ROADWORKS SUMMARY
Wooded Close, BURY, BL9 6PA
Introduction
View current and future planned roadworks and road closures for Wooded Close, BL9 6PA and the surrounding area.
Our roadwork details are constantly updated and reflect the current situation and we offer both a map view and a listing. We also highlight the major and significant roadworks occuring near to you help you avoid the worst of the delays to your journey.
The roadworks shown below show all current and proposed works during the next 90 days and historical data is recorded since July 2020.
Please note that we re-publish this data and cannot provide any additional information pertaining to a roadwork event. If you require more information, please contact the organisation carrying out the work.
Data are provided by the Department for Transport.
Have we helped today?
If we have helped you today, please consider buying us a quick coffee to keep us going!
Major Roadworks near to Wooded Close, BURY, BL9 6PA
Details of major roadworks, currently in progress or starting soon and resulting in road closures and/or traffic signal management for Wooded Close are shown here covering a 5 mile radius. See further down for details of all roadworks in your area.
4 Jun 2023 and 29 Jun 2025
Electricity North West (NorWeb) are proposing to carry out Utility repair and maintenance works on Gipsy Lane, Castleton North, Rochdale.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 4 June 2023 and could run through until 29 June 2025. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Electricity North West (NorWeb) on 3 Apr 2023 at 14:30.
4 Jun 2023 and 29 Jun 2025
Electricity North West (NorWeb) are proposing to carry out Utility repair and maintenance works on Manchester Road, Sparthbottoms & College Bank, Rochdale.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 4 June 2023 and could run through until 29 June 2025. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Electricity North West (NorWeb) on 3 Apr 2023 at 06:59.
1 Jan 2026
are carrying out Utility repair and maintenance works on Footpath From Nuttall Lane East To Manchester Road Gollinroad, Ramsbottom.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 2 January 2024 at 17:00 and could run through until 1 January 2026. The works will impact the footpath only.
This roadwork event was last updated by on 2 Jan 2024 at 17:06.
29 Nov 2024
Rochdale Borough Council are carrying out Utility asset works on Over Town Lane, Norden North, Rochdale.
These works are categorised as Major.
The works started on 2 April 2024 at 07:30 and could run through until 29 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Rochdale Borough Council on 11 Nov 2024 at 11:09.
29 Nov 2024
Bury Metropolitan Borough Council are carrying out Highway improvement works on Pilsworth Road, Bury.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 22 April 2024 at 09:30 and could run through until 29 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Bury Metropolitan Borough Council on 26 Jul 2024 at 09:10.
Tomorrow
Electricity North West (NorWeb) are proposing to carry out Diversionary works on Rochdale Road East, Heywood East, Heywood.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 30 September 2024 and could run through until 22 November 2024. The works will impact the footway, carriageway and verge.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Electricity North West (NorWeb) on 3 Sep 2024 at 15:22.
9 Oct and 2 Dec 2024
Electricity North West (NorWeb) are proposing to carry out New service connection on Kearsley Road, Radcliffe.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 9 October 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Electricity North West (NorWeb) on 31 Jul 2024 at 13:48.
Tomorrow
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Alfred Street, Bury.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 14 October 2024 and could run through until 22 November 2024. The works will impact the carriageway only.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Bury Metropolitan Borough Council on 20 May 2024 at 06:51.
Tomorrow
Cadent Gas are proposing to carry out Utility asset works on Bury New Road, Radcliffe.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 17 October 2024 and could run through until 22 November 2024. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Cadent Gas on 31 Jul 2024 at 15:12.
20 Oct 2024 and 17 Oct 2025
Bury Metropolitan Borough Council are proposing to carry out Section 58 on Spring Lane, Radcliffe.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 20 October 2024 and could run through until 17 October 2025. The works will impact the footway, carriageway and verge.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Bury Metropolitan Borough Council on 31 Jul 2024 at 14:06.
21 Oct and 2 Dec 2024
Electricity North West (NorWeb) were proposing to carry out Diversionary works on Hareshill Road, Hopwood East & Birch, Heywood.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 21 October 2024 and run through until 2 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 3 Oct 2024 at 09:14.
Tomorrow
Electricity North West (NorWeb) were proposing to carry out Diversionary works on Rochdale Road East, Heywood East, Heywood.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 21 October 2024 and run through until 22 November 2024. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by Electricity North West (NorWeb) on 17 Oct 2024 at 14:17.
2 Dec 2024
Electricity North West (NorWeb) are carrying out Diversionary works on Rochdale Road East, Heywood East, Heywood.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 30 October 2024 at 08:00 and could run through until 2 December 2024. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Electricity North West (NorWeb) on 19 Nov 2024 at 10:50.
Today
Bolton Metropolitan Borough Council are carrying out Highway repair and maintenance works on Bradshaw Road, Bolton.
These works are categorised as Major.
The works started on 30 October 2024 at 10:30 and could run through until 21 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Bolton Metropolitan Borough Council on 13 Nov 2024 at 08:49.
8 and 28 Nov 2024
Electricity North West (NorWeb) are proposing to carry out Diversionary works on Birch Street, Bury.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 8 November 2024 and could run through until 28 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 21 Aug 2024 at 14:26.
Tomorrow
Electricity North West (NorWeb) were proposing to carry out Diversionary works on Kenyon Street, Bury.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 11 November 2024 and run through until 22 November 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 11 Sep 2024 at 13:50.
11 and 29 Nov 2024
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Helmshore Road, Ramsbottom.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 14 Aug 2024 at 09:19.
Tomorrow
Electricity North West (NorWeb) are proposing to carry out Diversionary works on Hornby Street, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 22 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 4 Sep 2024 at 15:04.
Tomorrow
Electricity North West (NorWeb) are proposing to carry out Diversionary works on Brook Street, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 22 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 4 Sep 2024 at 15:02.
13 Dec 2024
Bury Metropolitan Borough Council are carrying out Highway improvement works on Ashbourne Grove, Radcliffe.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 8 November 2024 at 08:24 and could run through until 13 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 21 Nov 2024 at 09:38.
13 Dec 2024
Bury Metropolitan Borough Council are carrying out Highway improvement works on Newlands Avenue, Radcliffe.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 8 November 2024 at 08:34 and could run through until 13 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 21 Nov 2024 at 10:02.
11 and 29 Nov 2024
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Kenmore Road, Whitefield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 4 Sep 2024 at 14:57.
14 Nov and 18 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Market Street, Bury.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 14 November 2024 and could run through until 18 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 4 Sep 2024 at 14:49.
14 Nov and 18 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Angouleme Way, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 14 November 2024 and could run through until 18 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 4 Sep 2024 at 14:47.
14 Nov and 18 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Angouleme Way, Bury.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 14 November 2024 and could run through until 18 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 6 Sep 2024 at 15:17.
15 Nov and 19 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Murray Road, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 15 November 2024 and could run through until 19 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 4 Sep 2024 at 14:50.
18 Nov and 20 Dec 2024
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Parkhills Road, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 14 May 2024 at 13:54.
2 Dec 2024
United Utilities Water (formerly North West Water) are carrying out Utility repair and maintenance works on Outwood Road, Radcliffe.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 19 November 2024 at 11:03 and could run through until 2 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by United Utilities Water (formerly North West Water) on 19 Nov 2024 at 13:49.
25 Nov and 20 Dec 2024
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Alfred Street, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Bury Metropolitan Borough Council on 1 Oct 2024 at 10:35.
25 and 29 Nov 2024
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Bond Street, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 15 Nov 2024 at 14:42.
25 and 29 Nov 2024
United Utilities Water (formerly North West Water) are proposing to carry out Utility asset works on Maple Avenue, Whitefield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by United Utilities Water (formerly North West Water) on 15 Nov 2024 at 14:04.
25 Nov and 20 Dec 2024
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Kenmore Road, Whitefield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 21 Nov 2024 at 09:44.
2 and 20 Dec 2024
Electricity North West (NorWeb) are proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 20 Nov 2024 at 08:27.
2 and 20 Dec 2024
Electricity North West (NorWeb) are proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 13 Nov 2024 at 12:55.
2 and 20 Dec 2024
Electricity North West (NorWeb) were proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 20 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 13 Nov 2024 at 11:01.
2 and 20 Dec 2024
Electricity North West (NorWeb) are proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 13 Nov 2024 at 12:56.
2 and 20 Dec 2024
Electricity North West (NorWeb) were proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 20 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 13 Nov 2024 at 10:56.
2 and 20 Dec 2024
Electricity North West (NorWeb) are proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 20 Nov 2024 at 08:32.
2 and 20 Dec 2024
Electricity North West (NorWeb) are proposing to carry out Remedial works on Langley Lane, Langley North And West, Middleton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 13 Nov 2024 at 12:41.
2 and 20 Dec 2024
Rochdale Borough Council are proposing to carry out Section 50 on Tower Street, Heywood West And Central, Heywood.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Rochdale Borough Council on 22 Oct 2024 at 11:34.
3 and 9 Dec 2024
Electricity North West (NorWeb) are proposing to carry out New service connection on George Street, Whitefield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 December 2024 and could run through until 9 December 2024. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Electricity North West (NorWeb) on 13 Sep 2024 at 14:06.
4 and 12 Dec 2024
Electricity North West (NorWeb) are proposing to carry out Diversionary works on Kenyon Street, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 4 December 2024 and could run through until 12 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 19 Sep 2024 at 12:45.
4 and 24 Dec 2024
Electricity North West (NorWeb) are proposing to carry out Diversionary works on Birch Street, Bury.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 4 December 2024 and could run through until 24 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 18 Sep 2024 at 16:02.
9 and 13 Dec 2024
Rochdale Borough Council are proposing to carry out Remedial works on Queens Park Road, Back O Th Moss & Ashworth, Heywood.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 13 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Rochdale Borough Council on 12 Nov 2024 at 09:43.
9 and 13 Dec 2024
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Rhiwlas Drive, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 13 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 18 Nov 2024 at 12:31.
11 and 13 Dec 2024
BT are proposing to carry out Utility repair and maintenance works on Ainsworth Road, Radcliffe.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 December 2024 and could run through until 13 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by BT on 2 Oct 2024 at 12:15.
13 and 19 Dec 2024
Electricity North West (NorWeb) are proposing to carry out New service connection on Firwood Grove, Bolton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 December 2024 and could run through until 19 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 20 Sep 2024 at 15:13.
16 Dec 2024 and 14 Feb 2025
Bury Metropolitan Borough Council are proposing to carry out Highway repair and maintenance works on Rowlands Road, Ramsbottom.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 14 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 16 Oct 2024 at 14:11.
16 and 20 Dec 2024
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Killon Street, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 14 May 2024 at 13:47.
16 and 27 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Mile Lane, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 27 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 19 Sep 2024 at 12:00.
16 and 27 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Mile Lane, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 27 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 24 Sep 2024 at 10:38.
16 and 23 Dec 2024
Electricity North West (NorWeb) are proposing to carry out New service connection on Hurst Street, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 23 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 12 Nov 2024 at 11:58.
16 and 26 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Mile Lane, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 26 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 26 Sep 2024 at 11:33.
16 and 26 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Mile Lane, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 26 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 30 Sep 2024 at 08:29.
16 and 23 Dec 2024
Electricity North West (NorWeb) are proposing to carry out New service connection on Hurst Street, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 23 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 18 Oct 2024 at 10:58.
30 Dec 2024 and 3 Jan 2025
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Bond Street, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 30 December 2024 and could run through until 3 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 4 Nov 2024 at 15:15.
30 Dec 2024 and 10 Jan 2025
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Gigg Lane, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 30 December 2024 and could run through until 10 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Bury Metropolitan Borough Council on 7 Oct 2024 at 12:30.
30 Dec 2024 and 3 Jan 2025
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Rhiwlas Drive, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 30 December 2024 and could run through until 3 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 4 Nov 2024 at 15:16.
30 Dec 2024 and 3 Jan 2025
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Spring Street, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 30 December 2024 and could run through until 3 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 1 Nov 2024 at 13:57.
6 and 31 Jan 2025
Electricity North West (NorWeb) are proposing to carry out Utility asset works on Gipsy Lane, Castleton North, Rochdale.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 31 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Electricity North West (NorWeb) on 22 Oct 2024 at 09:10.
6 Jan and 25 Apr 2025
Rochdale Borough Council were proposing to carry out Highway improvement works on Bamford Road, Back O Th Moss & Ashworth, Heywood.
These works were categorised as Major.
Two-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 25 April 2025. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by Rochdale Borough Council on 8 Nov 2024 at 13:23.
6 Jan and 25 Apr 2025
Rochdale Borough Council were proposing to carry out Highway improvement works on West Starkey Street, Back O Th Moss & Ashworth, Heywood.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 25 April 2025. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by Rochdale Borough Council on 8 Nov 2024 at 13:26.
6 Jan and 25 Apr 2025
Rochdale Borough Council were proposing to carry out Highway improvement works on Starkey Street, Back O Th Moss & Ashworth, Heywood.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 25 April 2025. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by Rochdale Borough Council on 8 Nov 2024 at 13:25.
6 Jan and 14 Feb 2025
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Alfred Street, Bury.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 14 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Bury Metropolitan Borough Council on 1 Oct 2024 at 11:50.
6 and 31 Jan 2025
Bury Metropolitan Borough Council are proposing to carry out Section 50 on Radcliffe Moor Road, Radcliffe.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Bury Metropolitan Borough Council on 19 Nov 2024 at 15:04.
13 Jan and 10 Mar 2025
Bury Metropolitan Borough Council are proposing to carry out Highway repair and maintenance works on Rowlands Road, Ramsbottom.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 10 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 28 Oct 2024 at 11:10.
15 and 22 Jan 2025
Electricity North West (NorWeb) are proposing to carry out New service connection on Hurst Street, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 15 January 2025 and could run through until 22 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 5 Nov 2024 at 15:52.
20 and 24 Jan 2025
Electricity North West (NorWeb) are proposing to carry out Utility repair and maintenance works on Silver Street, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 24 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 15 Nov 2024 at 15:51.
3 and 28 Feb 2025
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Helmshore Road, Ramsbottom.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 28 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 21 Nov 2024 at 09:26.
4 and 10 Feb 2025
Electricity North West (NorWeb) are proposing to carry out Utility repair and maintenance works on Silver Street, Bury.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 4 February 2025 and could run through until 10 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Electricity North West (NorWeb) on 15 Nov 2024 at 11:57.
4 and 6 Feb 2025
United Utilities Water (formerly North West Water) are proposing to carry out New service connection on Lever Street, Little Lever, Bolton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 4 February 2025 and could run through until 6 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by United Utilities Water (formerly North West Water) on 12 Nov 2024 at 12:56.
10 Feb and 21 Mar 2025
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Alfred Street, Bury.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 10 February 2025 and could run through until 21 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 1 Oct 2024 at 11:57.
10 Feb and 21 Mar 2025
Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Alfred Street, Bury.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 10 February 2025 and could run through until 21 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Bury Metropolitan Borough Council on 1 Oct 2024 at 10:51.
12 and 18 Feb 2025
United Utilities Water (formerly North West Water) are proposing to carry out Utility asset works on Maple Avenue, Whitefield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 12 February 2025 and could run through until 18 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by United Utilities Water (formerly North West Water) on 13 Nov 2024 at 13:46.
Roadworks Map near to Wooded Close, BURY, BL9 6PA
- Any red lines indicate the extent of the works.
- Clicking on the map will re-centre to the selected point.
- Within 1 mile, all roadworks are displayed.
- Within 2-3 miles, standard, urgent and major roadworks are displayed.
- For 3-5 miles, only major roadworks are shown.
- The higher the marker number, the further away the roadworks are from the centre of the postcode.
- Where traffic camera videos or images are shown, no historical versions are retained. Once a new image or video becomes available it overwrites the previous version.
Roadworks Listing near to Wooded Close, BURY, BL9 6PA (19 Events)
(Scheduled Dates)
(miles)
(Scheduled: 19 Nov 2024 - 25 Nov 2024)
(Scheduled: 21 Nov 2024 - 27 Nov 2024)
Contains public sector information licensed under the Open Government Licence v3.0.