ROADWORKS SUMMARY
Algers Road, LOUGHTON, IG10 4NG
Introduction
View current and future planned roadworks and road closures for Algers Road, IG10 4NG and the surrounding area.
Our roadwork details are constantly updated and reflect the current situation and we offer both a map view and a listing. We also highlight the major and significant roadworks occuring near to you help you avoid the worst of the delays to your journey.
The roadworks shown below show all current and proposed works during the next 90 days and historical data is recorded since July 2020.
Please note that we re-publish this data and cannot provide any additional information pertaining to a roadwork event. If you require more information, please contact the organisation carrying out the work.
Data are provided by the Department for Transport.
Have we helped today?
If we have helped you today, please consider buying us a quick coffee to keep us going!
Major Roadworks near to Algers Road, LOUGHTON, IG10 4NG
Details of major roadworks, currently in progress or starting soon and resulting in road closures and/or traffic signal management for Algers Road are shown here covering a 5 mile radius. See further down for details of all roadworks in your area.
4 May 2026
Essex County Council are carrying out Highway improvement works on Station Way, Buckhurst Hill.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 13 April 2023 at 08:33 and could run through until 4 May 2026. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 12 Jul 2024 at 07:13.
31 Dec 2024
London Borough Of Redbridge are carrying out Highway repair and maintenance works on Broadmead Road, Woodford Green.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 14 July 2023 at 07:34 and could run through until 31 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Redbridge on 17 Jun 2024 at 12:01.
30 Nov 2024
London Borough Of Enfield are carrying out Section 50 on Hertford Road, Edmonton.
These works are categorised as Major.
The works started on 1 August 2023 at 08:00 and could run through until 30 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Enfield on 15 Oct 2024 at 17:38.
14 Dec 2024
London Borough Of Enfield are carrying out Section 50 on Angel Walk, London.
These works are categorised as Major.
The works started on 13 January 2024 at 09:00 and could run through until 14 December 2024. The works will impact the verge, cycleway and footpath.
This roadwork event was last updated by London Borough Of Enfield on 17 Oct 2024 at 15:45.
20 Dec 2024
Thames Water are carrying out Utility asset works on Erskine Road, Walthamstow.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 28 May 2024 at 09:25 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 28 Oct 2024 at 16:07.
22 Nov 2024
Thames Water are carrying out Utility asset works on Melville Road, Walthamstow.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 16 July 2024 at 08:20 and could run through until 22 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 3 Sep 2024 at 15:55.
13 Dec 2024
Thames Water are carrying out Utility asset works on Fyfield Road, Walthamstow.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 22 July 2024 at 09:30 and could run through until 13 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 4 Oct 2024 at 13:28.
Monday
Cadent Gas are carrying out Utility asset works on Lambourne Road, Chigwell Town, Chigwell.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 22 July 2024 at 17:18 and could run through until 4 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 28 Aug 2024 at 12:09.
17 Nov 2024
Thames Water are carrying out Utility asset works on Eagle Lane, Wanstead, London.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 29 July 2024 at 08:48 and could run through until 17 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 24 Oct 2024 at 14:45.
29 Jul 2024 and 31 Jan 2025
London Borough Of Enfield are proposing to carry out Highway improvement works on Leeside Road, Tottenham, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 29 July 2024 and could run through until 31 January 2025. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by London Borough Of Enfield on 28 Jun 2024 at 14:16.
31 Jan 2025
London Borough Of Enfield are carrying out Highway improvement works on Meridian Way, Edmonton.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 29 July 2024 at 08:00 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Enfield on 9 Oct 2024 at 09:36.
29 Jul 2024 and 31 Jan 2025
London Borough Of Enfield are proposing to carry out Highway improvement works on Glover Drive, Edmonton.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 29 July 2024 and could run through until 31 January 2025. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by London Borough Of Enfield on 4 Jul 2024 at 15:51.
13 Dec 2024
Thames Water are carrying out roadworks on Avon Road, Walthamstow.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 14 August 2024 at 09:30 and could run through until 13 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 2 Oct 2024 at 09:01.
6 Jan 2025
Thames Water are carrying out Utility asset works on Beacontree Avenue, Walthamstow.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 2 September 2024 at 08:00 and could run through until 6 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 24 Oct 2024 at 15:08.
Tomorrow
London Borough Of Waltham Forest are proposing to carry out Highway repair and maintenance works on Spruce Hills Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 September 2024 and could run through until 31 October 2024. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by London Borough Of Waltham Forest on 31 Jul 2024 at 13:03.
15 Nov 2024
Cadent Gas are carrying out Utility asset works on Inglehurst Gardens, Ilford.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 6 September 2024 at 13:00 and could run through until 15 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 6 Sep 2024 at 13:11.
3 Sep 2024 and 4 Sep 2025
Essex County Council were proposing to carry out Highway improvement works on High Street, Epping Town, Epping.
These works were categorised as Major.
A lane was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 3 September 2024 and run through until 4 September 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Essex County Council on 12 Aug 2024 at 09:26.
9 Sep and 6 Dec 2024
Hertfordshire County Council are proposing to carry out Highway improvement works on Monarchs Way, Waltham Cross.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 September 2024 and could run through until 6 December 2024. The works will impact the footway and carriageway.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Hertfordshire County Council on 16 Sep 2024 at 12:27.
6 Dec 2024
Hertfordshire County Council are carrying out Highway improvement works on Monarchs Way, Waltham Cross.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 9 September 2024 at 07:00 and could run through until 6 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Hertfordshire County Council on 16 Sep 2024 at 13:40.
23 Sep and 8 Nov 2024
Cadent Gas were proposing to carry out Utility asset works on Perth Road, Gants Hill, Ilford.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 23 September 2024 and run through until 8 November 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 17 Sep 2024 at 16:01.
Friday
Cadent Gas are carrying out Utility asset works on Cocker Road, Enfield.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 23 September 2024 at 15:47 and could run through until 1 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 23 Oct 2024 at 14:45.
13 Dec 2024
Thames Water are carrying out Utility asset works on Carnanton Road, Walthamstow.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 24 September 2024 at 08:20 and could run through until 13 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 16 Oct 2024 at 14:36.
22 Nov 2024
Thames Water are carrying out Utility asset works on Borwick Avenue, Walthamstow.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 26 September 2024 at 08:30 and could run through until 22 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 23 Oct 2024 at 14:49.
Monday
Thames Water are carrying out Utility asset works on Lytton Avenue, Enfield.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 26 September 2024 at 10:30 and could run through until 4 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 24 Oct 2024 at 10:21.
Friday
Thames Water are proposing to carry out Utility asset works on South Countess Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 September 2024 and could run through until 1 November 2024. The works will impact the carriageway only.
*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.
This roadwork event was last updated by Thames Water on 26 Sep 2024 at 10:44.
8 Nov 2024
Thames Water are carrying out Utility asset works on South Countess Road, Walthamstow.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 28 September 2024 at 08:05 and could run through until 8 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 23 Oct 2024 at 15:05.
Friday
Thames Water are proposing to carry out Utility asset works on Forest Road, Walthamstow.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 30 September 2024 and could run through until 1 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 18 Sep 2024 at 15:14.
Friday
Thames Water are proposing to carry out Utility asset works on Borwick Avenue, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 30 September 2024 and could run through until 1 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 18 Sep 2024 at 10:27.
19 Dec 2024
Cadent Gas are carrying out Utility asset works on Bedford Road, South Woodford, London.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 4 October 2024 at 11:39 and could run through until 19 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 25 Oct 2024 at 16:30.
30 Sep and 13 Dec 2024
Thames Water are proposing to carry out Utility asset works on Pentire Road, Walthamstow.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 30 September 2024 and could run through until 13 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 12 Sep 2024 at 09:43.
30 Sep 2024 and 20 Mar 2025
London Borough Of Enfield were proposing to carry out Highway improvement works on Harbet Road, Edmonton.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 30 September 2024 and run through until 20 March 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Enfield on 15 Aug 2024 at 15:29.
30 Sep 2024 and 20 Jul 2025
London Borough Of Enfield are proposing to carry out Highway improvement works on Harbet Road, Edmonton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 30 September 2024 and could run through until 20 July 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Enfield on 21 Aug 2024 at 13:15.
6 Oct and 16 Dec 2024
Thames Water are proposing to carry out Utility asset works on Hillcrest Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 October 2024 and could run through until 16 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 23 Apr 2024 at 11:54.
6 Oct and 20 Dec 2024
Thames Water are proposing to carry out Utility asset works on Carnanton Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 October 2024 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 23 Apr 2024 at 11:54.
7 Oct and 22 Nov 2024
Transport for London (TfL) are proposing to carry out Highway improvement works on North Circular Road, Wanstead, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 7 October 2024 and could run through until 22 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Transport for London (TfL) on 13 Aug 2024 at 11:16.
7 Oct and 22 Nov 2024
Transport for London (TfL) are proposing to carry out Highway improvement works on North Circular Road, Wanstead, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 7 October 2024 and could run through until 22 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Transport for London (TfL) on 17 Sep 2024 at 09:56.
22 Nov 2024
Transport for London (TfL) are carrying out Highway improvement works on North Circular Road, Wanstead, London.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 7 October 2024 at 08:00 and could run through until 22 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Transport for London (TfL) on 8 Oct 2024 at 09:45.
7 Oct and 22 Nov 2024
Transport for London (TfL) are proposing to carry out Highway improvement works on Eastern Avenue, Ilford.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 7 October 2024 and could run through until 22 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Transport for London (TfL) on 13 Aug 2024 at 11:15.
7 Oct and 22 Nov 2024
Transport for London (TfL) are proposing to carry out Highway improvement works on Eastern Avenue, Ilford.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 7 October 2024 and could run through until 22 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Transport for London (TfL) on 17 Sep 2024 at 09:49.
22 Nov 2024
Transport for London (TfL) are carrying out Highway improvement works on Eastern Avenue, Ilford.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 7 October 2024 at 08:00 and could run through until 22 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Transport for London (TfL) on 8 Oct 2024 at 09:44.
7 Oct and 18 Nov 2024
Thames Water were proposing to carry out Utility asset works on Winsbeach, Walthamstow.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 7 October 2024 and run through until 18 November 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 16 Oct 2024 at 10:14.
7 Oct and 25 Nov 2024
Thames Water are proposing to carry out Utility asset works on Marrilyne Avenue, Enfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 7 October 2024 and could run through until 25 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 27 Mar 2024 at 11:34.
Monday
Thames Water are carrying out Utility repair and maintenance works on Brook Road, Epping Town, Epping.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 11 October 2024 at 10:00 and could run through until 4 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 28 Oct 2024 at 08:32.
14 Oct and 11 Nov 2024
Cadent Gas are proposing to carry out Utility asset works on Nutter Lane, Wanstead, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 14 October 2024 and could run through until 11 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 11 Jun 2024 at 07:49.
14 Oct and 11 Nov 2024
Cadent Gas are proposing to carry out Utility asset works on Nutter Lane, Wanstead, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 14 October 2024 and could run through until 11 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 20 Aug 2024 at 11:08.
Friday
London Borough Of Redbridge are carrying out Highway improvement works on Roding Lane North, Woodford Green.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 14 October 2024 at 20:00 and could run through until 1 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Redbridge on 30 Oct 2024 at 08:45.
14 Oct and 8 Nov 2024
Essex County Council are proposing to carry out Highway improvement works on Broadfield Way, Buckhurst Hill.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 14 October 2024 and could run through until 8 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 26 Jul 2024 at 10:41.
14 Oct and 8 Nov 2024
Essex County Council are proposing to carry out Highway improvement works on Field Close, Buckhurst Hill.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 14 October 2024 and could run through until 8 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 26 Jul 2024 at 10:43.
14 Oct and 11 Nov 2024
London Borough Of Enfield are proposing to carry out Highway improvement works on Brick Lane, Enfield.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 14 October 2024 and could run through until 11 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Enfield on 9 Oct 2024 at 15:47.
11 Nov 2024
London Borough Of Enfield are carrying out Highway improvement works on Brick Lane, Enfield.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 14 October 2024 at 08:00 and could run through until 11 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Enfield on 16 Oct 2024 at 14:40.
Sunday
Thames Water were proposing to carry out Utility repair and maintenance works on Chingford Road, Chingford.
These works were categorised as Major.
Two-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 18 October 2024 and run through until 3 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Thames Water on 2 Oct 2024 at 12:57.
Sunday
Thames Water were proposing to carry out Utility repair and maintenance works on Rushcroft Road, Chingford.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 18 October 2024 and run through until 3 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Thames Water on 2 Oct 2024 at 12:59.
Tomorrow
Thames Water are carrying out roadworks on Woodgreen Road, Waltham Abbey Town, Waltham Abbey.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 18 October 2024 at 20:22 and could run through until 31 October 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 29 Oct 2024 at 11:20.
11 Nov 2024
Cadent Gas are carrying out Utility asset works on Nutter Lane, Wanstead, London.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 21 October 2024 at 10:54 and could run through until 11 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 22 Oct 2024 at 11:24.
21 Oct and 7 Nov 2024
Cadent Gas are proposing to carry out Utility asset works on Woodford Road, South Woodford, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 21 October 2024 and could run through until 7 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 29 Jul 2024 at 14:04.
21 Oct and 7 Nov 2024
Cadent Gas are proposing to carry out Utility asset works on Woodford Road, South Woodford, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 21 October 2024 and could run through until 7 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 6 Aug 2024 at 10:41.
21 Oct and 18 Nov 2024
Thames Water are proposing to carry out Utility asset works on Winsbeach, Walthamstow.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 21 October 2024 and could run through until 18 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 16 Oct 2024 at 11:30.
18 Nov 2024
Thames Water are carrying out Utility asset works on Winsbeach, Walthamstow.
These works are categorised as Major.
Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 21 October 2024 at 08:01 and could run through until 18 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 21 Oct 2024 at 08:01.
Tuesday
Thames Water are carrying out Utility asset works on Winsbeach, Walthamstow.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 21 October 2024 at 09:20 and could run through until 5 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 21 Oct 2024 at 09:55.
Tuesday
Thames Water are carrying out Utility asset works on Forest Road, Walthamstow.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 21 October 2024 at 09:20 and could run through until 5 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 21 Oct 2024 at 09:55.
Tuesday
Thames Water are carrying out Utility asset works on Woodstock Road, Walthamstow.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 21 October 2024 at 09:20 and could run through until 5 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 21 Oct 2024 at 09:57.
21 Oct and 18 Nov 2024
Cadent Gas were proposing to carry out Utility asset works on Lambourne Road, Chigwell Town, Chigwell.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 21 October 2024 and run through until 18 November 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 4 Sep 2024 at 16:04.
21 Oct and 18 Nov 2024
Cadent Gas are proposing to carry out Utility asset works on Lambourne Road, Chigwell Town, Chigwell.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 21 October 2024 and could run through until 18 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 27 Sep 2024 at 09:23.
21 Oct and 18 Nov 2024
Cadent Gas were proposing to carry out Utility asset works on Lambourne Road, Chigwell Town, Chigwell.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 21 October 2024 and run through until 18 November 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 16 Oct 2024 at 11:20.
Today
Thames Water are carrying out Statutory Infrastructure Works on Simmons Lane, Chingford.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 24 October 2024 at 09:45 and could run through until 30 October 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 24 Oct 2024 at 10:25.
21 Oct and 8 Nov 2024
ESP Electricity are proposing to carry out Utility asset works on Rayfield, Epping Town, Epping.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 21 October 2024 and could run through until 8 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by ESP Electricity on 22 Oct 2024 at 14:56.
22 Oct 2024 and 5 Apr 2025
Thames Water were proposing to carry out Utility asset works on Station Road, Chingford.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 22 October 2024 and run through until 5 April 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 6 Aug 2024 at 08:31.
22 Oct and 6 Dec 2024
Hertfordshire County Council are proposing to carry out Highway improvement works on Stanhope Road, Waltham Cross.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 22 October 2024 and could run through until 6 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Hertfordshire County Council on 18 Oct 2024 at 10:57.
6 Dec 2024
Hertfordshire County Council are carrying out Highway improvement works on Stanhope Road, Waltham Cross.
These works are categorised as Major.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 22 October 2024 at 21:00 and could run through until 6 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Hertfordshire County Council on 23 Oct 2024 at 10:29.
24 Oct and 29 Nov 2024
Thames Water are proposing to carry out Disconnection or alteration of supply on Cecil Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 24 October 2024 and could run through until 29 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 30 Jan 2024 at 14:08.
24 Oct and 13 Nov 2024
Cadent Gas are proposing to carry out Utility asset works on Canterbury Close, Chigwell Town, Chigwell.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 24 October 2024 and could run through until 13 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 21 Oct 2024 at 15:47.
Today
Thames Water are carrying out Utility repair and maintenance works on Lambourne Road, Chigwell Town, Chigwell.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 24 October 2024 at 13:26 and could run through until 30 October 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 24 Oct 2024 at 15:25.
Today
Thames Water were proposing to carry out Utility repair and maintenance works on Lambourne Road, Chigwell Town, Chigwell.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 24 October 2024 and run through until 30 October 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Thames Water on 29 Oct 2024 at 10:24.
Today
Cadent Gas are carrying out roadworks on Beaconsfield Road, Enfield.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 24 October 2024 at 14:51 and could run through until 30 October 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 28 Oct 2024 at 08:42.
Today
Cadent Gas are carrying out Utility repair and maintenance works on Ordnance Road, Enfield.
Two-way signals are to be in place for some or all of the period and could cause delays to journeys.
The works started on 24 October 2024 at 14:44 and could run through until 30 October 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 28 Oct 2024 at 08:43.
25 Oct and 19 Nov 2024
Transport for London (TfL) are proposing to carry out Highway improvement works on Eastern Avenue, Ilford.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 October 2024 and could run through until 19 November 2024. The works will impact the verge only.
This roadwork event was last updated by Transport for London (TfL) on 28 Jun 2024 at 14:54.
25 Oct and 19 Nov 2024
Transport for London (TfL) are proposing to carry out Highway improvement works on Eastern Avenue, Ilford.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 October 2024 and could run through until 19 November 2024. The works will impact the verge only.
This roadwork event was last updated by Transport for London (TfL) on 28 Aug 2024 at 15:46.
Saturday
London Borough Of Enfield are proposing to carry out Section 50 on Hertford Road, Edmonton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 26 October 2024 and could run through until 2 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Enfield on 3 Sep 2024 at 12:46.
Saturday
London Borough Of Enfield are proposing to carry out Section 50 on Hertford Road, Edmonton.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 26 October 2024 and could run through until 2 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Enfield on 3 Sep 2024 at 12:53.
28 Oct and 19 Nov 2024
Transport for London (TfL) are proposing to carry out Highway improvement works on Eastern Avenue, Ilford.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 October 2024 and could run through until 19 November 2024. The works will impact the verge only.
This roadwork event was last updated by Transport for London (TfL) on 23 Sep 2024 at 11:14.
28 Oct and 13 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on The Avenue, Wanstead, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 October 2024 and could run through until 13 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 15 Oct 2024 at 09:45.
28 Oct and 13 Nov 2024
Thames Water were proposing to carry out Utility asset works on Manor Road, Chigwell Town, Chigwell.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 28 October 2024 and run through until 13 November 2024. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by Thames Water on 30 Aug 2024 at 14:15.
28 Oct and 17 Nov 2024
Cadent Gas are proposing to carry out Utility asset works on Vicarage Lane, Chigwell Town, Chigwell.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 28 October 2024 and could run through until 17 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 27 Sep 2024 at 09:21.
Friday
Thames Water were proposing to carry out Utility repair and maintenance works on Old Church Road, Chingford.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 28 October 2024 and run through until 1 November 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 10 Sep 2024 at 10:51.
Saturday
Thames Water are proposing to carry out New service connection on Chester Road, Edmonton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 October 2024 and could run through until 2 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 9 Aug 2024 at 15:41.
Saturday
Thames Water are carrying out New service connection on Chester Road, Edmonton.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 28 October 2024 at 09:04 and could run through until 2 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 28 Oct 2024 at 09:24.
19 Nov 2024
Thames Water are carrying out Utility asset works on Carbis Close, Chingford.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 30 October 2024 at 07:00 and could run through until 19 November 2024. The works will impact the footway, carriageway and footpath.
This roadwork event was last updated by Thames Water on 30 Oct 2024 at 07:17.
Tomorrow
UK Power Networks Eastern & London are proposing to carry out Utility repair and maintenance works on Manor Road, Lambourne, Epping.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 October 2024 and could run through until 31 October 2024. The works will impact the verge only.
This roadwork event was last updated by UK Power Networks Eastern & London on 9 Aug 2024 at 08:42.
Tomorrow
UK Power Networks Eastern & London are proposing to carry out Utility repair and maintenance works on Manor Road, Lambourne, Epping.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 October 2024 and could run through until 31 October 2024. The works will impact the verge only.
This roadwork event was last updated by UK Power Networks Eastern & London on 9 Sep 2024 at 08:32.
Tomorrow
UK Power Networks Eastern & London were proposing to carry out Utility repair and maintenance works on Manor Road, Lambourne, Epping.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 28 October 2024 and run through until 31 October 2024. The works were due to impact the verge only.
This roadwork event was last updated by UK Power Networks Eastern & London on 16 Sep 2024 at 09:14.
28 Oct and 8 Nov 2024
London Borough Of Enfield are proposing to carry out Highway improvement works on Brick Lane, Enfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 October 2024 and could run through until 8 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Enfield on 25 Oct 2024 at 09:07.
28 Oct and 8 Nov 2024
London Borough Of Enfield are proposing to carry out Highway improvement works on Brick Lane, Enfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 October 2024 and could run through until 8 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Enfield on 25 Oct 2024 at 09:19.
Sunday
Thames Water were proposing to carry out Utility asset works on Platts Road, Enfield.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 28 October 2024 and run through until 3 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Thames Water on 21 Aug 2024 at 08:42.
Sunday
Thames Water are proposing to carry out Utility asset works on Platts Road, Enfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 October 2024 and could run through until 3 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 28 Aug 2024 at 08:56.
Friday
Thames Water are proposing to carry out New service connection on Oatlands Road, Enfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 28 October 2024 and could run through until 1 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 25 Jul 2024 at 13:50.
Friday
Thames Water were proposing to carry out New service connection on Oatlands Road, Enfield.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 28 October 2024 and run through until 1 November 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 22 Oct 2024 at 11:13.
28 Oct and 26 Nov 2024
Essex County Council are proposing to carry out Highway improvement works on Chequers Walk, Waltham Abbey Town, Waltham Abbey.
These works are categorised as Major.
There will be no traffic signals or road closures necessary for these works and traffic will operate on a give-and-take basis.
The works will start on or after 28 October 2024 and could run through until 26 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 21 Aug 2024 at 15:25.
Tomorrow
National Highways are proposing to carry out Works for road purposes on Charlie Brown's Roundabout, Wanstead, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 29 October 2024 and could run through until 31 October 2024. The works will impact the carriageway only.
This roadwork event was last updated by National Highways on 1 Oct 2024 at 09:29.
National Highways carried out Works for road purposes on Charlie Brown's Roundabout, Wanstead, London.
These works were categorised as Major.
The road was closed for some or all of the period.
The works were originally planned between 29 Oct 2024 and 31 Oct 2024 and were actually completed between 29 Oct 2024 (22:00) and 30 Oct 2024 (04:30). The works impacted the carriageway only.
This roadwork event was last updated by National Highways on 30 Oct 2024 at 09:43.
Tomorrow
National Highways were proposing to carry out Works for road purposes on Charlie Brown's Roundabout, Wanstead, London.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 29 October 2024 and run through until 31 October 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by National Highways on 2 Oct 2024 at 13:10.
Monday
Thames Water are carrying out Utility repair and maintenance works on Deepdene Road, Loughton Town, Loughton.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 29 October 2024 at 08:45 and could run through until 4 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 29 Oct 2024 at 10:55.
Tomorrow
Essex County Council are proposing to carry out Highway improvement works on Abridge Road, Theydon Bois, Epping.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 29 October 2024 and could run through until 31 October 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 5 Sep 2024 at 14:42.
6 Nov 2024
Essex County Council are carrying out Highway improvement works on Palace Gardens, Buckhurst Hill.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 30 October 2024 at 09:05 and could run through until 6 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 30 Oct 2024 at 09:12.
Saturday
Thames Water are proposing to carry out New service connection on Borders Lane, Loughton Town, Loughton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 30 October 2024 and could run through until 2 November 2024. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Thames Water on 19 Aug 2024 at 12:00.
Saturday
Thames Water are carrying out New service connection on Borders Lane, Loughton Town, Loughton.
These works are categorised as Major.
The road is closed for some or all of the period and could cause delays to journeys.
The works started on 30 October 2024 at 08:30 and could run through until 2 November 2024. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Thames Water on 30 Oct 2024 at 10:08.
Saturday
Essex County Council are proposing to carry out Highway improvement works on Abridge Road, Theydon Bois, Epping.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 30 October 2024 and could run through until 2 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 14 Oct 2024 at 14:16.
Today
Thames Water are carrying out Utility repair and maintenance works on Highbridge Street, Waltham Abbey Town, Waltham Abbey.
The road is closed for some or all of the period and could cause delays to journeys.
The works are scheduled for 30 October 2024 and are due to last for only one day. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 30 Oct 2024 at 13:43.
Monday
Thames Water are proposing to carry out Utility repair and maintenance works on Hollybush Hill, Wanstead, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 31 October 2024 and could run through until 4 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 8 Oct 2024 at 12:45.
Monday
Thames Water are proposing to carry out Utility repair and maintenance works on Hollybush Hill, Wanstead, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 31 October 2024 and could run through until 4 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 9 Oct 2024 at 11:00.
Monday
Thames Water are proposing to carry out Utility repair and maintenance works on Hollybush Hill, Wanstead, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 31 October 2024 and could run through until 4 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 9 Oct 2024 at 15:00.
Saturday
Essex County Council were proposing to carry out Remedial works on Volunteer Roundabout, Waltham Abbey Town, Waltham Abbey.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 31 October 2024 and run through until 2 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Essex County Council on 8 Oct 2024 at 16:06.
Saturday
Essex County Council were proposing to carry out Highway repair and maintenance works on M25 J26 Leave W, Epping Forest.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 31 October 2024 and run through until 2 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Essex County Council on 8 Oct 2024 at 16:02.
1 Nov and 6 Dec 2024
Thames Water are proposing to carry out Utility asset works on Forest Road, Walthamstow.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 1 November 2024 and could run through until 6 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 16 Oct 2024 at 12:35.
1 Nov and 6 Dec 2024
Thames Water are proposing to carry out Utility asset works on Forest Road, Walthamstow.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 1 November 2024 and could run through until 6 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 23 Oct 2024 at 15:40.
1 Nov and 6 Dec 2024
Thames Water are proposing to carry out Utility asset works on Rosebank Grove, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 November 2024 and could run through until 6 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 16 Oct 2024 at 12:38.
1 Nov and 6 Dec 2024
Thames Water are proposing to carry out Utility asset works on Rosebank Grove, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 1 November 2024 and could run through until 6 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 23 Oct 2024 at 15:41.
4 and 27 Nov 2024
Transport for London (TfL) are proposing to carry out Highway improvement works on North Circular Road, Wanstead, London.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 4 November 2024 and could run through until 27 November 2024. The works will impact the verge only.
This roadwork event was last updated by Transport for London (TfL) on 28 Jun 2024 at 14:56.
4 and 27 Nov 2024
Transport for London (TfL) are proposing to carry out Highway improvement works on North Circular Road, Wanstead, London.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 4 November 2024 and could run through until 27 November 2024. The works will impact the verge only.
This roadwork event was last updated by Transport for London (TfL) on 28 Aug 2024 at 15:41.
4 Nov and 2 Dec 2024
Thames Water are proposing to carry out Utility asset works on Hillside Gardens, Walthamstow.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 4 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 22 Oct 2024 at 14:22.
4 Nov and 2 Dec 2024
Thames Water are proposing to carry out Utility asset works on Hillside Gardens, Walthamstow.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 4 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 30 Oct 2024 at 16:35.
4 Nov and 16 Dec 2024
Thames Water are proposing to carry out Utility asset works on Castleton Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 4 November 2024 and could run through until 16 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 14 Oct 2024 at 14:47.
4 Nov and 2 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Lambourne Road, Chigwell Town, Chigwell.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 4 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 29 Oct 2024 at 08:31.
4 Nov and 2 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Lambourne Road, Chigwell Town, Chigwell.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 4 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 30 Oct 2024 at 09:54.
4 and 6 Nov 2024
UK Power Networks Eastern & London are proposing to carry out Remedial works on Larkshall Road, Chingford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 4 November 2024 and could run through until 6 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 23 Oct 2024 at 11:49.
6 Nov and 2 Dec 2024
Thames Water are proposing to carry out Utility asset works on Pentire Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 30 Oct 2024 at 16:34.
6 and 8 Nov 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Wake Road, Waltham Abbey Town, Waltham Abbey.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 November 2024 and could run through until 8 November 2024. The works will impact the carriageway and verge.
This roadwork event was last updated by Thames Water on 21 Oct 2024 at 16:01.
8 and 29 Nov 2024
Thames Water are proposing to carry out Utility asset works on Rosebank Villas, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 8 November 2024 and could run through until 29 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 25 Oct 2024 at 13:23.
9 and 19 Nov 2024
Thames Water are proposing to carry out New service connection on High Street, Waltham Cross.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 November 2024 and could run through until 19 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 9 Oct 2024 at 10:59.
9 and 19 Nov 2024
Thames Water are proposing to carry out New service connection on High Street, Waltham Cross.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 November 2024 and could run through until 19 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 17 Oct 2024 at 15:29.
11 Nov 2024 and 23 Jan 2025
Cadent Gas were proposing to carry out Utility asset works on Grove Park, Wanstead, London.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 11 November 2024 and run through until 23 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 13 Aug 2024 at 10:01.
11 Nov 2024 and 23 Jan 2025
Cadent Gas are proposing to carry out Utility asset works on The Avenue, Wanstead, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 23 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 11 Jun 2024 at 07:49.
11 Nov 2024 and 23 Jan 2025
Cadent Gas are proposing to carry out Utility asset works on The Avenue, Wanstead, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 23 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 20 Aug 2024 at 11:08.
11 and 22 Nov 2024
Cadent Gas were proposing to carry out Utility asset works on Nutter Lane, Wanstead, London.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 11 November 2024 and run through until 22 November 2024. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 13 Aug 2024 at 10:02.
11 Nov and 2 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Comely Bank Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 18 Jun 2024 at 14:42.
11 Nov and 2 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Comely Bank Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 19 Aug 2024 at 11:22.
11 Nov and 2 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Comely Bank Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 12 Sep 2024 at 13:36.
11 Nov and 2 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Comely Bank Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 2 Oct 2024 at 15:39.
11 and 28 Nov 2024
Cadent Gas are proposing to carry out Utility asset works on Addison Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 28 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 23 Oct 2024 at 15:28.
11 Nov and 9 Dec 2024
Thames Water are proposing to carry out Utility asset works on Radbourne Crescent, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 9 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 23 Apr 2024 at 11:51.
11 and 13 Nov 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Spruce Hills Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 13 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 11 Sep 2024 at 16:17.
11 and 22 Nov 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Malvern Avenue, Chingford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 22 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 29 Aug 2024 at 15:38.
11 Nov and 8 Dec 2024
London Borough Of Enfield are proposing to carry out Section 50 on Albany Road, Edmonton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 8 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Enfield on 14 Oct 2024 at 13:02.
11 Nov and 20 Dec 2024
London Borough Of Enfield are proposing to carry out Section 50 on Albany Road, Edmonton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Enfield on 29 Oct 2024 at 15:25.
11 Nov and 20 Dec 2024
London Borough Of Enfield are proposing to carry out Section 50 on Albany Road, Edmonton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Enfield on 29 Oct 2024 at 15:32.
11 Nov and 30 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Montalt Road, Woodford Green.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 30 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 16 Oct 2024 at 13:54.
11 and 30 Nov 2024
London Borough Of Enfield were proposing to carry out Section 50 on Plevna Road, Edmonton.
These works were categorised as Major.
Two-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 11 November 2024 and run through until 30 November 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by London Borough Of Enfield on 11 Oct 2024 at 12:02.
11 and 30 Nov 2024
London Borough Of Enfield are proposing to carry out Section 50 on Plevna Road, Edmonton.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 30 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Enfield on 11 Oct 2024 at 12:06.
11 and 16 Nov 2024
Essex County Council are proposing to carry out Highway improvement works on Epping New Road, Buckhurst Hill.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 16 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 2 Jul 2024 at 12:09.
11 and 16 Nov 2024
London Borough Of Waltham Forest are proposing to carry out Highway repair and maintenance works on Sewardstone Road, Chingford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 16 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Waltham Forest on 3 Oct 2024 at 17:32.
11 and 16 Nov 2024
London Borough Of Waltham Forest are proposing to carry out Highway repair and maintenance works on Sewardstone Road, Chingford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 November 2024 and could run through until 16 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Waltham Forest on 4 Oct 2024 at 10:49.
13 and 16 Nov 2024
Thames Water are proposing to carry out Remedial works on The Forest, Leytonstone.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 November 2024 and could run through until 16 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 12 Sep 2024 at 14:05.
18 and 29 Nov 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Marlborough Road, South Woodford, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 29 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 14 Aug 2024 at 10:21.
18 Nov 2024 and 9 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Hurst Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 9 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 15 Aug 2024 at 15:52.
18 Nov 2024 and 9 Mar 2025
Cadent Gas were proposing to carry out Utility asset works on Hurst Road, Walthamstow.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 18 November 2024 and run through until 9 March 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 24 Oct 2024 at 13:59.
18 Nov 2024 and 31 Jan 2025
Cadent Gas are proposing to carry out Utility asset works on Forest Road, Walthamstow.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 13 Aug 2024 at 16:12.
18 Nov 2024 and 31 Jan 2025
Cadent Gas were proposing to carry out Utility asset works on Forest Road, Walthamstow.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 18 November 2024 and run through until 31 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 24 Oct 2024 at 13:57.
18 Nov and 8 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Vicarage Lane, Chigwell Town, Chigwell.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 8 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 29 Oct 2024 at 08:36.
18 Nov and 15 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Shillibeer Walk, Chigwell Town, Chigwell.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 15 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 10 Oct 2024 at 12:48.
18 Nov 2024 and 11 May 2025
Thames Water are proposing to carry out Utility asset works on Station Road, Chingford.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 11 May 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 3 Sep 2024 at 16:27.
18 Nov 2024 and 11 May 2025
Thames Water are proposing to carry out Utility asset works on Station Road, Chingford.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 11 May 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 11 Sep 2024 at 16:20.
18 Nov 2024 and 6 Apr 2025
Thames Water are proposing to carry out Utility asset works on Station Road, Chingford.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 6 April 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 7 Oct 2024 at 15:11.
18 and 23 Nov 2024
Essex County Council are proposing to carry out Highway improvement works on High Road, Buckhurst Hill.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 23 November 2024. The works will impact the carriageway and verge.
This roadwork event was last updated by Essex County Council on 24 Oct 2024 at 08:48.
18 and 23 Nov 2024
Essex County Council are proposing to carry out Highway improvement works on Manor Road, Buckhurst Hill.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 23 November 2024. The works will impact the carriageway and verge.
This roadwork event was last updated by Essex County Council on 24 Oct 2024 at 08:52.
18 and 29 Nov 2024
London Borough Of Enfield are proposing to carry out Highway improvement works on Kingsway, Enfield.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 29 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Enfield on 23 Oct 2024 at 06:51.
18 Nov and 23 Dec 2024
Thames Water are proposing to carry out Utility asset works on Newbury Avenue, Enfield.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 23 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 27 Mar 2024 at 11:33.
18 Nov 2024 and 17 Jan 2025
Cadent Gas were proposing to carry out Utility asset works on Severn Drive, Enfield.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 18 November 2024 and run through until 17 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 24 Oct 2024 at 12:16.
18 and 22 Nov 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Wake Road, Waltham Abbey Town, Waltham Abbey.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 22 November 2024. The works will impact the carriageway and verge.
This roadwork event was last updated by Thames Water on 15 Oct 2024 at 15:44.
18 and 20 Nov 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Wake Road, Waltham Abbey Town, Waltham Abbey.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 20 November 2024. The works will impact the carriageway and verge.
This roadwork event was last updated by Thames Water on 26 Sep 2024 at 12:42.
18 and 23 Nov 2024
Essex County Council are proposing to carry out Highway improvement works on Sewardstone Road, Waltham Abbey Town, Waltham Abbey.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 November 2024 and could run through until 23 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 17 Oct 2024 at 12:57.
19 and 28 Nov 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Clays Lane, Loughton Town, Loughton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 19 November 2024 and could run through until 28 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 2 Sep 2024 at 09:39.
19 and 28 Nov 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Clays Lane, Loughton Town, Loughton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 19 November 2024 and could run through until 28 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 25 Oct 2024 at 11:07.
20 Nov 2024 and 20 Jan 2025
UK Power Networks Eastern & London are proposing to carry out New service connection on Brancroft Way, Enfield.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 20 November 2024 and could run through until 20 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 19 Sep 2024 at 12:07.
20 Nov 2024 and 20 Jan 2025
UK Power Networks Eastern & London are proposing to carry out New service connection on Brancroft Way, Enfield.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 20 November 2024 and could run through until 20 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 16 Oct 2024 at 12:08.
20 Nov 2024 and 13 Jan 2025
Thames Water are proposing to carry out Utility asset works on Bideford Road, Enfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 November 2024 and could run through until 13 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 24 Oct 2024 at 14:24.
20 Nov 2024 and 29 Jan 2025
UK Power Networks Eastern & London are proposing to carry out New service connection on Turkey Street, Enfield.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 20 November 2024 and could run through until 29 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 19 Sep 2024 at 12:08.
20 Nov 2024 and 29 Jan 2025
UK Power Networks Eastern & London are proposing to carry out New service connection on Turkey Street, Enfield.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 20 November 2024 and could run through until 29 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 16 Oct 2024 at 12:09.
20 and 22 Nov 2024
Affinity Water are proposing to carry out Utility repair and maintenance works on Hemnall Street, Epping Town, Epping.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 November 2024 and could run through until 22 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Affinity Water on 2 Sep 2024 at 09:54.
20 and 22 Nov 2024
Affinity Water are proposing to carry out Utility repair and maintenance works on Hemnall Street, Epping Town, Epping.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 November 2024 and could run through until 22 November 2024. The works will impact the carriageway only.
This roadwork event was last updated by Affinity Water on 9 Sep 2024 at 09:02.
25 Nov and 15 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Grosvenor Road, Wanstead, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 15 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 29 Oct 2024 at 10:00.
25 Nov and 9 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Woodford Road, South Woodford, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 9 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 29 Jul 2024 at 14:04.
25 Nov and 9 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Woodford Road, South Woodford, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 9 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 6 Aug 2024 at 10:41.
25 Nov and 15 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Bedford Road, South Woodford, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 15 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 3 Sep 2024 at 13:57.
25 Nov and 15 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Bedford Road, South Woodford, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 15 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 11 Sep 2024 at 15:30.
25 Nov 2024 and 24 Jan 2025
Thames Water are proposing to carry out Utility asset works on Grantock Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 24 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 30 Oct 2024 at 15:57.
25 and 27 Nov 2024
Network Rail are proposing to carry out Works for Rail Purposes on Ordnance Road, Enfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 27 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Network Rail on 4 Sep 2024 at 10:10.
25 and 27 Nov 2024
Network Rail are proposing to carry out Works for Rail Purposes on Ordnance Road, Enfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 27 November 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Network Rail on 23 Oct 2024 at 11:27.
25 Nov and 6 Dec 2024
Essex County Council are proposing to carry out Highway improvement works on Western Avenue, Epping Town, Epping.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 25 November 2024 and could run through until 6 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 12 Aug 2024 at 08:56.
26 Nov and 16 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Cleveland Road, South Woodford, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 26 November 2024 and could run through until 16 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 3 Sep 2024 at 13:57.
26 Nov and 16 Dec 2024
Cadent Gas are proposing to carry out Utility asset works on Cleveland Road, South Woodford, London.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 26 November 2024 and could run through until 16 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Cadent Gas on 11 Sep 2024 at 15:30.
29 Nov and 3 Dec 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Church Road, Waltham Abbey Town, Waltham Abbey.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 29 November 2024 and could run through until 3 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 11 Sep 2024 at 10:14.
29 Nov and 3 Dec 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Church Road, Waltham Abbey Town, Waltham Abbey.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 29 November 2024 and could run through until 3 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 19 Sep 2024 at 08:36.
2 and 6 Dec 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Hollybush Hill, Wanstead, London.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 6 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 11 Sep 2024 at 14:00.
2 Dec 2024 and 6 Jan 2025
Cadent Gas are proposing to carry out Utility asset works on Brunswick Street, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 6 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 19 Jun 2024 at 10:52.
2 Dec 2024 and 15 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on Folkestone Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 15 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 2 Oct 2024 at 15:36.
2 Dec 2024 and 15 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on St Mary Road, Walthamstow.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 15 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 19 Jun 2024 at 10:48.
2 Dec 2024 and 15 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on St Mary Road, Walthamstow.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 15 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 12 Sep 2024 at 14:28.
2 Dec 2024 and 15 Feb 2025
Cadent Gas are proposing to carry out Utility asset works on St Mary Road, Walthamstow.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 15 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 13 Sep 2024 at 15:56.
2 and 23 Dec 2024
Thames Water are proposing to carry out Utility asset works on Avon Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 23 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 23 Apr 2024 at 11:51.
2 and 10 Dec 2024
Affinity Water are proposing to carry out Utility asset works on Church Row, Epping Town, Epping.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 December 2024 and could run through until 10 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Affinity Water on 30 Sep 2024 at 09:56.
3 and 7 Dec 2024
Essex County Council are proposing to carry out Highway improvement works on Shernbroke Road, Waltham Abbey Town, Waltham Abbey.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 December 2024 and could run through until 7 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 25 Oct 2024 at 11:39.
3 and 7 Dec 2024
Essex County Council are proposing to carry out Highway improvement works on Shernbroke Road, Waltham Abbey Town, Waltham Abbey.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 December 2024 and could run through until 7 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 30 Oct 2024 at 13:15.
3 and 7 Dec 2024
Essex County Council are proposing to carry out Highway improvement works on Maynard Court, Waltham Abbey Town, Waltham Abbey.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 December 2024 and could run through until 7 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 25 Oct 2024 at 11:39.
3 and 7 Dec 2024
Essex County Council are proposing to carry out Highway improvement works on Maynard Court, Waltham Abbey Town, Waltham Abbey.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 December 2024 and could run through until 7 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 30 Oct 2024 at 13:15.
4 and 20 Dec 2024
Transport for London (TfL) are proposing to carry out Highway improvement works on Eastern Avenue, Ilford.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 4 December 2024 and could run through until 20 December 2024. The works will impact the verge only.
This roadwork event was last updated by Transport for London (TfL) on 15 Oct 2024 at 08:05.
4 and 20 Dec 2024
Transport for London (TfL) are proposing to carry out Highway improvement works on Eastern Avenue, Ilford.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 4 December 2024 and could run through until 20 December 2024. The works will impact the verge only.
This roadwork event was last updated by Transport for London (TfL) on 16 Oct 2024 at 12:02.
6 Dec 2024 and 28 Mar 2025
Cadent Gas are proposing to carry out Utility asset works on Hatch Lane, Chingford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 December 2024 and could run through until 28 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 22 Oct 2024 at 15:15.
9 Dec 2024 and 13 Jan 2025
Thames Water are proposing to carry out roadworks on Springfield Road, Chingford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 13 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 7 Oct 2024 at 15:33.
9 Dec 2024 and 13 Jan 2025
Thames Water are proposing to carry out roadworks on Connaught Avenue, Chingford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 13 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 7 Oct 2024 at 15:26.
9 and 11 Dec 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Mott Street, Loughton Town, Loughton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 11 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 11 Sep 2024 at 10:12.
9 and 11 Dec 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Mott Street, Loughton Town, Loughton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 11 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 18 Sep 2024 at 15:52.
9 and 11 Dec 2024
Thames Water are proposing to carry out Utility asset works on High Street, Waltham Cross.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 11 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 14 Oct 2024 at 17:33.
9 and 11 Dec 2024
Thames Water are proposing to carry out Utility asset works on High Street, Waltham Cross.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 11 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 29 Oct 2024 at 12:25.
9 and 11 Dec 2024
Thames Water are proposing to carry out Utility asset works on Lodge Crescent, Waltham Cross.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 11 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 4 Oct 2024 at 12:37.
9 and 20 Dec 2024
Essex County Council are proposing to carry out Highway improvement works on The Drummonds, Epping Town, Epping.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 9 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 12 Aug 2024 at 09:08.
10 and 12 Dec 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Wellington Hill, Waltham Abbey Town, Waltham Abbey.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 10 December 2024 and could run through until 12 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 30 Sep 2024 at 09:01.
10 and 12 Dec 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Wellington Hill, Waltham Abbey Town, Waltham Abbey.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 10 December 2024 and could run through until 12 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 4 Oct 2024 at 10:53.
10 and 12 Dec 2024
Vodafone are proposing to carry out Utility asset works on Shernbroke Road, Waltham Abbey Town, Waltham Abbey.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 10 December 2024 and could run through until 12 December 2024. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by Vodafone on 11 Sep 2024 at 10:17.
10 and 12 Dec 2024
Vodafone were proposing to carry out Utility asset works on Shernbroke Road, Waltham Abbey Town, Waltham Abbey.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 10 December 2024 and run through until 12 December 2024. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by Vodafone on 26 Sep 2024 at 14:40.
11 and 13 Dec 2024
Essex County Council are proposing to carry out Highway improvement works on Palace Gardens, Buckhurst Hill.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 11 December 2024 and could run through until 13 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 30 Oct 2024 at 15:05.
12 and 22 Dec 2024
Essex County Council are proposing to carry out Highway improvement works on Lower Park Road, Loughton Town, Loughton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 12 December 2024 and could run through until 22 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 25 Oct 2024 at 10:18.
14 and 22 Dec 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Turpins Lane, Chigwell Town, Chigwell.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 14 December 2024 and could run through until 22 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 26 Sep 2024 at 10:13.
14 and 22 Dec 2024
Thames Water are proposing to carry out Utility repair and maintenance works on Turpins Lane, Chigwell Town, Chigwell.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 14 December 2024 and could run through until 22 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 27 Sep 2024 at 14:43.
16 Dec 2024 and 10 Jan 2025
Essex County Council are proposing to carry out Highway improvement works on Purlieu Way, Theydon Bois, Epping.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 10 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 27 Aug 2024 at 09:51.
16 and 20 Dec 2024
UK Power Networks Eastern & London are proposing to carry out Utility repair and maintenance works on Western Avenue, Epping Town, Epping.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by UK Power Networks Eastern & London on 18 Sep 2024 at 08:19.
16 and 20 Dec 2024
UK Power Networks Eastern & London are proposing to carry out Utility repair and maintenance works on Western Avenue, Epping Town, Epping.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 16 December 2024 and could run through until 20 December 2024. The works will impact the footway and carriageway.
This roadwork event was last updated by UK Power Networks Eastern & London on 23 Sep 2024 at 09:54.
17 and 20 Dec 2024
Essex County Council are proposing to carry out Highway improvement works on Daleside Gardens, Chigwell Town, Chigwell.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 17 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 30 Oct 2024 at 16:09.
18 and 20 Dec 2024
Essex County Council are proposing to carry out Highway improvement works on Daleside Gardens, Chigwell Town, Chigwell.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 18 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 30 Oct 2024 at 16:09.
20 and 22 Dec 2024
Thames Water were proposing to carry out Utility repair and maintenance works on Chingford Road, Chingford.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 20 December 2024 and run through until 22 December 2024. The works were due to impact the carriageway only.
This roadwork event was last updated by Thames Water on 18 Sep 2024 at 11:35.
30 Dec 2024 and 26 Jan 2025
Cadent Gas were proposing to carry out Utility asset works on Lambourne Road, Chigwell Town, Chigwell.
These works were categorised as Major.
Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.
The works were originally planned to start 30 December 2024 and run through until 26 January 2025. The works were due to impact the footway and carriageway.
This roadwork event was last updated by Cadent Gas on 14 Oct 2024 at 14:25.
2 Jan and 13 Mar 2025
Thames Water are proposing to carry out Utility asset works on Winsbeach, Walthamstow.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 January 2025 and could run through until 13 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 23 Apr 2024 at 11:49.
2 Jan and 13 Mar 2025
Thames Water are proposing to carry out Utility asset works on Winsbeach, Walthamstow.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 2 January 2025 and could run through until 13 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 28 Oct 2024 at 15:05.
2 Jan and 6 Feb 2025
Thames Water are proposing to carry out Utility asset works on Ulverston Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 January 2025 and could run through until 6 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 28 Oct 2024 at 15:53.
2 Jan and 13 Mar 2025
Thames Water are proposing to carry out Utility asset works on Castleton Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 January 2025 and could run through until 13 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 23 Apr 2024 at 11:55.
2 Jan and 13 Mar 2025
Thames Water are proposing to carry out Utility asset works on Grantock Road, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 January 2025 and could run through until 13 March 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 23 Apr 2024 at 11:53.
2 Jan and 20 Mar 2025
Thames Water are proposing to carry out Utility asset works on Bideford Road, Enfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 2 January 2025 and could run through until 20 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 27 Mar 2024 at 11:33.
3 and 6 Jan 2025
Thames Water are proposing to carry out Remedial works on The Forest, Leytonstone.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 3 January 2025 and could run through until 6 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 14 Oct 2024 at 15:31.
6 and 31 Jan 2025
Essex County Council are proposing to carry out Highway improvement works on Broadfield Way, Buckhurst Hill.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Essex County Council on 16 Sep 2024 at 08:41.
6 and 31 Jan 2025
Essex County Council are proposing to carry out Highway improvement works on Field Close, Buckhurst Hill.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Essex County Council on 16 Sep 2024 at 08:42.
6 and 8 Jan 2025
London Borough Of Enfield are proposing to carry out Remedial works on Southfield Road, Enfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 8 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Enfield on 20 Sep 2024 at 10:32.
6 and 8 Jan 2025
London Borough Of Enfield are proposing to carry out Remedial works on Southfield Road, Enfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 8 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by London Borough Of Enfield on 2 Oct 2024 at 10:05.
6 and 10 Jan 2025
UK Power Networks Eastern & London are proposing to carry out New service connection on Uckfield Road, Enfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 6 January 2025 and could run through until 10 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by UK Power Networks Eastern & London on 17 Sep 2024 at 11:50.
12 and 14 Jan 2025
Thames Water were proposing to carry out roadworks on Rushcroft Road, Chingford.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 12 January 2025 and run through until 14 January 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Thames Water on 28 Oct 2024 at 08:47.
13 and 24 Jan 2025
BT were proposing to carry out Utility repair and maintenance works on Forest Rise, Walthamstow.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 13 January 2025 and run through until 24 January 2025. The works were due to impact the footway, carriageway and verge.
This roadwork event was last updated by BT on 21 Oct 2024 at 11:35.
13 and 24 Jan 2025
BT are proposing to carry out Utility repair and maintenance works on Forest Rise, Walthamstow.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 24 January 2025. The works will impact the footway, carriageway and verge.
This roadwork event was last updated by BT on 21 Oct 2024 at 11:36.
13 Jan and 3 Feb 2025
Thames Water were proposing to carry out roadworks on Connaught Road, Chingford.
These works were categorised as Major.
The road was planned to be closed for some or all of the period. However, the works were cancelled.
The works were originally planned to start 13 January 2025 and run through until 3 February 2025. The works were due to impact the carriageway only.
This roadwork event was last updated by Thames Water on 30 Sep 2024 at 14:20.
13 Jan and 3 Feb 2025
Thames Water are proposing to carry out roadworks on Connaught Road, Chingford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 3 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 7 Oct 2024 at 15:15.
13 and 28 Jan 2025
T-Mobile (UK) are proposing to carry out Utility repair and maintenance works on Ladyfields, Loughton Town, Loughton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 28 January 2025. The works will impact the carriageway and verge.
This roadwork event was last updated by T-Mobile (UK) on 22 Oct 2024 at 12:06.
13 and 15 Jan 2025
Virgin Media are proposing to carry out Utility asset works on Crown Road, Enfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 15 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Virgin Media on 7 Oct 2024 at 15:18.
13 and 16 Jan 2025
Thames Water are proposing to carry out Utility repair and maintenance works on Wellington Hill, Waltham Abbey Town, Waltham Abbey.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 16 January 2025. The works will impact the carriageway and verge.
This roadwork event was last updated by Thames Water on 28 Oct 2024 at 09:52.
13 Jan and 24 Feb 2025
Thames Water are proposing to carry out Utility asset works on Marrilyne Avenue, Enfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 13 January 2025 and could run through until 24 February 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 11 Sep 2024 at 10:38.
20 Jan and 10 Apr 2025
UK Power Networks Eastern & London are proposing to carry out New service connection on Beehive Lane, Ilford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 10 April 2025. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 23 Oct 2024 at 15:15.
20 Jan and 25 Feb 2025
UK Power Networks Eastern & London are proposing to carry out New service connection on Woodford Bridge Road, Ilford.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 25 February 2025. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 28 Oct 2024 at 13:00.
20 Jan and 9 Feb 2025
Thames Water are proposing to carry out Utility asset works on Woodford New Road, Walthamstow.
These works are categorised as Major.
Two-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 9 February 2025. The works will impact the footway, carriageway and cycleway.
This roadwork event was last updated by Thames Water on 25 Oct 2024 at 13:18.
20 and 23 Jan 2025
Essex County Council are proposing to carry out Highway improvement works on Gravel Lane, Chigwell Town, Chigwell.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 23 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Essex County Council on 25 Oct 2024 at 10:10.
20 Jan and 4 Mar 2025
UK Power Networks Eastern & London are proposing to carry out New service connection on Mollison Avenue, Enfield.
These works are categorised as Major.
Multi-way signals will be in place for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 4 March 2025. The works will impact the carriageway only.
This roadwork event was last updated by UK Power Networks Eastern & London on 19 Sep 2024 at 11:34.
20 and 24 Jan 2025
Thames Water are proposing to carry out New service connection on Marrilyne Avenue, Enfield.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 20 January 2025 and could run through until 24 January 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by Thames Water on 14 Oct 2024 at 13:21.
21 Jan and 12 Feb 2025
Transport for London (TfL) are proposing to carry out Highway improvement works on North Circular Road, Wanstead, London.
These works are categorised as Major.
A lane will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 21 January 2025 and could run through until 12 February 2025. The works will impact the carriageway and verge.
This roadwork event was last updated by Transport for London (TfL) on 22 Oct 2024 at 10:27.
27 and 29 Jan 2025
Thames Water are proposing to carry out roadworks on Rushcroft Road, Chingford.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 29 January 2025. The works will impact the carriageway only.
This roadwork event was last updated by Thames Water on 28 Oct 2024 at 09:08.
27 Jan and 26 Oct 2025
London Borough Of Enfield are proposing to carry out Highway improvement works on Harbet Road, Edmonton.
These works are categorised as Major.
The road will be closed for some or all of the period and could cause delays to journeys.
The works will start on or after 27 January 2025 and could run through until 26 October 2025. The works will impact the footway and carriageway.
This roadwork event was last updated by London Borough Of Enfield on 28 Oct 2024 at 14:28.
Roadworks Map near to Algers Road, LOUGHTON, IG10 4NG
- Any red lines indicate the extent of the works.
- Clicking on the map will re-centre to the selected point.
- Within 1 mile, all roadworks are displayed.
- Within 2-3 miles, standard, urgent and major roadworks are displayed.
- For 3-5 miles, only major roadworks are shown.
- The higher the marker number, the further away the roadworks are from the centre of the postcode.
- Where traffic camera videos or images are shown, no historical versions are retained. Once a new image or video becomes available it overwrites the previous version.
Roadworks Listing near to Algers Road, LOUGHTON, IG10 4NG (26 Events)
(Scheduled Dates)
(miles)
(Scheduled: 29 Oct 2024 - 4 Nov 2024)
(Scheduled: 24 Oct 2024 - 4 Nov 2024)
(Scheduled: 28 Oct 2024 - 1 Nov 2024)
(Scheduled: 29 Oct 2024 - 31 Oct 2024)
(Scheduled: 29 Oct 2024 - 31 Oct 2024)
(Scheduled: 4 Oct 2024 - 31 Mar 2025)
Contains public sector information licensed under the Open Government Licence v3.0.