ROADWORKS SUMMARY
Warwick Road, RAYLEIGH, SS6 8TG

Introduction

Image of petrol pumps

View current and future planned roadworks and road closures for Warwick Road, SS6 8TG and the surrounding area.

Our roadwork details are constantly updated and reflect the current situation and we offer both a map view and a listing. We also highlight the major and significant roadworks occuring near to you help you avoid the worst of the delays to your journey.

The roadworks shown below show all current and proposed works during the next 90 days and historical data is recorded since July 2020.

Please note that we re-publish this data and cannot provide any additional information pertaining to a roadwork event. If you require more information, please contact the organisation carrying out the work.

Data are provided by the Department for Transport.

Have we helped today?

If we have helped you today, please consider buying us a quick coffee to keep us going!

Transport for London Traffic cameras are currently unavailable whilst TfL resolve a data security issue.

Major Roadworks near to Warwick Road, RAYLEIGH, SS6 8TG

Details of major roadworks, currently in progress or starting soon and resulting in road closures and/or traffic signal management for Warwick Road are shown here covering a 5 mile radius. See further down for details of all roadworks in your area.

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Cadent Gas logo
LONG TERM
Until
15 Apr 2025
Details
View Map
Share
Follow
Rectory Road

Cadent Gas are carrying out Utility asset works on Rectory Road, Pitsea.

These works are categorised as Major.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 12 April 2024 at 11:40 and could run through until 15 April 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 4 Nov 2024 at 15:59.

Cadent Gas logo
LONG TERM
Between
2 Sep 2024 and 31 Jan 2025
Details
View Map
Share
Follow
Pound Lane

Cadent Gas are proposing to carry out Utility asset works on Pound Lane, North Benfleet, Basildon.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 September 2024 and could run through until 31 January 2025. The works will impact the footway and carriageway.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Cadent Gas on 30 Jul 2024 at 10:52.

Cadent Gas logo
LONG TERM
Between
2 Sep 2024 and 31 Jan 2025
Details
View Map
Share
Follow
Pound Lane

Cadent Gas are proposing to carry out Utility asset works on Pound Lane, North Benfleet, Basildon.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 September 2024 and could run through until 31 January 2025. The works will impact the footway and carriageway.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Cadent Gas on 23 Aug 2024 at 12:14.

Cadent Gas logo
LONG TERM
Between
2 Sep 2024 and 31 Jan 2025
Details
View Map
Share
Follow
Pound Lane

Cadent Gas are proposing to carry out Utility asset works on Pound Lane, North Benfleet, Basildon.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 September 2024 and could run through until 31 January 2025. The works will impact the footway and carriageway.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Cadent Gas on 30 Aug 2024 at 11:01.

Cadent Gas logo
LONG TERM
Between
2 Sep 2024 and 31 Jan 2025
Details
View Map
Share
Follow
Pound Lane

Cadent Gas are proposing to carry out Utility asset works on Pound Lane, North Benfleet, Basildon.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 September 2024 and could run through until 31 January 2025. The works will impact the footway and carriageway.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Cadent Gas on 4 Sep 2024 at 10:34.

Cadent Gas logo
LONG TERM
Finishing
Today
Details
View Map
Share
Follow
Lekoe Road

Cadent Gas are carrying out Utility asset works on Lekoe Road, Canvey Island.

These works are categorised as Major.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 16 September 2024 at 09:52 and could run through until 24 November 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 31 Oct 2024 at 08:53.

Cadent Gas logo
LONG TERM
Between
24 Sep and 20 Dec 2024
Details
View Map
Share
Follow
Harrow Road

Cadent Gas are proposing to carry out Utility asset works on Harrow Road, Bowers Gifford And North Benfleet, Basildon.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 September 2024 and could run through until 20 December 2024. The works will impact the footway and carriageway.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Cadent Gas on 15 Aug 2024 at 17:51.

Cadent Gas logo
LONG TERM
Between
21 Oct and 16 Dec 2024
Details
View Map
Share
Snakes Lane

Cadent Gas were proposing to carry out Utility asset works on Snakes Lane, Eastwood.

These works were categorised as Major.

Two-way signals were planned to be in use for some or all of the period. However, the works were cancelled.

The works were originally planned to start 21 October 2024 and run through until 16 December 2024. The works were due to impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 18 Oct 2024 at 10:39.

Cadent Gas logo
LONG TERM
Until
15 Dec 2024
Details
View Map
Share
Follow
Pound Lane

Cadent Gas are carrying out Utility asset works on Pound Lane, Bowers Gifford And North Benfleet, Basildon.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 21 October 2024 at 08:55 and could run through until 15 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 20 Nov 2024 at 11:20.

Essex County Council logo
LONG TERM
Finishing
Saturday
Details
View Map
Share
Follow
Chelmsford Road

Essex County Council are proposing to carry out Highway improvement works on Chelmsford Road, Rawreth.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 21 October 2024 and could run through until 30 November 2024. The works will impact the carriageway only.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Essex County Council on 8 Oct 2024 at 13:03.

Southend-on-sea Borough Council logo
LONG TERM
Finishing
Saturday
Details
View Map
Share
Follow
Seaview Road

Southend-on-sea Borough Council are carrying out Works for road purposes on Seaview Road, Leigh-on-sea.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 22 October 2024 at 13:00 and could run through until 30 November 2024. The works will impact the carriageway only.

This roadwork event was last updated by Southend-on-sea Borough Council on 23 Oct 2024 at 13:25.

LONG TERM
Until
16 Dec 2024
Details
View Map
Share
Follow
Lower Road

Essex And Suffolk Water are carrying out Utility repair and maintenance works on Lower Road, Hockley.

These works are categorised as Major.

Two-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 22 October 2024 at 09:00 and could run through until 16 December 2024. The works will impact the carriageway and verge.

This roadwork event was last updated by Essex And Suffolk Water on 20 Nov 2024 at 14:14.

Essex County Council logo
LONG TERM
Finishing
Thursday
Details
View Map
Share
Follow
Ashingdon Road

Essex County Council are proposing to carry out Highway improvement works on Ashingdon Road, Rochford.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 24 October 2024 and could run through until 28 November 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 20 Sep 2024 at 14:25.

Essex County Council logo
LONG TERM
Finishing
Saturday
Details
View Map
Share
Follow
Chelmsford Road

Essex County Council are proposing to carry out Highway improvement works on Chelmsford Road, Rawreth.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 October 2024 and could run through until 30 November 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 17 Oct 2024 at 10:17.

Essex County Council logo
LONG TERM
Finishing
Saturday
Details
View Map
Share
Follow
Chelmsford Road

Essex County Council are carrying out Highway improvement works on Chelmsford Road, Rawreth.

These works are categorised as Major.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 24 October 2024 at 00:00 and could run through until 30 November 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 25 Oct 2024 at 07:50.

LONG TERM
Between
28 Oct and 20 Dec 2024
Details
View Map
Share
Ferry Road

Essex And Suffolk Water were proposing to carry out Utility repair and maintenance works on Ferry Road, Hullbridge.

These works were categorised as Major.

Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.

The works were originally planned to start 28 October 2024 and run through until 20 December 2024. The works were due to impact the footway and carriageway.

This roadwork event was last updated by Essex And Suffolk Water on 14 Aug 2024 at 15:22.

Between
4 Nov and 2 Dec 2024
Details
View Map
Share
Follow
Eastern Avenue

Essex And Suffolk Water are proposing to carry out Utility repair and maintenance works on Eastern Avenue, Southend-on-sea.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 November 2024 and could run through until 2 December 2024. The works will impact the carriageway and verge.

This roadwork event was last updated by Essex And Suffolk Water on 22 Aug 2024 at 10:16.

Essex County Council logo
Finishing
Friday
Details
View Map
Share
Follow
The Ridings

Essex County Council are proposing to carry out Highway improvement works on The Ridings, Canvey Island.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 11 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 20 May 2024 at 13:49.

Finishing
Tomorrow
Details
View Map
Share
Follow
Leigh Road

UK Power Distribution are carrying out New service connection on Leigh Road, Leigh-on-sea.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 11 November 2024 at 09:30 and could run through until 25 November 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by UK Power Distribution on 22 Nov 2024 at 18:48.

Essex County Council logo
Finishing
Thursday
Details
View Map
Share
Follow
Arterial Road

Essex County Council are carrying out Highway improvement works on Arterial Road, Rayleigh.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 11 November 2024 at 17:03 and could run through until 28 November 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 11 Nov 2024 at 17:20.

Essex County Council logo
Finishing
Thursday
Details
View Map
Share
Follow
Southend Arterial Road

Essex County Council are carrying out Highway improvement works on Southend Arterial Road, Thundersley, Benfleet.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 11 November 2024 at 17:03 and could run through until 28 November 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 11 Nov 2024 at 17:20.

Cadent Gas logo
Between
11 Nov and 9 Dec 2024
Details
View Map
Share
Follow
Grove Road

Cadent Gas are proposing to carry out Utility asset works on Grove Road, Rayleigh.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 11 November 2024 and could run through until 9 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 19 Aug 2024 at 13:48.

Cadent Gas logo
Between
11 Nov and 9 Dec 2024
Details
View Map
Share
Follow
Grove Road

Cadent Gas are proposing to carry out Utility asset works on Grove Road, Rayleigh.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 11 November 2024 and could run through until 9 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 9 Oct 2024 at 13:13.

Cadent Gas logo
Until
9 Dec 2024
Details
View Map
Share
Follow
Grove Road

Cadent Gas are carrying out Utility asset works on Grove Road, Rayleigh.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 11 November 2024 at 11:08 and could run through until 9 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 13 Nov 2024 at 17:00.

Cadent Gas logo
Between
11 Nov and 9 Dec 2024
Details
View Map
Share
Follow
Dorothy Farm Road

Cadent Gas are proposing to carry out Utility asset works on Dorothy Farm Road, Rayleigh.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 11 November 2024 and could run through until 9 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 13 Sep 2024 at 09:50.

Cadent Gas logo
Between
11 Nov and 9 Dec 2024
Details
View Map
Share
Follow
Dorothy Farm Road

Cadent Gas are proposing to carry out Utility asset works on Dorothy Farm Road, Rayleigh.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 11 November 2024 and could run through until 9 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 10 Oct 2024 at 15:03.

Cadent Gas logo
Until
9 Dec 2024
Details
View Map
Share
Follow
Dorothy Farm Road

Cadent Gas are carrying out Utility asset works on Dorothy Farm Road, Rayleigh.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 11 November 2024 at 11:09 and could run through until 9 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 11 Nov 2024 at 12:09.

Finishing
Tomorrow
Details
View Map
Share
Follow
Daws Heath Road

Essex And Suffolk Water are carrying out Utility repair and maintenance works on Daws Heath Road, Rayleigh.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 15 November 2024 at 09:46 and could run through until 25 November 2024. The works will impact the carriageway and verge.

This roadwork event was last updated by Essex And Suffolk Water on 20 Nov 2024 at 12:46.

UK Power Networks Eastern & London logo
Finishing
Tuesday
Details
View Map
Share
Follow
Abbey Road

UK Power Networks Eastern & London are carrying out Utility repair and maintenance works on Abbey Road, Hullbridge.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 16 November 2024 at 08:19 and could run through until 26 November 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by UK Power Networks Eastern & London on 20 Nov 2024 at 08:05.

Cadent Gas logo
Between
18 Nov and 9 Dec 2024
Details
View Map
Share
Follow
Fairlop Avenue

Cadent Gas are proposing to carry out Utility asset works on Fairlop Avenue, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 18 November 2024 and could run through until 9 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 12 Aug 2024 at 08:02.

Between
18 Nov and 16 Dec 2024
Details
View Map
Share
Follow
Eastern Avenue

Essex And Suffolk Water are proposing to carry out Utility repair and maintenance works on Eastern Avenue, Southend-on-sea.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 18 November 2024 and could run through until 16 December 2024. The works will impact the carriageway and verge.

This roadwork event was last updated by Essex And Suffolk Water on 17 Sep 2024 at 11:23.

Finishing
Tomorrow
Details
View Map
Share
Follow
Daws Heath Road

Essex And Suffolk Water are carrying out Utility repair and maintenance works on Daws Heath Road, Rayleigh.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 18 November 2024 at 07:02 and could run through until 25 November 2024. The works will impact the carriageway and verge.

This roadwork event was last updated by Essex And Suffolk Water on 18 Nov 2024 at 15:53.

Essex County Council logo
Between
18 Nov and 4 Dec 2024
Details
View Map
Share
Elm Close

Essex County Council were proposing to carry out Highway improvement works on Elm Close, Rayleigh.

These works were categorised as Major.

Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.

The works were originally planned to start 18 November 2024 and run through until 4 December 2024. The works were due to impact the carriageway only.

This roadwork event was last updated by Essex County Council on 16 Aug 2024 at 14:10.

Cadent Gas logo
LONG TERM
Until
23 Dec 2024
Details
View Map
Share
Follow
Ruskin Path

Cadent Gas are carrying out Utility asset works on Ruskin Path, Wickford.

These works are categorised as Major.

The works should not impact the carriageway.

The works started on 19 November 2024 at 08:50 and could run through until 23 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 20 Nov 2024 at 15:41.

Essex County Council logo
Finishing
Wednesday
Details
View Map
Share
Follow
Canvey Way

Essex County Council are carrying out Remedial works on Canvey Way, South Benfleet, Benfleet.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 20 November 2024 at 00:00 and could run through until 27 November 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 21 Nov 2024 at 08:48.

Until
3 Dec 2024
Details
View Map
Share
Follow
Chapmans Walk

Essex And Suffolk Water are carrying out Utility repair and maintenance works on Chapmans Walk, Leigh-on-sea.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 20 November 2024 at 09:37 and could run through until 3 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Essex And Suffolk Water on 20 Nov 2024 at 13:23.

Cadent Gas logo
LONG TERM
Between
21 Nov 2024 and 13 Jan 2025
Details
View Map
Share
Pound Lane

Cadent Gas were proposing to carry out Utility asset works on Pound Lane, North Benfleet, Basildon.

These works were categorised as Major.

Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.

The works were originally planned to start 21 November 2024 and run through until 13 January 2025. The works were due to impact the carriageway only.

This roadwork event was last updated by Cadent Gas on 10 Sep 2024 at 11:48.

Southend-on-sea Borough Council logo
Finishing
Wednesday
Details
View Map
Share
Follow
Dundonald Drive

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Dundonald Drive, Leigh-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 25 November 2024 and could run through until 27 November 2024. The works will impact the verge only.

This roadwork event was last updated by Southend-on-sea Borough Council on 30 Aug 2024 at 08:45.

Essex County Council logo
Between
25 Nov and 6 Dec 2024
Details
View Map
Share
Follow
Rectory Road

Essex County Council are proposing to carry out Highway improvement works on Rectory Road, Rochford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 25 November 2024 and could run through until 6 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 9 Sep 2024 at 11:20.

Essex County Council logo
Between
25 Nov and 6 Dec 2024
Details
View Map
Share
Follow
Rectory Road

Essex County Council are proposing to carry out Highway improvement works on Rectory Road, Rochford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 25 November 2024 and could run through until 6 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 9 Oct 2024 at 09:09.

Essex County Council logo
Between
25 Nov and 6 Dec 2024
Details
View Map
Share
Follow
Rectory Road

Essex County Council are proposing to carry out Highway improvement works on Rectory Road, Rochford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 25 November 2024 and could run through until 6 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 11 Oct 2024 at 10:49.

Southend-on-sea Borough Council logo
Between
28 Nov and 12 Dec 2024
Details
View Map
Share
Follow
Queensway

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Queensway, Southend-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 November 2024 and could run through until 12 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Southend-on-sea Borough Council on 3 Oct 2024 at 10:15.

Southend-on-sea Borough Council logo
Between
28 Nov and 2 Dec 2024
Details
View Map
Share
Follow
West Street

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on West Street, Southend-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 November 2024 and could run through until 2 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Southend-on-sea Borough Council on 24 Sep 2024 at 14:24.

Essex County Council logo
Between
29 Nov and 4 Dec 2024
Details
View Map
Share
Follow
London Road Roundabout

Essex County Council are proposing to carry out Highway improvement works on London Road Roundabout, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 29 November 2024 and could run through until 4 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 27 Jun 2024 at 10:41.

Cadent Gas logo
Between
2 and 20 Dec 2024
Details
View Map
Share
Follow
Pennial Road

Cadent Gas are proposing to carry out Utility asset works on Pennial Road, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 December 2024 and could run through until 20 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 11 Nov 2024 at 09:40.

Cadent Gas logo
Between
2 and 16 Dec 2024
Details
View Map
Share
Follow
Thelma Avenue

Cadent Gas are proposing to carry out Utility asset works on Thelma Avenue, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 December 2024 and could run through until 16 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 12 Aug 2024 at 08:31.

Southend-on-sea Borough Council logo
Between
2 and 6 Dec 2024
Details
View Map
Share
Follow
St Vincent's Road

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on St Vincent's Road, Westcliff-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 December 2024 and could run through until 6 December 2024. The works will impact the verge only.

This roadwork event was last updated by Southend-on-sea Borough Council on 21 Aug 2024 at 15:21.

Southend-on-sea Borough Council logo
Between
2 and 6 Dec 2024
Details
View Map
Share
Follow
St Vincent's Road

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on St Vincent's Road, Westcliff-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 December 2024 and could run through until 6 December 2024. The works will impact the verge only.

This roadwork event was last updated by Southend-on-sea Borough Council on 22 Aug 2024 at 15:34.

Essex County Council logo
Between
2 and 4 Dec 2024
Details
View Map
Share
Follow
Richmond Avenue

Essex County Council are proposing to carry out Highway improvement works on Richmond Avenue, South Benfleet, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 December 2024 and could run through until 4 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Essex County Council on 1 Nov 2024 at 09:35.

Essex County Council logo
Between
2 and 4 Dec 2024
Details
View Map
Share
Richmond Avenue

Essex County Council were proposing to carry out Highway improvement works on Richmond Avenue, South Benfleet, Benfleet.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 2 December 2024 and run through until 4 December 2024. The works were due to impact the footway and carriageway.

This roadwork event was last updated by Essex County Council on 4 Nov 2024 at 11:19.

Essex County Council logo
Between
2 and 4 Dec 2024
Details
View Map
Share
Follow
Church Road

Essex County Council are proposing to carry out Highway improvement works on Church Road, Thundersley, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 December 2024 and could run through until 4 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 11 Oct 2024 at 15:41.

Essex County Council logo
Between
4 and 7 Dec 2024
Details
View Map
Share
Follow
Cranfield Park Road

Essex County Council are proposing to carry out Highway improvement works on Cranfield Park Road, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 December 2024 and could run through until 7 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 15 Oct 2024 at 11:45.

Essex County Council logo
Between
4 and 7 Dec 2024
Details
View Map
Share
Follow
Cranfield Park Road

Essex County Council are proposing to carry out Highway improvement works on Cranfield Park Road, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 December 2024 and could run through until 7 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 21 Oct 2024 at 16:30.

Essex County Council logo
Between
4 and 7 Dec 2024
Details
View Map
Share
Cranfield Park Road

Essex County Council were proposing to carry out Highway improvement works on Cranfield Park Road, Wickford.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 4 December 2024 and run through until 7 December 2024. The works were due to impact the carriageway only.

This roadwork event was last updated by Essex County Council on 28 Oct 2024 at 15:29.

Essex County Council logo
Between
4 and 7 Dec 2024
Details
View Map
Share
Cranfield Park Road

Essex County Council were proposing to carry out Highway improvement works on Cranfield Park Road, Wickford.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 4 December 2024 and run through until 7 December 2024. The works were due to impact the carriageway only.

This roadwork event was last updated by Essex County Council on 28 Oct 2024 at 15:29.

Essex County Council logo
Between
4 and 7 Dec 2024
Details
View Map
Share
Follow
Radwinter Avenue

Essex County Council are proposing to carry out Highway improvement works on Radwinter Avenue, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 December 2024 and could run through until 7 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 21 Oct 2024 at 16:09.

Essex County Council logo
Between
4 and 7 Dec 2024
Details
View Map
Share
Follow
Cranfield Park Road

Essex County Council are proposing to carry out Highway improvement works on Cranfield Park Road, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 December 2024 and could run through until 7 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 21 Oct 2024 at 16:30.

Essex County Council logo
Between
4 and 7 Dec 2024
Details
View Map
Share
Cranfield Park Road

Essex County Council were proposing to carry out Highway improvement works on Cranfield Park Road, Wickford.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 4 December 2024 and run through until 7 December 2024. The works were due to impact the carriageway only.

This roadwork event was last updated by Essex County Council on 28 Oct 2024 at 15:29.

Essex County Council logo
Between
4 and 7 Dec 2024
Details
View Map
Share
Follow
Cranfield Park Road

Essex County Council are proposing to carry out Highway improvement works on Cranfield Park Road, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 December 2024 and could run through until 7 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 21 Oct 2024 at 16:19.

Essex County Council logo
Between
4 and 7 Dec 2024
Details
View Map
Share
Follow
Cranfield Park Road

Essex County Council are proposing to carry out Highway improvement works on Cranfield Park Road, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 December 2024 and could run through until 7 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 25 Oct 2024 at 16:04.

Essex County Council logo
Between
4 and 14 Dec 2024
Details
View Map
Share
Follow
Cranfield Park Road

Essex County Council are proposing to carry out Highway improvement works on Cranfield Park Road, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 December 2024 and could run through until 14 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 29 Oct 2024 at 13:19.

Essex County Council logo
Between
4 and 14 Dec 2024
Details
View Map
Share
Follow
Cranfield Park Road

Essex County Council are proposing to carry out Highway improvement works on Cranfield Park Road, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 December 2024 and could run through until 14 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 5 Nov 2024 at 12:44.

Essex County Council logo
Between
4 and 7 Dec 2024
Details
View Map
Share
Follow
Salcott Crescent

Essex County Council are proposing to carry out Highway improvement works on Salcott Crescent, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 December 2024 and could run through until 7 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 25 Oct 2024 at 16:46.

Essex County Council logo
Between
4 and 14 Dec 2024
Details
View Map
Share
Follow
Salcott Crescent

Essex County Council are proposing to carry out Highway improvement works on Salcott Crescent, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 December 2024 and could run through until 14 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 29 Oct 2024 at 13:19.

Essex County Council logo
Between
4 and 14 Dec 2024
Details
View Map
Share
Follow
Salcott Crescent

Essex County Council are proposing to carry out Highway improvement works on Salcott Crescent, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 December 2024 and could run through until 14 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 6 Nov 2024 at 09:17.

Essex County Council logo
Between
4 and 7 Dec 2024
Details
View Map
Share
Follow
Radwinter Avenue

Essex County Council are proposing to carry out Highway improvement works on Radwinter Avenue, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 December 2024 and could run through until 7 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 25 Oct 2024 at 16:04.

Essex County Council logo
Between
4 and 14 Dec 2024
Details
View Map
Share
Follow
Radwinter Avenue

Essex County Council are proposing to carry out Highway improvement works on Radwinter Avenue, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 December 2024 and could run through until 14 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 29 Oct 2024 at 13:19.

Essex County Council logo
Between
4 and 14 Dec 2024
Details
View Map
Share
Follow
Radwinter Avenue

Essex County Council are proposing to carry out Highway improvement works on Radwinter Avenue, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 December 2024 and could run through until 14 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 5 Nov 2024 at 13:44.

Essex County Council logo
Between
8 and 10 Dec 2024
Details
View Map
Share
Follow
Furtherwick Road

Essex County Council are proposing to carry out Remedial works on Furtherwick Road, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 8 December 2024 and could run through until 10 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 21 Nov 2024 at 14:14.

Essex County Council logo
Between
8 and 11 Dec 2024
Details
View Map
Share
Follow
Rayleigh Road

Essex County Council are proposing to carry out Highway improvement works on Rayleigh Road, Thundersley, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 8 December 2024 and could run through until 11 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 15 Nov 2024 at 09:51.

Essex County Council logo
Between
8 and 11 Dec 2024
Details
View Map
Share
Follow
Stadium Way

Essex County Council are proposing to carry out Highway improvement works on Stadium Way, Thundersley, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 8 December 2024 and could run through until 11 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 15 Nov 2024 at 09:51.

Cadent Gas logo
Between
9 and 23 Dec 2024
Details
View Map
Share
Follow
Thelma Avenue

Cadent Gas are proposing to carry out Utility asset works on Thelma Avenue, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 9 December 2024 and could run through until 23 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 30 Aug 2024 at 08:24.

Cadent Gas logo
Between
9 and 23 Dec 2024
Details
View Map
Share
Follow
Thelma Avenue

Cadent Gas are proposing to carry out Utility asset works on Thelma Avenue, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 9 December 2024 and could run through until 23 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 5 Nov 2024 at 15:44.

Southend-on-sea Borough Council logo
Between
9 and 23 Dec 2024
Details
View Map
Share
Carlingford Drive

Southend-on-sea Borough Council were proposing to carry out Highway repair and maintenance works on Carlingford Drive, Westcliff-on-sea.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 9 December 2024 and run through until 23 December 2024. The works were due to impact the carriageway only.

This roadwork event was last updated by Southend-on-sea Borough Council on 15 Oct 2024 at 11:18.

Southend-on-sea Borough Council logo
Between
9 and 23 Dec 2024
Details
View Map
Share
Follow
Arterial Road

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Arterial Road, Leigh-on-sea.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 9 December 2024 and could run through until 23 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Southend-on-sea Borough Council on 30 Sep 2024 at 11:51.

Essex County Council logo
Between
9 and 11 Dec 2024
Details
View Map
Share
Follow
Rayleigh Road

Essex County Council are proposing to carry out Highway improvement works on Rayleigh Road, Thundersley, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 9 December 2024 and could run through until 11 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 1 Nov 2024 at 10:34.

Essex County Council logo
Between
9 and 11 Dec 2024
Details
View Map
Share
Follow
Stadium Way

Essex County Council are proposing to carry out Highway improvement works on Stadium Way, Thundersley, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 9 December 2024 and could run through until 11 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 1 Nov 2024 at 10:34.

Cadent Gas logo
LONG TERM
Between
9 Dec 2024 and 10 Jan 2025
Details
View Map
Share
Follow
Barrie Pavement

Cadent Gas are proposing to carry out Utility asset works on Barrie Pavement, Wickford.

These works are categorised as Major.

The works will start on or after 9 December 2024 and could run through until 10 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 30 Sep 2024 at 12:48.

Essex County Council logo
Between
10 and 12 Dec 2024
Details
View Map
Share
Follow
Church Road

Essex County Council are proposing to carry out Highway improvement works on Church Road, Thundersley, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 December 2024 and could run through until 12 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 16 Oct 2024 at 11:55.

Essex County Council logo
Between
10 and 12 Dec 2024
Details
View Map
Share
Follow
Church Road

Essex County Council are proposing to carry out Highway improvement works on Church Road, Thundersley, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 December 2024 and could run through until 12 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 15 Nov 2024 at 15:26.

Essex County Council logo
Between
16 and 18 Dec 2024
Details
View Map
Share
Follow
Furtherwick Road

Essex County Council are proposing to carry out Highway improvement works on Furtherwick Road, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 16 December 2024 and could run through until 18 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 11 Oct 2024 at 16:27.

Southend-on-sea Borough Council logo
Between
16 and 20 Dec 2024
Details
View Map
Share
Follow
Preston Road

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Preston Road, Westcliff-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 16 December 2024 and could run through until 20 December 2024. The works will impact the verge only.

This roadwork event was last updated by Southend-on-sea Borough Council on 2 Sep 2024 at 11:44.

Southend-on-sea Borough Council logo
Between
16 and 20 Dec 2024
Details
View Map
Share
Follow
Preston Road

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Preston Road, Westcliff-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 16 December 2024 and could run through until 20 December 2024. The works will impact the verge only.

This roadwork event was last updated by Southend-on-sea Borough Council on 3 Sep 2024 at 10:05.

Essex County Council logo
Between
17 and 21 Dec 2024
Details
View Map
Share
Follow
Eastern Esplanade

Essex County Council are proposing to carry out Highway improvement works on Eastern Esplanade, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 December 2024 and could run through until 21 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 16 Oct 2024 at 12:34.

Essex County Council logo
Between
17 and 21 Dec 2024
Details
View Map
Share
Follow
Eastern Esplanade

Essex County Council are proposing to carry out Highway improvement works on Eastern Esplanade, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 December 2024 and could run through until 21 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 21 Nov 2024 at 09:51.

Essex County Council logo
Between
17 and 21 Dec 2024
Details
View Map
Share
Follow
Furtherwick Road

Essex County Council are proposing to carry out Highway improvement works on Furtherwick Road, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 December 2024 and could run through until 21 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 16 Oct 2024 at 12:34.

Essex County Council logo
Between
17 and 21 Dec 2024
Details
View Map
Share
Follow
Furtherwick Road

Essex County Council are proposing to carry out Highway improvement works on Furtherwick Road, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 December 2024 and could run through until 21 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 21 Nov 2024 at 10:02.

Essex County Council logo
Between
17 and 19 Dec 2024
Details
View Map
Share
Follow
Kenneth Road

Essex County Council are proposing to carry out Highway improvement works on Kenneth Road, Thundersley, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 December 2024 and could run through until 19 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 6 Nov 2024 at 17:12.

Southend-on-sea Borough Council logo
Between
19 Dec 2024 and 8 Jan 2025
Details
View Map
Share
Follow
Stock Road

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Stock Road, Southend-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 19 December 2024 and could run through until 8 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Southend-on-sea Borough Council on 3 Oct 2024 at 11:34.

Southend-on-sea Borough Council logo
Between
20 and 23 Dec 2024
Details
View Map
Share
Follow
Manners Way

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Manners Way, Southend-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 20 December 2024 and could run through until 23 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Southend-on-sea Borough Council on 3 Oct 2024 at 12:53.

Southend-on-sea Borough Council logo
Between
22 and 24 Dec 2024
Details
View Map
Share
Follow
Southsea Avenue

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Southsea Avenue, Leigh-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 22 December 2024 and could run through until 24 December 2024. The works will impact the verge only.

This roadwork event was last updated by Southend-on-sea Borough Council on 27 Sep 2024 at 13:38.

Cadent Gas logo
Between
2 and 23 Jan 2025
Details
View Map
Share
Follow
Fairlop Avenue

Cadent Gas are proposing to carry out Utility asset works on Fairlop Avenue, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 January 2025 and could run through until 23 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 11 Nov 2024 at 15:27.

Cadent Gas logo
Between
2 and 23 Jan 2025
Details
View Map
Share
Follow
Kenneth Road

Cadent Gas are proposing to carry out Utility asset works on Kenneth Road, Thundersley, Benfleet.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 January 2025 and could run through until 23 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 11 Oct 2024 at 15:23.

Cadent Gas logo
Between
2 and 23 Jan 2025
Details
View Map
Share
Follow
Kenneth Road

Cadent Gas are proposing to carry out Utility asset works on Kenneth Road, Thundersley, Benfleet.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 January 2025 and could run through until 23 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 11 Oct 2024 at 16:19.

Cadent Gas logo
Between
2 and 22 Jan 2025
Details
View Map
Share
Follow
Crest Avenue

Cadent Gas are proposing to carry out Utility asset works on Crest Avenue, Pitsea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 January 2025 and could run through until 22 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 22 Nov 2024 at 09:31.

Cadent Gas logo
Between
6 and 20 Jan 2025
Details
View Map
Share
Follow
Thelma Avenue

Cadent Gas are proposing to carry out Utility asset works on Thelma Avenue, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 20 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 28 Aug 2024 at 14:09.

Cadent Gas logo
Between
6 and 20 Jan 2025
Details
View Map
Share
Follow
Thelma Avenue

Cadent Gas are proposing to carry out Utility asset works on Thelma Avenue, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 20 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 19 Sep 2024 at 10:40.

Cadent Gas logo
Between
6 and 20 Jan 2025
Details
View Map
Share
Follow
Thelma Avenue

Cadent Gas are proposing to carry out Utility asset works on Thelma Avenue, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 20 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 23 Sep 2024 at 10:41.

Cadent Gas logo
Between
6 and 20 Jan 2025
Details
View Map
Share
Follow
Lionel Road

Cadent Gas are proposing to carry out Utility asset works on Lionel Road, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 20 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 28 Aug 2024 at 14:12.

Cadent Gas logo
Between
6 and 20 Jan 2025
Details
View Map
Share
Follow
Lionel Road

Cadent Gas are proposing to carry out Utility asset works on Lionel Road, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 20 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 19 Sep 2024 at 10:30.

Cadent Gas logo
Between
6 and 20 Jan 2025
Details
View Map
Share
Follow
Lionel Road

Cadent Gas are proposing to carry out Utility asset works on Lionel Road, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 20 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 5 Nov 2024 at 15:12.

Cadent Gas logo
Between
6 Jan and 4 Feb 2025
Details
View Map
Share
Follow
Fourth Walk

Cadent Gas are proposing to carry out Utility asset works on Fourth Walk, Canvey Island.

These works are categorised as Major.

The works will start on or after 6 January 2025 and could run through until 4 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 12 Nov 2024 at 11:22.

Cadent Gas logo
Between
6 Jan and 4 Feb 2025
Details
View Map
Share
Follow
Fourth Walk

Cadent Gas are proposing to carry out Utility asset works on Fourth Walk, Canvey Island.

These works are categorised as Major.

The works will start on or after 6 January 2025 and could run through until 4 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 19 Nov 2024 at 10:48.

Essex County Council logo
Between
6 and 11 Jan 2025
Details
View Map
Share
Follow
Main Road

Essex County Council are proposing to carry out Highway improvement works on Main Road, Hawkwell.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 11 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 29 Oct 2024 at 17:15.

Essex County Council logo
Between
6 and 11 Jan 2025
Details
View Map
Share
Follow
Southend Road

Essex County Council are proposing to carry out Highway improvement works on Southend Road, Hockley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 11 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 29 Oct 2024 at 17:14.

Cadent Gas logo
Between
6 Jan and 3 Feb 2025
Details
View Map
Share
London Road

Cadent Gas were proposing to carry out Utility asset works on London Road, Wickford.

These works were categorised as Major.

Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.

The works were originally planned to start 6 January 2025 and run through until 3 February 2025. The works were due to impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 6 Nov 2024 at 14:28.

Cadent Gas logo
Between
6 Jan and 3 Feb 2025
Details
View Map
Share
Follow
Irvon Hill Road

Cadent Gas are proposing to carry out Utility asset works on Irvon Hill Road, Wickford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 3 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 6 Sep 2024 at 07:00.

Cadent Gas logo
Between
6 Jan and 3 Feb 2025
Details
View Map
Share
Irvon Hill Road

Cadent Gas were proposing to carry out Utility asset works on Irvon Hill Road, Wickford.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 6 January 2025 and run through until 3 February 2025. The works were due to impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 6 Nov 2024 at 15:01.

Between
7 Jan and 4 Feb 2025
Details
View Map
Share
Follow
Prittlewell Chase

Essex And Suffolk Water are proposing to carry out Remedial works on Prittlewell Chase, Westcliff-on-sea.

These works are categorised as Major.

A lane will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 January 2025 and could run through until 4 February 2025. The works will impact the carriageway, verge and cycleway.

This roadwork event was last updated by Essex And Suffolk Water on 20 Aug 2024 at 11:29.

Between
11 and 13 Jan 2025
Details
View Map
Share
Follow
Highbank Close

Essex And Suffolk Water are proposing to carry out Permanent reinstatement on Highbank Close, Leigh-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 11 January 2025 and could run through until 13 January 2025. The works will impact the footway, carriageway and footpath.

This roadwork event was last updated by Essex And Suffolk Water on 22 Nov 2024 at 15:34.

Essex County Council logo
Between
13 and 24 Jan 2025
Details
View Map
Share
Follow
Greenacres

Essex County Council are proposing to carry out Highway improvement works on Greenacres, Hadleigh, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 January 2025 and could run through until 24 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Essex County Council on 14 Oct 2024 at 12:28.

Essex County Council logo
Between
13 and 15 Jan 2025
Details
View Map
Share
Follow
Kenneth Road

Essex County Council are proposing to carry out Highway improvement works on Kenneth Road, Thundersley, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 January 2025 and could run through until 15 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 8 Nov 2024 at 09:37.

Essex County Council logo
Between
13 and 15 Jan 2025
Details
View Map
Share
Follow
Daws Heath Road

Essex County Council are proposing to carry out Highway improvement works on Daws Heath Road, Rayleigh.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 January 2025 and could run through until 15 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 14 Nov 2024 at 15:45.

Cadent Gas logo
Between
13 and 17 Jan 2025
Details
View Map
Share
Follow
South Street

Cadent Gas are proposing to carry out New service connection on South Street, Rochford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 January 2025 and could run through until 17 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 17 Oct 2024 at 11:31.

Essex County Council logo
Between
13 and 18 Jan 2025
Details
View Map
Share
Follow
Hall Road

Essex County Council are proposing to carry out Highway improvement works on Hall Road, Hawkwell.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 January 2025 and could run through until 18 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 19 Nov 2024 at 08:55.

Essex County Council logo
Between
13 and 18 Jan 2025
Details
View Map
Share
Follow
Main Road

Essex County Council are proposing to carry out Highway improvement works on Main Road, Hawkwell.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 January 2025 and could run through until 18 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 19 Nov 2024 at 08:54.

Essex County Council logo
Between
13 and 18 Jan 2025
Details
View Map
Share
Follow
Southend Road

Essex County Council are proposing to carry out Highway improvement works on Southend Road, Hockley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 January 2025 and could run through until 18 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 19 Nov 2024 at 08:54.

Southend-on-sea Borough Council logo
Between
14 and 16 Jan 2025
Details
View Map
Share
Follow
Coleman Street

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Coleman Street, Southend-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 14 January 2025 and could run through until 16 January 2025. The works will impact the verge only.

This roadwork event was last updated by Southend-on-sea Borough Council on 2 Sep 2024 at 15:29.

Southend-on-sea Borough Council logo
Between
14 and 16 Jan 2025
Details
View Map
Share
Follow
Coleman Street

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Coleman Street, Southend-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 14 January 2025 and could run through until 16 January 2025. The works will impact the verge only.

This roadwork event was last updated by Southend-on-sea Borough Council on 3 Sep 2024 at 10:04.

Southend-on-sea Borough Council logo
Between
15 and 29 Jan 2025
Details
View Map
Share
Follow
Carlingford Drive

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Carlingford Drive, Westcliff-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 15 January 2025 and could run through until 29 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Southend-on-sea Borough Council on 16 Oct 2024 at 12:11.

Essex County Council logo
Between
15 and 17 Jan 2025
Details
View Map
Share
Follow
Victoria Road

Essex County Council are proposing to carry out Highway improvement works on Victoria Road, Rayleigh.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 15 January 2025 and could run through until 17 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 15 Nov 2024 at 09:03.

Essex County Council logo
Between
15 and 17 Jan 2025
Details
View Map
Share
Follow
Victoria Road

Essex County Council are proposing to carry out Highway improvement works on Victoria Road, Rayleigh.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 15 January 2025 and could run through until 17 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 22 Nov 2024 at 14:38.

Essex County Council logo
Between
15 and 17 Jan 2025
Details
View Map
Share
Follow
Uplands Park Road

Essex County Council are proposing to carry out Highway improvement works on Uplands Park Road, Rayleigh.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 15 January 2025 and could run through until 17 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 15 Nov 2024 at 09:04.

Essex County Council logo
Between
15 and 17 Jan 2025
Details
View Map
Share
Follow
Uplands Park Road

Essex County Council are proposing to carry out Highway improvement works on Uplands Park Road, Rayleigh.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 15 January 2025 and could run through until 17 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 22 Nov 2024 at 14:38.

Essex County Council logo
Between
15 and 17 Jan 2025
Details
View Map
Share
Follow
Hockley Road

Essex County Council are proposing to carry out Highway improvement works on Hockley Road, Rayleigh.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 15 January 2025 and could run through until 17 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 15 Nov 2024 at 09:02.

Essex County Council logo
Between
15 and 17 Jan 2025
Details
View Map
Share
Follow
Hockley Road

Essex County Council are proposing to carry out Highway improvement works on Hockley Road, Rayleigh.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 15 January 2025 and could run through until 17 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 22 Nov 2024 at 14:38.

Cadent Gas logo
Between
20 Jan and 17 Feb 2025
Details
View Map
Share
Follow
Waarem Avenue

Cadent Gas are proposing to carry out Utility asset works on Waarem Avenue, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 20 January 2025 and could run through until 17 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 28 Aug 2024 at 14:14.

Cadent Gas logo
Between
20 Jan and 17 Feb 2025
Details
View Map
Share
Waarem Avenue

Cadent Gas were proposing to carry out Utility asset works on Waarem Avenue, Canvey Island.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 20 January 2025 and run through until 17 February 2025. The works were due to impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 20 Sep 2024 at 17:24.

Cadent Gas logo
Between
21 Jan and 2 Feb 2025
Details
View Map
Share
Follow
Lionel Road

Cadent Gas are proposing to carry out Utility asset works on Lionel Road, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 21 January 2025 and could run through until 2 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 28 Aug 2024 at 14:17.

Cadent Gas logo
Between
21 Jan and 2 Feb 2025
Details
View Map
Share
Follow
Lionel Road

Cadent Gas are proposing to carry out Utility asset works on Lionel Road, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 21 January 2025 and could run through until 2 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 17 Sep 2024 at 13:26.

Cadent Gas logo
Between
21 Jan and 2 Feb 2025
Details
View Map
Share
Follow
Lionel Road

Cadent Gas are proposing to carry out Utility asset works on Lionel Road, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 21 January 2025 and could run through until 2 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 19 Sep 2024 at 08:25.

Cadent Gas logo
Between
21 Jan and 2 Feb 2025
Details
View Map
Share
Follow
Fairlop Avenue

Cadent Gas are proposing to carry out Utility asset works on Fairlop Avenue, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 21 January 2025 and could run through until 2 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 28 Aug 2024 at 14:22.

Cadent Gas logo
Between
21 Jan and 2 Feb 2025
Details
View Map
Share
Follow
Fairlop Avenue

Cadent Gas are proposing to carry out Utility asset works on Fairlop Avenue, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 21 January 2025 and could run through until 2 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 13 Sep 2024 at 10:00.

Cadent Gas logo
Between
21 Jan and 2 Feb 2025
Details
View Map
Share
Follow
Fairlop Avenue

Cadent Gas are proposing to carry out Utility asset works on Fairlop Avenue, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 21 January 2025 and could run through until 2 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 17 Sep 2024 at 13:06.

Essex County Council logo
Between
23 and 25 Jan 2025
Details
View Map
Share
Follow
Windsor Gardens

Essex County Council are proposing to carry out Highway improvement works on Windsor Gardens, Thundersley, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 23 January 2025 and could run through until 25 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 19 Nov 2024 at 10:43.

Essex County Council logo
Between
23 and 25 Jan 2025
Details
View Map
Share
Follow
Westwood Close

Essex County Council are proposing to carry out Highway improvement works on Westwood Close, Thundersley, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 23 January 2025 and could run through until 25 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 19 Nov 2024 at 10:43.

Essex County Council logo
Between
23 and 25 Jan 2025
Details
View Map
Share
Follow
Parkfields

Essex County Council are proposing to carry out Highway improvement works on Parkfields, Thundersley, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 23 January 2025 and could run through until 25 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 19 Nov 2024 at 10:43.

Essex County Council logo
Between
23 and 25 Jan 2025
Details
View Map
Share
Follow
Rayleigh Road Access Road

Essex County Council are proposing to carry out Highway improvement works on Rayleigh Road Access Road, Thundersley, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 23 January 2025 and could run through until 25 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 19 Nov 2024 at 10:43.

Essex County Council logo
Between
23 and 25 Jan 2025
Details
View Map
Share
Follow
Queensmere

Essex County Council are proposing to carry out Highway improvement works on Queensmere, Thundersley, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 23 January 2025 and could run through until 25 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 19 Nov 2024 at 10:43.

Essex County Council logo
Between
27 and 29 Jan 2025
Details
View Map
Share
Follow
Rectory Road

Essex County Council are proposing to carry out Highway improvement works on Rectory Road, Hadleigh, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 27 January 2025 and could run through until 29 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 18 Oct 2024 at 12:11.

Essex County Council logo
Between
27 and 29 Jan 2025
Details
View Map
Share
Follow
Dalwood Gardens

Essex County Council are proposing to carry out Highway improvement works on Dalwood Gardens, Hadleigh, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 27 January 2025 and could run through until 29 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 18 Oct 2024 at 12:16.

Essex County Council logo
Between
27 and 29 Jan 2025
Details
View Map
Share
Follow
Daws Heath Road

Essex County Council are proposing to carry out Highway improvement works on Daws Heath Road, Hadleigh, Benfleet.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 27 January 2025 and could run through until 29 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 18 Oct 2024 at 12:15.

Essex County Council logo
Between
27 and 31 Jan 2025
Details
View Map
Share
Follow
Halstow Way

Essex County Council are proposing to carry out Highway improvement works on Halstow Way, Pitsea, Basildon.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 27 January 2025 and could run through until 31 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 15 Oct 2024 at 13:01.

Essex County Council logo
Between
27 and 31 Jan 2025
Details
View Map
Share
Follow
Crest Avenue

Essex County Council are proposing to carry out Highway improvement works on Crest Avenue, Pitsea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 27 January 2025 and could run through until 31 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 15 Oct 2024 at 10:28.

Cadent Gas logo
LONG TERM
Between
27 Jan and 7 Apr 2025
Details
View Map
Share
Follow
Nevendon Road

Cadent Gas are proposing to carry out Utility asset works on Nevendon Road, Wickford.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 27 January 2025 and could run through until 7 April 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 12 Nov 2024 at 12:30.

Southend-on-sea Borough Council logo
Between
28 and 31 Jan 2025
Details
View Map
Share
Follow
Tankerville Drive

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Tankerville Drive, Leigh-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 January 2025 and could run through until 31 January 2025. The works will impact the verge only.

This roadwork event was last updated by Southend-on-sea Borough Council on 11 Sep 2024 at 14:51.

Southend-on-sea Borough Council logo
Between
28 and 31 Jan 2025
Details
View Map
Share
Follow
Tankerville Drive

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Tankerville Drive, Leigh-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 January 2025 and could run through until 31 January 2025. The works will impact the verge only.

This roadwork event was last updated by Southend-on-sea Borough Council on 13 Sep 2024 at 11:45.

Essex County Council logo
Between
3 and 21 Feb 2025
Details
View Map
Share
Follow
Stafford Walk

Essex County Council are proposing to carry out Highway improvement works on Stafford Walk, Canvey Island.

These works are categorised as Major.

The works are not expected to impact the carriageway.

The works will start on or after 3 February 2025 and could run through until 21 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 30 Apr 2024 at 10:48.

Between
3 and 6 Feb 2025
Details
View Map
Share
Follow
Middlesex Avenue

Essex And Suffolk Water are proposing to carry out Utility repair and maintenance works on Middlesex Avenue, Leigh-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 6 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Essex And Suffolk Water on 12 Nov 2024 at 14:59.

Southend-on-sea Borough Council logo
Between
10 and 24 Feb 2025
Details
View Map
Share
Follow
Rochford Road

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Rochford Road, Southend-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 February 2025 and could run through until 24 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Southend-on-sea Borough Council on 11 Nov 2024 at 13:15.

Southend-on-sea Borough Council logo
Between
11 and 25 Feb 2025
Details
View Map
Share
Follow
Marine Parade

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Marine Parade, Leigh-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 11 February 2025 and could run through until 25 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Southend-on-sea Borough Council on 18 Nov 2024 at 12:19.

Southend-on-sea Borough Council logo
Between
13 and 27 Feb 2025
Details
View Map
Share
Follow
Stock Road

Southend-on-sea Borough Council are proposing to carry out Highway repair and maintenance works on Stock Road, Southend-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 February 2025 and could run through until 27 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Southend-on-sea Borough Council on 13 Nov 2024 at 09:55.

Cadent Gas logo
Between
17 Feb and 3 Mar 2025
Details
View Map
Share
Follow
Thisselt Road

Cadent Gas are proposing to carry out Utility asset works on Thisselt Road, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 February 2025 and could run through until 3 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 28 Aug 2024 at 14:16.

Cadent Gas logo
Between
17 Feb and 3 Mar 2025
Details
View Map
Share
Follow
Thisselt Road

Cadent Gas are proposing to carry out Utility asset works on Thisselt Road, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 February 2025 and could run through until 3 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 23 Sep 2024 at 11:28.

Cadent Gas logo
Between
17 Feb and 10 Mar 2025
Details
View Map
Share
Follow
Thisselt Road

Cadent Gas are proposing to carry out Utility asset works on Thisselt Road, Canvey Island.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 February 2025 and could run through until 10 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 15 Nov 2024 at 14:59.

UK Power Networks Eastern & London logo
Between
17 and 23 Feb 2025
Details
View Map
Share
Follow
Bournemouth Park Road

UK Power Networks Eastern & London are proposing to carry out New service connection on Bournemouth Park Road, Southend-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 February 2025 and could run through until 23 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by UK Power Networks Eastern & London on 25 Oct 2024 at 16:47.

UK Power Networks Eastern & London logo
Between
17 and 23 Feb 2025
Details
View Map
Share
Follow
Bournemouth Park Road

UK Power Networks Eastern & London are proposing to carry out New service connection on Bournemouth Park Road, Southend-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 February 2025 and could run through until 23 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by UK Power Networks Eastern & London on 6 Nov 2024 at 10:49.

UK Power Networks Eastern & London logo
Between
17 and 23 Feb 2025
Details
View Map
Share
Follow
Bournemouth Park Road

UK Power Networks Eastern & London are proposing to carry out New service connection on Bournemouth Park Road, Southend-on-sea.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 February 2025 and could run through until 23 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by UK Power Networks Eastern & London on 7 Nov 2024 at 16:00.

Nexfibre Networks Limited logo
Between
17 Feb and 17 Mar 2025
Details
View Map
Share
Follow
Ashingdon Road

Nexfibre Networks Limited are proposing to carry out Utility asset works on Ashingdon Road, Hawkwell.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 17 February 2025 and could run through until 17 March 2025. The works will impact the footway, carriageway and verge.

This roadwork event was last updated by Nexfibre Networks Limited on 15 Nov 2024 at 09:34.


Roadworks Map near to Warwick Road, RAYLEIGH, SS6 8TG

Colour Codes
Planned
In Progress
Completed
Cancelled
Last Updated: 24 Nov 2024 04:39
Notes

  • Any red lines indicate the extent of the works.
  • Clicking on the map will re-centre to the selected point.
  • Within 1 mile, all roadworks are displayed.
  • Within 2-3 miles, standard, urgent and major roadworks are displayed.
  • For 3-5 miles, only major roadworks are shown.
  • The higher the marker number, the further away the roadworks are from the centre of the postcode.
  • Where traffic camera videos or images are shown, no historical versions are retained. Once a new image or video becomes available it overwrites the previous version.

Roadworks Listing near to Warwick Road, RAYLEIGH, SS6 8TG (32 Events)

  • ...
Works Location and Details
Actual Work Date
(Scheduled Dates)
Status
Distance
(miles)
1
URGENT
  
CLARENCE ROAD 
(0.2 miles)
Essex And Suffolk Water
Utility repair and maintenance works - Footway, Carriageway, Verge - Give and take
Complete
21 Nov 2024 12:54 - 23 Nov 2024 09:05
0.2
Details
Share
2
Cadent Gas logo
MAJOR
  
ALBANY ROAD 
(0.2 miles)
Cadent Gas
Utility asset works - Footway - Road closure
Planned
Scheduled: 11 Nov 2024 - 9 Dec 2024
0.2
Details
Share
Follow
3
Cadent Gas logo
MAJOR
  
ALBANY ROAD 
(0.2 miles)
Cadent Gas
Utility asset works - Footway - Road closure
In Progress
Since: 11 Nov 2024 11:12
(Scheduled: 11 Nov 2024 - 9 Dec 2024)
0.2
Details
Share
Follow
4
Cadent Gas logo
MAJOR
  
ALBANY ROAD 
(0.2 miles)
Cadent Gas
Utility asset works - Footway - Road closure
Planned
Scheduled: 11 Nov 2024 - 9 Dec 2024
0.2
Details
Share
Follow
5
Cadent Gas logo
MAJOR
  
CLARENCE ROAD 
(0.3 miles)
Cadent Gas
Utility asset works - Footway - Road closure
Planned
Scheduled: 11 Nov 2024 - 9 Dec 2024
0.3
Details
Share
Follow
6
Cadent Gas logo
MAJOR
  
CLARENCE ROAD 
(0.3 miles)
Cadent Gas
Utility asset works - Footway - Road closure
Planned
Scheduled: 11 Nov 2024 - 9 Dec 2024
0.3
Details
Share
Follow
7
Cadent Gas logo
MAJOR
  
CLARENCE ROAD 
(0.3 miles)
Cadent Gas
Utility asset works - Footway - Road closure
Planned
Scheduled: 11 Nov 2024 - 9 Dec 2024
0.3
Details
Share
Follow
8
Cadent Gas logo
MAJOR
  
CLARENCE ROAD 
(0.3 miles)
Cadent Gas
Utility asset works - Footway - Multi-way signals
In Progress
Since: 11 Nov 2024 11:10
(Scheduled: 11 Nov 2024 - 9 Dec 2024)
0.3
Details
Share
Follow
9
Cadent Gas logo
MAJOR
  
GROVE ROAD 
(0.3 miles)
Cadent Gas
Utility asset works - Footway, Carriageway - Two-way signals
Planned
Scheduled: 11 Nov 2024 - 9 Dec 2024
0.3
Details
Share
Follow
10
Cadent Gas logo
MAJOR
  
GROVE ROAD 
(0.3 miles)
Cadent Gas
Utility asset works - Footway, Carriageway - Two-way signals
Planned
Scheduled: 11 Nov 2024 - 9 Dec 2024
0.3
Details
Share
Follow
  • ...