ROADWORKS SUMMARY
Crown Wood, FOREST ROW, RH18 5FW
Introduction
View current and future planned roadworks and road closures for Crown Wood, RH18 5FW and the surrounding area.
Our roadwork details are constantly updated and reflect the current situation and we offer both a map view and a listing. We also highlight the major and significant roadworks occuring near to you help you avoid the worst of the delays to your journey.
The roadworks shown below show all current and proposed works during the next 90 days and historical data is recorded since July 2020.
Please note that we re-publish this data and cannot provide any additional information pertaining to a roadwork event. If you require more information, please contact the organisation carrying out the work.
Data are provided by the Department for Transport.
Have we helped today?
If we have helped you today, please consider buying us a quick coffee to keep us going!
Major Roadworks near to Crown Wood, FOREST ROW, RH18 5FW
Details of major roadworks, currently in progress or starting soon and resulting in road closures and/or traffic signal management for Crown Wood are shown here covering a 5 mile radius. See further down for details of all roadworks in your area.
1 Nov 2024 and 6 Jan 2025
Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Aviemore Road, Crowborough.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 1 November 2024 and could run through until 6 January 2025. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Southern Gas Networks on 18 Sep 2024 at 13:53.
17 Jan 2025
Southern Gas Networks are carrying out Utility repair and maintenance works on Warren Road, Crowborough.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 8 November 2024 at 15:45 and could run through until 17 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Southern Gas Networks on 17 Dec 2024 at 12:11.
3 Dec 2024 and 6 Jan 2025
Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Rannoch Road, Crowborough.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 3 December 2024 and could run through until 6 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Southern Gas Networks on 1 Oct 2024 at 16:29.
6 Jan and 20 Feb 2025
Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Aviemore Road, Crowborough.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 20 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Southern Gas Networks on 17 Dec 2024 at 10:52.
21 and 23 Jan 2025
South East Water are proposing to carry out Remedial works on Priory Road, Forest Row.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 January 2025 and could run through until 23 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by South East Water on 31 Oct 2024 at 10:44.
21 and 23 Jan 2025
South East Water are proposing to carry out New service connection on Priory Road, Forest Row.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 January 2025 and could run through until 23 January 2025. The works will impact the carriageway and verge.
This roadwork event was last updated by South East Water on 10 Dec 2024 at 12:40.
21 and 23 Jan 2025
South East Water are proposing to carry out New service connection on Priory Road, Forest Row.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 January 2025 and could run through until 23 January 2025. The works will impact the carriageway and verge.
This roadwork event was last updated by South East Water on 9 Oct 2024 at 12:15.
27 Jan and 21 Feb 2025
Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Castlefields, Hartfield.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 21 February 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Southern Gas Networks on 15 Oct 2024 at 14:28.
27 Jan and 8 Feb 2025
East Sussex County Council are proposing to carry out Highway repair and maintenance works on Hartfield Road, Forest Row.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 8 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by East Sussex County Council on 11 Oct 2024 at 10:06.
3 and 14 Feb 2025
East Sussex County Council are proposing to carry out Highway repair and maintenance works on Black Hill, Crowborough.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 14 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by East Sussex County Council on 8 Oct 2024 at 14:24.
3 and 14 Feb 2025
East Sussex County Council are proposing to carry out Highway repair and maintenance works on Church Hill, Crowborough.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 February 2025 and could run through until 14 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by East Sussex County Council on 8 Oct 2024 at 14:24.
3 Feb and 21 Mar 2025
East Sussex County Council were proposing to carry out Highway repair and maintenance works on Harts Lane, Hartfield.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 3 February 2025 and run through until 21 March 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by East Sussex County Council on 4 Dec 2024 at 13:31.
5 and 10 Feb 2025
West Sussex County Council are proposing to carry out Highway repair and maintenance works on Lingfield Road, East Grinstead.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 5 February 2025 and could run through until 10 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by West Sussex County Council on 8 Nov 2024 at 11:30.
17 Feb and 15 Mar 2025
East Sussex County Council are proposing to carry out Highway repair and maintenance works on Hartfield Road, Forest Row.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 February 2025 and could run through until 15 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by East Sussex County Council on 4 Dec 2024 at 09:53.
20 Feb and 20 Mar 2025
Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Rannoch Road, Crowborough.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 20 February 2025 and could run through until 20 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Southern Gas Networks on 17 Dec 2024 at 11:30.
20 and 24 Feb 2025
South East Water are proposing to carry out New service connection on Hartfield Road, Cowden.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 February 2025 and could run through until 24 February 2025. The works will impact the carriageway and verge.
This roadwork event was last updated by South East Water on 11 Dec 2024 at 14:52.
24 Feb and 7 Mar 2025
West Sussex County Council are proposing to carry out Highway improvement works on Vicarage Walk, East Grinstead.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 7 March 2025. The works will impact the footway and footpath.
This roadwork event was last updated by West Sussex County Council on 13 Dec 2024 at 10:39.
24 Feb and 7 Mar 2025
West Sussex County Council are proposing to carry out Highway improvement works on Vicarage Walk, East Grinstead.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 7 March 2025. The works will impact the footway and footpath.
This roadwork event was last updated by West Sussex County Council on 20 Dec 2024 at 10:23.
24 Feb and 7 Mar 2025
West Sussex County Council were proposing to carry out Highway improvement works on Vicarage Walk, East Grinstead.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 24 February 2025 and run through until 7 March 2025. The works were due to impact the footway and footpath.
This roadwork event was last updated by West Sussex County Council on 27 Nov 2024 at 16:00.
24 and 26 Feb 2025
South East Water are proposing to carry out New service connection on Hartfield Road, Forest Row.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 26 February 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by South East Water on 8 Nov 2024 at 11:05.
24 and 26 Feb 2025
South East Water are proposing to carry out New service connection on Hartfield Road, Forest Row.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 24 February 2025 and could run through until 26 February 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by South East Water on 25 Nov 2024 at 15:38.
3 and 28 Mar 2025
Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Castlefields, Hartfield.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 3 March 2025 and could run through until 28 March 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Southern Gas Networks on 21 Oct 2024 at 13:35.
3 and 28 Mar 2025
Southern Gas Networks are proposing to carry out Utility repair and maintenance works on Castlefields, Hartfield.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 3 March 2025 and could run through until 28 March 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Southern Gas Networks on 15 Nov 2024 at 10:43.
4 and 11 Mar 2025
West Sussex County Council are proposing to carry out Highway improvement works on Beeching Way, East Grinstead.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 4 March 2025 and could run through until 11 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by West Sussex County Council on 12 Dec 2024 at 09:30.
10 and 20 Mar 2025
East Sussex County Council are proposing to carry out Highway repair and maintenance works on Whitehouse Lane, Crowborough.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 10 March 2025 and could run through until 20 March 2025. The works will impact the carriageway and verge.
This roadwork event was last updated by East Sussex County Council on 19 Dec 2024 at 12:04.
10 and 20 Mar 2025
East Sussex County Council were proposing to carry out Highway repair and maintenance works on Whitehouse Lane, Crowborough.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 10 March 2025 and run through until 20 March 2025. The works were due to impact the carriageway and verge.
This roadwork event was last updated by East Sussex County Council on 19 Dec 2024 at 12:03.
10 and 12 Mar 2025
West Sussex County Council were proposing to carry out Highway repair and maintenance works on Holtye Road, East Grinstead.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 10 March 2025 and run through until 12 March 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by West Sussex County Council on 5 Dec 2024 at 14:09.
11 and 13 Mar 2025
West Sussex County Council are proposing to carry out Highway repair and maintenance works on Holtye Road, East Grinstead.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 March 2025 and could run through until 13 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by West Sussex County Council on 9 Dec 2024 at 14:24.
17 and 28 Mar 2025
East Sussex County Council are proposing to carry out Highway repair and maintenance works on Priory Road, Forest Row.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 March 2025 and could run through until 28 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by East Sussex County Council on 17 Dec 2024 at 14:27.
17 and 26 Mar 2025
Southern Gas Networks were proposing to carry out New service connection on Warren Road, Crowborough.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 17 March 2025 and run through until 26 March 2025. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by Southern Gas Networks on 18 Dec 2024 at 07:40.
18 and 20 Mar 2025
South East Water are proposing to carry out Utility repair and maintenance works on Chelwood Gate Road, Nutley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 March 2025 and could run through until 20 March 2025. The works will impact the verge only.
This roadwork event was last updated by South East Water on 20 Dec 2024 at 16:01.
19 and 22 Mar 2025
East Sussex County Council are proposing to carry out Highway repair and maintenance works on Beacon Road, Crowborough.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 19 March 2025 and could run through until 22 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by East Sussex County Council on 20 Dec 2024 at 13:52.
24 and 28 Mar 2025
UK Power Networks South Eastern are proposing to carry out New service connection on High Street, Hartfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 24 March 2025 and could run through until 28 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by UK Power Networks South Eastern on 13 Dec 2024 at 11:38.
24 and 26 Mar 2025
East Sussex County Council are proposing to carry out Highway repair and maintenance works on High Street, Nutley.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 24 March 2025 and could run through until 26 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by East Sussex County Council on 20 Dec 2024 at 14:36.
25 Mar and 8 Apr 2025
Energy Assets Networks (formerly Utility Distribution Networks) were proposing to carry out New service connection on Beeching Way, East Grinstead.
These works were categorised as Major.
A lane was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 25 March 2025 and run through until 8 April 2025. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by Energy Assets Networks (formerly Utility Distribution Networks) on 11 Dec 2024 at 10:48.
25 Mar and 8 Apr 2025
Energy Assets Networks (formerly Utility Distribution Networks) were proposing to carry out New service connection on London Road, East Grinstead.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 25 March 2025 and run through until 8 April 2025. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by Energy Assets Networks (formerly Utility Distribution Networks) on 11 Dec 2024 at 10:48.
Roadworks Map near to Crown Wood, FOREST ROW, RH18 5FW
- Any red lines indicate the extent of the works.
- Clicking on the map will re-centre to the selected point.
- Within 1 mile, all roadworks are displayed.
- Within 2-3 miles, standard, urgent and major roadworks are displayed.
- For 3-5 miles, only major roadworks are shown.
- The higher the marker number, the further away the roadworks are from the centre of the postcode.
- Where traffic camera videos or images are shown, no historical versions are retained. Once a new image or video becomes available it overwrites the previous version.
Roadworks Listing near to Crown Wood, FOREST ROW, RH18 5FW (1 Events)
(Scheduled Dates)
(miles)
(Scheduled: 11 Nov 2024 - 17 Jan 2025)
Contains public sector information licensed under the Open Government Licence v3.0.