ROADWORK EVENT SUMMARY
Alfred Street, Bury between 10 Feb and 21 Mar 2025

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Alfred Street, Bury

Bury Metropolitan Borough Council are proposing to carry out Highway improvement works on Alfred Street, Bury.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 10 February 2025 and could run through until 21 March 2025. The works will impact the carriageway only.

The information for these works was last updated by Bury Metropolitan Borough Council on 1 October 2024 at 10:51.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Alfred Street, Bury

Works Details

WORKS PLANNED
Major
Bury Metropolitan Borough Council logo
These works are handled by:
Bury Metropolitan Borough Council
Bury Metropolitan Borough Council logo
Local Authority:
Bury Metropolitan Borough Council
Works Reference BJ004HS618-006E-2
Permit Number 02
Place Name Alfred Street
Bury
Proposed Start 10 Feb 2025
Proposed End 21 Mar 2025
Actual Start
Actual End
Traffic Management Two-way signals
Impact Carriageway
Coordinates
Lat, Lon
53.583286
-2.285875
Last Updated 1 Oct 2024 10:51
Works History for Activity BJ004HS618-006E-2 (Alfred Street, Bury)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
12 Jul 2024
13:45
Permit Submitted
2 Sep 2024
10:00
11 Oct 2024
18:30
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Jul 2024
15:24
Permit Granted
2 Sep 2024
10:00
11 Oct 2024
18:30
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
1 Oct 2024
11:51
Permit Alteration Granted
10 Feb 2025
09:00
21 Mar 2025
17:30
Planned

Works Permits for Alfred Street, Bury

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT08a (Traffic management request)

For the activities hereby permitted, it is a condition of this permit that works, or the relevant part of the activity, shall only take place when the following traffic management is deployed by use of x (where x determines type of control i.e. portable signals, stop/go boards etc.)

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.