ROADWORK EVENT SUMMARY
Eastern Avenue, Ilford between 7 Oct and 22 Nov 2024

Works Description for Eastern Avenue, Ilford

This is a PAA (Provisional Advance Authorisation) permit that has been granted before final details of an activity have been finalised. A full permit will be required before activities can commence.


Transport for London (TfL) are proposing to carry out Highway improvement works on Eastern Avenue, Ilford.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 7 October 2024 and could run through until 22 November 2024. The works will impact the footway and carriageway.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

The information for these works was last updated by Transport for London (TfL) on 17 September 2024 at 09:49.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Eastern Avenue, Ilford

Works Details

WORKS PLANNED
Major (PAA)
Transport for London (TfL) logo
These works are handled by:
Transport for London (TfL)
Transport for London (TfL) logo
Local Authority:
Transport for London (TfL)
Works Reference YG52597348050
Permit Number 02
Place Name Eastern Avenue
Ilford
Proposed Start 7 Oct 2024
Proposed End 22 Nov 2024
Actual Start
Actual End
Traffic Management Multi-way signals
Impact Footway, Carriageway
Coordinates
Lat, Lon
51.575801
0.045347
Last Updated 17 Sep 2024 09:49
Contact Details for Activity YG52597348050 (Eastern Avenue, Ilford)

In the event that you have an issue with these works, please contact Transport for London (TfL), the works operator.

It would assist the organisation if you quote the work reference number of YG52597348050.

Transport for London (TfL)
Websitehttps://tfl.gov.uk/help-and-contact/contact-us-about-streets-and-other-road-issues
TelephoneTraffic signals faults 020 7941 2010
TelephoneRed Route Issues 020 7343 5000
Works History for Activity YG52597348050 (Eastern Avenue, Ilford)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
2 Sep 2024
12:21
Permit Submitted
7 Oct 2024
09:00
22 Nov 2024
05:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Sep 2024
10:49
Permit Granted
7 Oct 2024
09:00
22 Nov 2024
05:00
Planned

Works Permits for Eastern Avenue, Ilford

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT05a (Width and/or length of road space that can be occupied)

For the activities hereby permitted, it is a condition of this permit that the activity shall occur only within the area [insert description of area or provide traffic management plan reference] including the relevant and required signing, lighting and guarding excluding advance warning, advance communication and diversionary signs.

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT10a (Employment (as agreed) of appropriate methodology)

For the activities hereby permitted, it is a condition of this permit that, for the activities on this site, as agreed, the works methodology employed will be A, B, C [describe agreed methodology] throughout the duration of the works activity.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.