20 and 28 Jan 2025
London Borough Of Harrow are proposing to carry out Highway repair and maintenance works on Pinner Road, North Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 28 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 22 Nov 2024 at 07:21.
24 and 28 Jan 2025
London Borough Of Ealing are proposing to carry out Highway improvement works on Wharncliffe Drive, Southall.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 24 January 2025 and could run through until 28 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Ealing on 8 Nov 2024 at 13:57.
27 Jan and 21 Apr 2025
Thames Water are proposing to carry out Utility asset works on Willesden Lane, Willesden, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 21 April 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 14 Nov 2024 at 20:53.
27 and 31 Jan 2025
Thames Water are proposing to carry out New service connection on Coles Green Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 22 Nov 2024 at 09:13.
27 and 30 Jan 2025
Affinity Water are proposing to carry out Utility repair and maintenance works on Kingsfield Avenue, North Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 30 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Affinity Water on 18 Oct 2024 at 09:48.
28 Jan and 30 Apr 2025
London Borough Of Ealing are proposing to carry out Highway improvement works on Ruislip Road, Northolt.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 28 January 2025 and could run through until 30 April 2025. The works will impact the footway, carriageway, verge, cycleway and footpath.
This roadwork event was last updated by London Borough Of Ealing on 31 Oct 2024 at 16:15.
28 and 31 Jan 2025
Affinity Water are proposing to carry out Utility asset works on Station Road, Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 25 Nov 2024 at 16:02.
29 Jan and 16 Feb 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Claremont Road, Cricklewood, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 29 January 2025 and could run through until 16 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Barnet on 20 Sep 2024 at 13:49.
3 and 7 Feb 2025
Royal Borough Of Kensington And Chelsea are proposing to carry out Highway improvement works on Southam Street, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 7 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Royal Borough Of Kensington And Chelsea on 24 Oct 2024 at 11:26.
3 and 7 Feb 2025
Royal Borough Of Kensington And Chelsea are proposing to carry out Highway improvement works on Southam Street, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 7 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Royal Borough Of Kensington And Chelsea on 30 Oct 2024 at 10:10.
3 and 7 Feb 2025
Royal Borough Of Kensington And Chelsea are proposing to carry out Highway improvement works on Adair Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 7 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Royal Borough Of Kensington And Chelsea on 30 Oct 2024 at 10:10.
3 and 7 Feb 2025
Royal Borough Of Kensington And Chelsea are proposing to carry out Highway improvement works on Adair Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 7 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Royal Borough Of Kensington And Chelsea on 1 Nov 2024 at 15:04.
3 and 7 Feb 2025
Royal Borough Of Kensington And Chelsea are proposing to carry out Highway improvement works on Kensal Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 7 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Royal Borough Of Kensington And Chelsea on 30 Oct 2024 at 10:10.
3 and 7 Feb 2025
Royal Borough Of Kensington And Chelsea are proposing to carry out Highway improvement works on Kensal Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 7 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Royal Borough Of Kensington And Chelsea on 1 Nov 2024 at 15:04.
3 and 5 Feb 2025
Royal Borough Of Kensington And Chelsea are proposing to carry out Highway improvement works on Kensal Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 5 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Royal Borough Of Kensington And Chelsea on 4 Nov 2024 at 15:13.
3 and 14 Feb 2025
Thames Water are proposing to carry out Utility repair and maintenance works on Bowrons Avenue, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 14 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 6 Nov 2024 at 11:02.
3 and 5 Feb 2025
Affinity Water are proposing to carry out Utility repair and maintenance works on Castleton Avenue, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 5 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 3 Nov 2024 at 19:10.
4 and 7 Feb 2025
Affinity Water were proposing to carry out Utility repair and maintenance works on Norval Road, Wembley.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 4 February 2025 and run through until 7 February 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 31 Oct 2024 at 11:23.
4 and 7 Feb 2025
Affinity Water are proposing to carry out Utility repair and maintenance works on Norval Road, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 4 February 2025 and could run through until 7 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 31 Oct 2024 at 23:04.
6 and 27 Feb 2025
Scottish Hydro Electric Power Dis are proposing to carry out Utility repair and maintenance works on Neal Avenue, Southall.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 February 2025 and could run through until 27 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Scottish Hydro Electric Power Dis on 14 Nov 2024 at 14:14.
6 and 27 Feb 2025
Scottish Hydro Electric Power Dis are proposing to carry out Utility repair and maintenance works on Lady Margaret Road, Southall.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 February 2025 and could run through until 27 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Scottish Hydro Electric Power Dis on 22 Nov 2024 at 13:48.
6 and 27 Feb 2025
Scottish Hydro Electric Power Dis are proposing to carry out Utility repair and maintenance works on Lady Margaret Road, Southall.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 February 2025 and could run through until 27 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Scottish Hydro Electric Power Dis on 25 Nov 2024 at 12:50.
7 Feb and 28 Apr 2025
Transport for London (TfL) are proposing to carry out roadworks on West Cross Route, London.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 7 February 2025 and could run through until 28 April 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 5 Jul 2024 at 16:26.
7 and 10 Feb 2025
Network Rail are proposing to carry out Works for Rail Purposes on Eastcote Lane, Northolt.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 7 February 2025 and could run through until 10 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Network Rail on 1 Nov 2024 at 16:55.
7 and 21 Feb 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Claremont Road, Cricklewood, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 7 February 2025 and could run through until 21 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Barnet on 14 Oct 2024 at 15:18.
9 Feb and 13 Mar 2025
London Borough Of Ealing are proposing to carry out Highway improvement works on Park Royal Road, Acton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 February 2025 and could run through until 13 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Ealing on 8 Aug 2024 at 09:49.
10 Feb and 7 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Neasden Lane North, London.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 10 February 2025 and could run through until 7 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 25 Nov 2024 at 12:39.
10 and 12 Feb 2025
Affinity Water are proposing to carry out Utility repair and maintenance works on Blenheim Road, West Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 10 February 2025 and could run through until 12 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 20 Nov 2024 at 10:47.
11 and 13 Feb 2025
Affinity Water are proposing to carry out Utility repair and maintenance works on Alexandra Avenue, Rayners Lane.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 February 2025 and could run through until 13 February 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Affinity Water on 12 Nov 2024 at 08:40.
14 and 17 Feb 2025
Thames Water are proposing to carry out Utility repair and maintenance works on Finchley Road, Frognal And Fitzjohns, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 14 February 2025 and could run through until 17 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 8 Nov 2024 at 12:46.
14 Feb and 7 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Chessington Court, Pinner.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 14 February 2025 and could run through until 7 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 6 Nov 2024 at 14:30.
15 and 25 Feb 2025
London Borough Of Ealing are proposing to carry out Highway improvement works on York Road, Ealing.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 15 February 2025 and could run through until 25 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Ealing on 14 Oct 2024 at 11:31.
15 and 24 Feb 2025
London Borough Of Brent are proposing to carry out Highway repair and maintenance works on Hawkins Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 15 February 2025 and could run through until 24 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Brent on 15 Oct 2024 at 11:10.
15 and 24 Feb 2025
London Borough Of Brent are proposing to carry out Highway repair and maintenance works on Bridge Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 15 February 2025 and could run through until 24 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Brent on 23 Oct 2024 at 09:07.
15 and 21 Feb 2025
Thames Water are proposing to carry out Utility asset works on Tenterden Grove, Hendon, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 15 February 2025 and could run through until 21 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 16 Oct 2024 at 08:03.
15 and 21 Feb 2025
Thames Water are proposing to carry out Utility asset works on Tenterden Grove, Hendon, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 15 February 2025 and could run through until 21 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 22 Oct 2024 at 15:43.
17 and 21 Feb 2025
Thames Water are proposing to carry out New service connection on Carville Crescent, Brentford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 21 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 21 Nov 2024 at 13:37.
17 Feb and 19 May 2025
Transport for London (TfL) are proposing to carry out Highway improvement works on West Cross Route, London.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 19 May 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 31 Oct 2024 at 17:40.
17 Feb and 24 Mar 2025
Thames Water are proposing to carry out Statutory Infrastructure Works on Twyford Abbey Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 24 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 18 Nov 2024 at 08:01.
17 and 19 Feb 2025
Affinity Water are proposing to carry out Utility repair and maintenance works on Clarendon Gardens, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 19 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 23 Oct 2024 at 21:31.
17 Feb and 3 Mar 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Claremont Road, Cricklewood, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 3 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Barnet on 18 Oct 2024 at 13:23.
17 and 28 Feb 2025
Thames Water are proposing to carry out Utility repair and maintenance works on Wentworth Hill, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 28 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 21 Nov 2024 at 16:05.
17 and 23 Feb 2025
Affinity Water are proposing to carry out Utility asset works on Borthwick Road, Colindale, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 23 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 22 Nov 2024 at 14:51.
17 and 23 Feb 2025
Affinity Water are proposing to carry out Utility asset works on Borthwick Road, Colindale, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 23 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 26 Nov 2024 at 16:06.
17 and 23 Feb 2025
Affinity Water are proposing to carry out Utility asset works on West Hendon Broadway, Colindale, London.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 23 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Affinity Water on 26 Sep 2024 at 08:17.
17 and 23 Feb 2025
Affinity Water are proposing to carry out Utility asset works on West Hendon Broadway, Colindale, London.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 23 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Affinity Water on 22 Nov 2024 at 14:58.
17 and 23 Feb 2025
Affinity Water are proposing to carry out Utility asset works on West Hendon Broadway, Colindale, London.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 23 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Affinity Water on 26 Nov 2024 at 16:06.
17 and 21 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on The Chase, Eastcote.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 21 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 8 Oct 2024 at 08:39.
17 and 28 Feb 2025
UK Power Networks Eastern & London are proposing to carry out New service connection on Brockenhurst Gardens, Mill Hill, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 28 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 20 Nov 2024 at 10:51.
18 and 20 Feb 2025
Vodafone are proposing to carry out Remedial works on Caple Road, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 February 2025 and could run through until 20 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Vodafone on 11 Nov 2024 at 16:25.
18 and 21 Feb 2025
Affinity Water are proposing to carry out Utility asset works on Eastcote Lane, Northolt.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 February 2025 and could run through until 21 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 22 Nov 2024 at 07:47.
18 and 20 Feb 2025
London Borough Of Harrow are proposing to carry out Highway improvement works on Rayners Lane, Rayners Lane.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 February 2025 and could run through until 20 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 26 Nov 2024 at 07:30.
18 and 20 Feb 2025
London Borough Of Harrow are proposing to carry out Highway improvement works on The Close, Rayners Lane.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 February 2025 and could run through until 20 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 26 Nov 2024 at 07:39.
19 and 21 Feb 2025
Affinity Water are proposing to carry out Highway repair and maintenance works on Northolt Road, South Harrow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 19 February 2025 and could run through until 21 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Affinity Water on 22 Nov 2024 at 12:28.
21 Feb and 19 May 2025
Transport for London (TfL) are proposing to carry out Highway improvement works on West Cross Route, London.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 February 2025 and could run through until 19 May 2025. The works will impact the carriageway only.
This roadwork event was last updated by Transport for London (TfL) on 31 Oct 2024 at 17:39.
21 and 25 Feb 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Harman Close, Cricklewood, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 February 2025 and could run through until 25 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 31 Oct 2024 at 12:11.
21 and 25 Feb 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Harman Close, Cricklewood, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 February 2025 and could run through until 25 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 18 Nov 2024 at 11:12.
21 and 27 Feb 2025
London Borough Of Barnet are proposing to carry out Highway improvement works on Leeside Crescent, Golders Green, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 February 2025 and could run through until 27 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 31 Oct 2024 at 14:13.
21 and 24 Feb 2025
London Borough Of Harrow are proposing to carry out Highway repair and maintenance works on Kenmore Avenue, Kenton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 February 2025 and could run through until 24 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Harrow on 21 Nov 2024 at 13:48.
24 Feb and 2 Mar 2025
Thames Water were proposing to carry out roadworks on Ponsard Road, London.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 24 February 2025 and run through until 2 March 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 4 Nov 2024 at 12:51.
24 and 28 Feb 2025
UK Power Networks Eastern & London are proposing to carry out New service connection on Clifton Way, Wembley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 28 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 19 Nov 2024 at 04:32.
24 Feb and 7 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Christchurch Avenue, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 7 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 14 Nov 2024 at 17:30.
24 and 28 Feb 2025
BT are proposing to carry out Utility repair and maintenance works on Greenford Road, Sudbury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 28 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by BT on 21 Nov 2024 at 15:55.
24 Feb and 14 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Blackbird Hill, London.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 14 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 25 Nov 2024 at 12:41.
10 Mar 2025
London Borough Of Barnet are carrying out Highway improvement works on Shirehall Lane, Hendon, London.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 24 February 2025 at 00:00 and could run through until 10 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Barnet on 6 Nov 2024 at 09:28.
24 Feb and 14 Mar 2025
Affinity Water are proposing to carry out Utility asset works on Girton Avenue, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 14 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Affinity Water on 10 Oct 2024 at 17:14.
24 Feb and 14 Mar 2025
Affinity Water are proposing to carry out Utility asset works on Girton Avenue, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 14 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Affinity Water on 20 Nov 2024 at 16:05.
24 Feb and 14 Mar 2025
Affinity Water are proposing to carry out Utility asset works on North Way, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 14 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 10 Oct 2024 at 17:14.
24 Feb and 14 Mar 2025
Affinity Water are proposing to carry out Utility asset works on North Way, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 14 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Affinity Water on 20 Nov 2024 at 16:05.
Roadworks Map near to Repton Avenue, WEMBLEY, HA0 3DL
- Any red lines indicate the extent of the works.
- Clicking on the map will re-centre to the selected point.
- Within 1 mile, all roadworks are displayed.
- Within 2-3 miles, standard, urgent and major roadworks are displayed.
- For 3-5 miles, only major roadworks are shown.
- The higher the marker number, the further away the roadworks are from the centre of the postcode.
- Where traffic camera videos or images are shown, no historical versions are retained. Once a new image or video becomes available it overwrites the previous version.
Roadworks Listing near to Repton Avenue, WEMBLEY, HA0 3DL (62 Events)
(Scheduled Dates)
(miles)
(Scheduled: 25 Nov 2024 - 29 Nov 2024)
(Scheduled: 26 Nov 2024 - 28 Nov 2024)
(Scheduled: 26 Nov 2024 - 28 Nov 2024)
(Scheduled: 26 Nov 2024 - 28 Nov 2024)
(Scheduled: 25 Nov 2024 - 28 Nov 2024)
Contains public sector information licensed under the Open Government Licence v3.0.
Traffic camera information is Powered by TfL Open Data