The roadworks shown below show all current and proposed works during the next 90 days and historical data is recorded since July 2020.
Please note that we re-publish this data and cannot provide any additional information pertaining to a roadwork event. If you require more information, please contact the organisation carrying out the work.
Data are provided by the Department for Transport.
Have we helped today?
If we have helped you today, please consider buying us a quick coffee to keep us going!
Major Roadworks near to Alvechurch Highway, BROMSGROVE, B60 1NY
Details of major roadworks, currently in progress or starting soon and resulting in road closures and/or traffic signal management for Alvechurch Highway are shown here covering a 5 mile radius. See further down for details of all roadworks in your area.
19 Aug 2025
Worcestershire County Council are carrying out Highway improvement works on Redditch Road, Stoke Heath.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 15 January 2024 at 07:00 and could run through until 19 August 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 16 Jan 2024 at 08:49.
31 May 2026
Worcestershire County Council are carrying out Highway improvement works on Redditch Road, Stoke Heath.
The works started on 22 January 2024 at 08:00 and could run through until 31 May 2026. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 5 Apr 2024 at 15:48.
31 May 2026
Worcestershire County Council are carrying out Highway improvement works on Bromsgrove Eastern Bypass, Bromsgrove.
The works started on 22 January 2024 at 08:00 and could run through until 31 May 2026. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 4 Apr 2024 at 13:06.
31 May 2026
Worcestershire County Council are carrying out Highway improvement works on Bromsgrove Highway, Bromsgrove.
The works started on 22 January 2024 at 08:00 and could run through until 31 May 2026. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 4 Apr 2024 at 13:13.
20 Feb 2026
Worcestershire County Council are carrying out Highway improvement works on Bromsgrove Eastern Bypass, Bromsgrove.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 29 January 2024 at 07:30 and could run through until 20 February 2026. The works will impact the verge only.
This roadwork event was last updated by Worcestershire County Council on 30 Jan 2024 at 09:22.
8 Oct 2025
Worcestershire County Council are carrying out Highway improvement works on Stratford Road, Bromsgrove.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 24 June 2024 at 07:30 and could run through until 8 October 2025. The works will impact the verge only.
This roadwork event was last updated by Worcestershire County Council on 10 Sep 2024 at 15:47.
10 Aug 2024 and 21 May 2025
Birmingham City Council are proposing to carry out Highway improvement works on Senneleys Park Road, Birmingham.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 10 August 2024 and could run through until 21 May 2025. The works will impact the carriageway only.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Birmingham City Council on 24 Jul 2024 at 10:55.
1 Oct 2024 and 31 Mar 2025
Worcestershire County Council are proposing to carry out Highway improvement works on Bromsgrove Eastern Bypass, Bromsgrove.
These works are categorised as Major.
The works will start on or after 1 October 2024 and could run through until 31 March 2025. The works will impact the carriageway only.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Worcestershire County Council on 13 Sep 2024 at 16:59.
31 Mar 2025
Worcestershire County Council are carrying out Highway improvement works on Bromsgrove Eastern Bypass, Bromsgrove.
These works are categorised as Major.
The works started on 1 October 2024 at 07:30 and could run through until 31 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 1 Oct 2024 at 13:14.
8 Oct 2024 and 25 Apr 2025
Worcestershire County Council were proposing to carry out Highway repair and maintenance works on New Road, Bromsgrove.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 8 October 2024 and run through until 25 April 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 8 Oct 2024 at 08:52.
8 Oct 2024 and 25 Apr 2025
Worcestershire County Council were proposing to carry out Highway repair and maintenance works on Bromsgrove Eastern Bypass, Bromsgrove.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 8 October 2024 and run through until 25 April 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 8 Oct 2024 at 08:52.
15 Oct 2024 and 15 Oct 2025
Birmingham City Council are proposing to carry out Highway improvement works on Pembridge Close, Birmingham.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 15 October 2024 and could run through until 15 October 2025. The works will impact the carriageway only.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Birmingham City Council on 12 Jul 2024 at 12:37.
18 Oct 2024 and 18 Jul 2026
Worcestershire County Council were proposing to carry out Highway improvement works on Stoke Road, Bromsgrove.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 18 October 2024 and run through until 18 July 2026. The works were due to impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 11 Sep 2024 at 09:11.
22 Dec 2024
Cadent Gas are carrying out Utility asset works on Perryfields Road, Bromsgrove.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 28 October 2024 at 08:00 and could run through until 22 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 28 Oct 2024 at 08:56.
20 Dec 2024
Cadent Gas are carrying out Utility asset works on Blackwell Road, Barnt Green.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 30 October 2024 at 08:00 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 22 Nov 2024 at 14:19.
28 Oct 2024 and 17 Jan 2025
Cadent Gas are proposing to carry out Utility asset works on Aqueduct Lane, Alvechurch.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 October 2024 and could run through until 17 January 2025. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Cadent Gas on 8 Mar 2024 at 11:30.
1 Nov 2024 and 6 Apr 2025
Worcestershire County Council were proposing to carry out Highway improvement works on Bromsgrove Eastern Bypass, Bromsgrove.
These works were categorised as Major.
A lane was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 1 November 2024 and run through until 6 April 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 3 Oct 2024 at 09:57.
4 Nov 2024 and 7 Feb 2025
Cadent Gas were proposing to carry out Utility asset works on Middleton Hall Road, Birmingham.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 4 November 2024 and run through until 7 February 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 20 Aug 2024 at 15:15.
4 Nov 2024 and 24 Jan 2025
Cadent Gas were proposing to carry out Utility asset works on Pershore Road, Bournville, Birmingham.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 4 November 2024 and run through until 24 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 20 Aug 2024 at 15:16.
4 Nov 2024 and 7 Mar 2025
Cadent Gas were proposing to carry out Utility asset works on Pershore Road South, Birmingham.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 4 November 2024 and run through until 7 March 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 20 Aug 2024 at 15:14.
4 Nov 2024 and 24 Jan 2025
Cadent Gas were proposing to carry out Utility asset works on Watford Road, Birmingham.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 4 November 2024 and run through until 24 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 20 Aug 2024 at 15:17.
Today
Western Power Distribution (West Midlands) are carrying out Utility asset works on Brightstone Road, Birmingham.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 22 November 2024 at 09:00 and could run through until 12 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Western Power Distribution (West Midlands) on 29 Nov 2024 at 11:20.
24 Nov 2024 and 31 Oct 2025
Worcestershire County Council were proposing to carry out Highway repair and maintenance works on Bromsgrove Eastern Bypass, Bromsgrove.
These works were categorised as Major.
A lane was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 24 November 2024 and run through until 31 October 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 19 Nov 2024 at 10:06.
25 Nov 2024 and 31 Oct 2025
Worcestershire County Council were proposing to carry out Highway repair and maintenance works on Stoke Road, Bromsgrove.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 25 November 2024 and run through until 31 October 2025. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by Worcestershire County Council on 19 Nov 2024 at 10:35.
25 Nov 2024 and 31 Oct 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Bromsgrove Eastern Bypass, Bromsgrove.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 31 October 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 21 Nov 2024 at 13:22.
31 Oct 2025
Worcestershire County Council are carrying out Highway repair and maintenance works on Bromsgrove Eastern Bypass, Bromsgrove.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 25 November 2024 at 07:30 and could run through until 31 October 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 25 Nov 2024 at 09:17.
Tomorrow
Worcestershire County Council are carrying out Highway improvement works on Bromsgrove Eastern Bypass, Bromsgrove.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 28 November 2024 at 09:30 and could run through until 13 December 2024. The works will impact the verge only.
This roadwork event was last updated by Worcestershire County Council on 2 Dec 2024 at 10:07.
2 and 20 Dec 2024
Severn Trent Water were proposing to carry out Utility asset works on Rocky Lane, Bournheath.
These works were categorised as Major.
Two-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 2 December 2024 and run through until 20 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 28 Oct 2024 at 14:36.
3 and 20 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Shepley Road, Barnt Green.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 3 December 2024 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 29 Nov 2024 at 14:00.
20 Dec 2024
Cadent Gas are carrying out Utility asset works on Shepley Road, Barnt Green.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 3 December 2024 at 11:30 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 3 Dec 2024 at 13:00.
24 Dec 2024
Worcestershire County Council are carrying out Highway repair and maintenance works on Holy Cross Green, Holy Cross.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 10 December 2024 at 07:30 and could run through until 24 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 10 Dec 2024 at 08:57.
Wednesday
Cadent Gas are carrying out Utility repair and maintenance works on Aversley Road, Birmingham.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 5 December 2024 at 07:52 and could run through until 18 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 10 Dec 2024 at 15:18.
Wednesday
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Spadesbourne Road, Lickey End.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 18 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 19 Sep 2024 at 13:57.
Tomorrow
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Hewell Lane, Barnt Green.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 13 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 1 Aug 2024 at 11:53.
Tomorrow
Worcestershire County Council were proposing to carry out Highway repair and maintenance works on Hewell Lane, Barnt Green.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 9 December 2024 and run through until 13 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 20 Sep 2024 at 10:20.
Today
Severn Trent Water are proposing to carry out New service connection on Dordale Road, Bournheath.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 10 December 2024 and could run through until 12 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 20 Sep 2024 at 14:47.
Tomorrow
Western Power Distribution (West Midlands) were proposing to carry out New service connection on Ednall Lane, Bromsgrove.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 11 December 2024 and run through until 13 December 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Western Power Distribution (West Midlands) on 17 Sep 2024 at 15:52.
Tomorrow
Western Power Distribution (West Midlands) are proposing to carry out New service connection on Ednall Lane, Bromsgrove.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 December 2024 and could run through until 13 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Western Power Distribution (West Midlands) on 10 Sep 2024 at 14:51.
Tuesday
Cadent Gas are carrying out Utility repair and maintenance works on Twatling Road, Barnt Green.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 11 December 2024 at 10:28 and could run through until 17 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 11 Dec 2024 at 14:25.
16 and 20 Dec 2024
Cadent Gas are proposing to carry out Disconnection or alteration of supply on School Lane, Alvechurch.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 24 Sep 2024 at 15:40.
16 and 20 Dec 2024
Cadent Gas are proposing to carry out Disconnection or alteration of supply on School Lane, Alvechurch.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 25 Sep 2024 at 11:57.
27 Dec 2024 and 17 Jan 2025
Cadent Gas were proposing to carry out Utility asset works on Bant Mill Road, Bromsgrove.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 27 December 2024 and run through until 17 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 1 Oct 2024 at 08:48.
6 and 15 Jan 2025
Worcestershire County Council were proposing to carry out Highway repair and maintenance works on Charford Road, Bromsgrove.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 15 January 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 5 Dec 2024 at 08:17.
6 Jan 2025 and 6 Feb 2026
Worcestershire County Council were proposing to carry out Highway improvement works on Bromsgrove Eastern Bypass, Bromsgrove.
These works were categorised as Major.
A lane was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 6 February 2026. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by Worcestershire County Council on 8 Nov 2024 at 13:14.
6 Jan 2025 and 15 Jan 2026
Worcestershire County Council are proposing to carry out Highway improvement works on Bromsgrove Eastern Bypass, Bromsgrove.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 15 January 2026. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Worcestershire County Council on 21 Nov 2024 at 13:47.
6 Jan 2025 and 6 Feb 2026
Worcestershire County Council are proposing to carry out Highway improvement works on Bromsgrove Eastern Bypass, Bromsgrove.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 6 February 2026. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Worcestershire County Council on 21 Nov 2024 at 15:55.
6 and 15 Jan 2025
Worcestershire County Council are proposing to carry out Highway improvement works on New Road, Bromsgrove.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 15 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 25 Oct 2024 at 14:37.
6 Jan and 25 Mar 2025
Worcestershire County Council are proposing to carry out Section 50 on Perryfields Road, Bromsgrove.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 25 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Worcestershire County Council on 30 Oct 2024 at 15:20.
6 Jan and 9 Apr 2025
Worcestershire County Council are proposing to carry out Section 50 on Perryfields Road, Bromsgrove.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 9 April 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Worcestershire County Council on 20 Nov 2024 at 15:54.
6 and 24 Jan 2025
Severn Trent Water were proposing to carry out Utility asset works on Rocky Lane, Bournheath.
These works were categorised as Major.
Two-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 6 January 2025 and run through until 24 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Severn Trent Water on 11 Nov 2024 at 15:41.
6 and 8 Jan 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Yarnold Lane, Dodford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 8 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 10 Oct 2024 at 08:17.
6 and 8 Jan 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Yarnold Lane, Dodford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 8 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 14 Oct 2024 at 14:39.
6 and 8 Jan 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Headley Heath Lane, Headley Heath.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 8 January 2025. The works will impact the verge only.
This roadwork event was last updated by Severn Trent Water on 10 Oct 2024 at 08:27.
6 and 8 Jan 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Headley Heath Lane, Headley Heath.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 8 January 2025. The works will impact the verge only.
This roadwork event was last updated by Severn Trent Water on 14 Oct 2024 at 14:36.
6 and 8 Jan 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Coleys Lane, Birmingham.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 8 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 16 Oct 2024 at 11:20.
6 and 8 Jan 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Coleys Lane, Birmingham.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 8 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 17 Oct 2024 at 11:20.
8 and 10 Jan 2025
Severn Trent Water were proposing to carry out Utility repair and maintenance works on Brookhouse Road, Barnt Green.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 8 January 2025 and run through until 10 January 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 16 Sep 2024 at 11:13.
8 and 10 Jan 2025
Severn Trent Water were proposing to carry out Utility repair and maintenance works on Icknield Street, Headley Heath.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 8 January 2025 and run through until 10 January 2025. The works were due to impact the verge only.
This roadwork event was last updated by Severn Trent Water on 11 Oct 2024 at 15:03.
13 and 17 Jan 2025
Worcestershire County Council were proposing to carry out Highway improvement works on Bromsgrove Eastern Bypass, Bromsgrove.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 13 January 2025 and run through until 17 January 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 15 Nov 2024 at 08:15.
13 Jan and 7 Mar 2025
BT are proposing to carry out Utility asset works on Albert Road, Bromsgrove.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 7 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by BT on 20 Nov 2024 at 11:13.
13 Jan and 13 Jun 2025
Worcestershire County Council were proposing to carry out Highway improvement works on New Road, Bromsgrove.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 13 January 2025 and run through until 13 June 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Worcestershire County Council on 20 Nov 2024 at 14:36.
13 Jan and 13 Jun 2025
Worcestershire County Council were proposing to carry out Highway improvement works on Bant Mill Road, Bromsgrove.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 13 January 2025 and run through until 13 June 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Worcestershire County Council on 20 Nov 2024 at 14:38.
13 Jan and 13 Jun 2025
Worcestershire County Council were proposing to carry out Highway improvement works on Fordhouse Road, Bromsgrove.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 13 January 2025 and run through until 13 June 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Worcestershire County Council on 20 Nov 2024 at 14:37.
13 and 17 Jan 2025
Worcestershire County Council were proposing to carry out Highway repair and maintenance works on Callow Hill Road, Alvechurch.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 13 January 2025 and run through until 17 January 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 27 Sep 2024 at 14:02.
14 and 16 Jan 2025
Severn Trent Water are proposing to carry out New service connection on Watery Lane, Weatheroak Hill.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 14 January 2025 and could run through until 16 January 2025. The works will impact the carriageway and verge.
This roadwork event was last updated by Severn Trent Water on 15 Oct 2024 at 14:19.
14 and 16 Jan 2025
Severn Trent Water are proposing to carry out New service connection on Watery Lane, Weatheroak Hill.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 14 January 2025 and could run through until 16 January 2025. The works will impact the carriageway and verge.
This roadwork event was last updated by Severn Trent Water on 16 Oct 2024 at 11:49.
15 and 17 Jan 2025
Severn Trent Water were proposing to carry out Utility repair and maintenance works on Victoria Road, Bromsgrove.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 15 January 2025 and run through until 17 January 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 15 Oct 2024 at 15:54.
16 and 24 Jan 2025
Worcestershire County Council are proposing to carry out Highway improvement works on New Road, Bromsgrove.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 January 2025 and could run through until 24 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 29 Oct 2024 at 14:30.
16 and 24 Jan 2025
Worcestershire County Council are proposing to carry out Highway improvement works on New Road, Bromsgrove.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 January 2025 and could run through until 24 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 4 Nov 2024 at 12:33.
20 Jan and 7 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on Churchfields, Bromsgrove.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 7 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 10 Jun 2024 at 08:23.
27 Jan and 21 Apr 2025
BT were proposing to carry out Utility asset works on Albert Road, Bromsgrove.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 27 January 2025 and run through until 21 April 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by BT on 6 Nov 2024 at 10:08.
27 and 31 Jan 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Callow Hill Road, Alvechurch.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 31 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 10 Oct 2024 at 11:14.
27 and 31 Jan 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Callow Hill Road, Alvechurch.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 31 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 14 Oct 2024 at 14:35.
27 and 29 Jan 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Farren Road, Birmingham.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 29 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Severn Trent Water on 29 Oct 2024 at 08:45.
29 and 31 Jan 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Chapel Lane, Alvechurch.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 29 January 2025 and could run through until 31 January 2025. The works will impact the verge only.
This roadwork event was last updated by Worcestershire County Council on 25 Oct 2024 at 10:52.
29 and 31 Jan 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Chapel Lane, Alvechurch.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 29 January 2025 and could run through until 31 January 2025. The works will impact the verge only.
This roadwork event was last updated by Worcestershire County Council on 28 Oct 2024 at 10:19.
29 Jan and 10 Feb 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Twatling Road, Barnt Green.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 29 January 2025 and could run through until 10 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 3 Sep 2024 at 14:35.
3 and 28 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on Churchfields Road, Bromsgrove.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 28 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 10 Jun 2024 at 08:22.
3 and 14 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on Hewell Lane, Barnt Green.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 14 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 25 Nov 2024 at 10:22.
3 and 7 Feb 2025
Worcestershire County Council were proposing to carry out Highway repair and maintenance works on Hewell Lane, Barnt Green.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 3 February 2025 and run through until 7 February 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 7 Oct 2024 at 12:06.
3 Feb and 11 Apr 2025
Cadent Gas were proposing to carry out Utility asset works on Stourbridge Road, Catshill.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 3 February 2025 and run through until 11 April 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 10 Dec 2024 at 14:24.
3 and 5 Feb 2025
Severn Trent Water were proposing to carry out Utility repair and maintenance works on Icknield Street, Headley Heath.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 3 February 2025 and run through until 5 February 2025. The works were due to impact the verge only.
This roadwork event was last updated by Severn Trent Water on 14 Nov 2024 at 15:19.
3 and 5 Feb 2025
Cadent Gas are proposing to carry out Remedial works on Holy Cross Lane, Holy Cross.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 5 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 12 Dec 2024 at 12:49.
10 Feb and 5 May 2025
BT were proposing to carry out Utility asset works on Albert Road, Bromsgrove.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 10 February 2025 and run through until 5 May 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by BT on 11 Nov 2024 at 11:35.
10 and 12 Feb 2025
Severn Trent Water were proposing to carry out Utility repair and maintenance works on Greenhill, Burcot.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 10 February 2025 and run through until 12 February 2025. The works were due to impact the verge only.
This roadwork event was last updated by Severn Trent Water on 11 Nov 2024 at 15:20.
10 and 12 Feb 2025
Severn Trent Water were proposing to carry out Utility repair and maintenance works on Walton Road, Bromsgrove.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 10 February 2025 and run through until 12 February 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 6 Nov 2024 at 08:24.
10 and 12 Feb 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Frankley Lane, Birmingham.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 10 February 2025 and could run through until 12 February 2025. The works will impact the verge only.
This roadwork event was last updated by Severn Trent Water on 15 Nov 2024 at 14:51.
11 Feb and 5 May 2025
BT are proposing to carry out Utility asset works on Albert Road, Bromsgrove.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 February 2025 and could run through until 5 May 2025. The works will impact the carriageway only.
This roadwork event was last updated by BT on 11 Nov 2024 at 14:05.
14 and 21 Feb 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Littleheath Lane, Lickey End.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 14 February 2025 and could run through until 21 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 20 Nov 2024 at 14:15.
17 Feb and 7 Mar 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Marlborough Avenue, Bromsgrove.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 7 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 6 Nov 2024 at 13:25.
17 Feb and 7 Mar 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Marlborough Avenue, Bromsgrove.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 7 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 8 Nov 2024 at 14:30.
17 Feb and 7 Mar 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Clive Road, Bromsgrove.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 7 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 12 Nov 2024 at 10:14.
17 Feb and 7 Mar 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Clive Road, Bromsgrove.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 7 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 13 Nov 2024 at 11:18.
17 Feb and 24 Mar 2025
Cadent Gas were proposing to carry out Utility asset works on Kidderminster Road, Bromsgrove.
These works were categorised as Major.
Two-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 17 February 2025 and run through until 24 March 2025. The works were due to impact the carriageway and verge.
This roadwork event was last updated by Cadent Gas on 14 Nov 2024 at 13:49.
17 and 20 Feb 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Victoria Road, Bromsgrove.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 20 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Severn Trent Water on 28 Oct 2024 at 12:50.
17 and 20 Feb 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Victoria Road, Bromsgrove.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 20 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Severn Trent Water on 4 Nov 2024 at 15:24.
17 and 21 Feb 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Alcester Road, Lickey End.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 21 February 2025. The works will impact the verge only.
This roadwork event was last updated by Worcestershire County Council on 27 Aug 2024 at 14:51.
17 and 19 Feb 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Bear Hill, Alvechurch.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 19 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Severn Trent Water on 25 Nov 2024 at 14:11.
17 and 19 Feb 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Bear Hill, Alvechurch.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 19 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Severn Trent Water on 26 Nov 2024 at 09:58.
17 and 19 Feb 2025
Severn Trent Water are proposing to carry out New service connection on Stonehouse Lane, Hopwood.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 19 February 2025. The works will impact the carriageway and verge.
This roadwork event was last updated by Severn Trent Water on 12 Nov 2024 at 10:11.
17 and 19 Feb 2025
Severn Trent Water are proposing to carry out New service connection on Stonehouse Lane, Hopwood.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 19 February 2025. The works will impact the carriageway and verge.
This roadwork event was last updated by Severn Trent Water on 25 Nov 2024 at 13:48.
17 and 19 Feb 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Icknield Street, Headley Heath.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 19 February 2025. The works will impact the verge only.
This roadwork event was last updated by Severn Trent Water on 25 Nov 2024 at 14:43.
17 and 19 Feb 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Icknield Street, Headley Heath.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 19 February 2025. The works will impact the verge only.
This roadwork event was last updated by Severn Trent Water on 3 Dec 2024 at 14:22.
19 and 21 Feb 2025
Severn Trent Water were proposing to carry out Utility repair and maintenance works on Holyoakes Lane, Bentley.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 19 February 2025 and run through until 21 February 2025. The works were due to impact the verge only.
This roadwork event was last updated by Severn Trent Water on 13 Nov 2024 at 16:07.
21 Feb and 6 Mar 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Drayton Road, Drayton, Belbroughton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 February 2025 and could run through until 6 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 28 Nov 2024 at 13:32.
21 Feb and 6 Mar 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Drayton Road, Drayton, Belbroughton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 February 2025 and could run through until 6 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 28 Nov 2024 at 15:31.
21 Feb and 6 Mar 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Drayton Road, Belbroughton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 February 2025 and could run through until 6 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 28 Nov 2024 at 13:33.
21 Feb and 6 Mar 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Drayton Road, Belbroughton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 February 2025 and could run through until 6 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 28 Nov 2024 at 15:29.
24 and 26 Feb 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Brookhouse Road, Barnt Green.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 26 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 15 Oct 2024 at 11:01.
24 and 26 Feb 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Brookhouse Road, Barnt Green.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 26 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Severn Trent Water on 18 Oct 2024 at 15:54.
24 Feb and 30 May 2025
Network Rail are proposing to carry out Works for Rail Purposes on Fiery Hill Road, Barnt Green.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 30 May 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Network Rail on 3 Dec 2024 at 14:40.
24 Feb and 2 May 2025
Cadent Gas are proposing to carry out Utility asset works on Stourbridge Road, Catshill.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 2 May 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 9 Dec 2024 at 16:30.
3 and 5 Mar 2025
Severn Trent Water were proposing to carry out New service connection on Fockbury Road, Dodford.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 3 March 2025 and run through until 5 March 2025. The works were due to impact the carriageway and verge.
This roadwork event was last updated by Severn Trent Water on 2 Dec 2024 at 11:55.
3 Mar and 30 May 2025
Network Rail are proposing to carry out Works for Rail Purposes on Fiery Hill Road, Barnt Green.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 3 March 2025 and could run through until 30 May 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Network Rail on 6 Dec 2024 at 13:54.
3 and 5 Mar 2025
Severn Trent Water are proposing to carry out New service connection on Stonehouse Lane, Hopwood.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 March 2025 and could run through until 5 March 2025. The works will impact the carriageway and verge.
This roadwork event was last updated by Severn Trent Water on 28 Nov 2024 at 08:38.
3 and 19 Mar 2025
Worcestershire County Council are proposing to carry out Highway repair and maintenance works on Headley Heath Lane, Headley Heath.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 March 2025 and could run through until 19 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Worcestershire County Council on 2 Dec 2024 at 13:51.
5 and 7 Mar 2025
Severn Trent Water were proposing to carry out Utility repair and maintenance works on Greenhill, Burcot.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 5 March 2025 and run through until 7 March 2025. The works were due to impact the verge only.
This roadwork event was last updated by Severn Trent Water on 26 Nov 2024 at 12:21.
10 and 12 Mar 2025
Severn Trent Water are proposing to carry out Utility repair and maintenance works on Greenhill, Burcot.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 10 March 2025 and could run through until 12 March 2025. The works will impact the verge only.
This roadwork event was last updated by Severn Trent Water on 8 Dec 2024 at 08:33.
10 and 28 Mar 2025
Cadent Gas were proposing to carry out Utility asset works on Pennine Road, Bromsgrove.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 10 March 2025 and run through until 28 March 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 18 Oct 2024 at 10:23.
10 and 28 Mar 2025
Cadent Gas were proposing to carry out Utility asset works on Pennine Road, Bromsgrove.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 10 March 2025 and run through until 28 March 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 22 Oct 2024 at 09:02.
10 and 28 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Pennine Road, Bromsgrove.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 10 March 2025 and could run through until 28 March 2025. The works will impact the footway, carriageway and footpath.
This roadwork event was last updated by Cadent Gas on 25 Oct 2024 at 14:52.
11 and 13 Mar 2025
Severn Trent Water are proposing to carry out New service connection on Hill Lane, Alvechurch.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 March 2025 and could run through until 13 March 2025. The works will impact the carriageway and verge.
This roadwork event was last updated by Severn Trent Water on 11 Dec 2024 at 12:01.
Roadworks Map near to Alvechurch Highway, BROMSGROVE, B60 1NY
- Any red lines indicate the extent of the works.
- Clicking on the map will re-centre to the selected point.
- Within 1 mile, all roadworks are displayed.
- Within 2-3 miles, standard, urgent and major roadworks are displayed.
- For 3-5 miles, only major roadworks are shown.
- The higher the marker number, the further away the roadworks are from the centre of the postcode.
- Where traffic camera videos or images are shown, no historical versions are retained. Once a new image or video becomes available it overwrites the previous version.
Roadworks Listing near to Alvechurch Highway, BROMSGROVE, B60 1NY (3 Events)
(Scheduled Dates)
(miles)
(Scheduled: 11 Dec 2024 - 17 Dec 2024)
(Scheduled: 11 Dec 2024 - 12 Dec 2024)