ROADWORK EVENT SUMMARY
A180 From Lock Hill Roundabout To Pyewipe Roundabout, Grimsby between 13 Apr and 2 Nov 2026

Works Description for A180 From Lock Hill Roundabout To Pyewipe Roundabout, Grimsby

North East Lincolnshire Council are carrying out Highway repair and maintenance works on A180 From Lock Hill Roundabout To Pyewipe Roundabout, Grimsby.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 13 April 2026 at 08:30 and could run through until 2 November 2026. The works will impact the carriageway, verge and footpath.

The information for these works was last updated by North East Lincolnshire Council on 18 August 2026 at 16:04.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for A180 From Lock Hill Roundabout To Pyewipe Roundabout, Grimsby

Works Details

WORKS IN PROGRESS
Major
North East Lincolnshire Council logo
These works are handled by:
North East Lincolnshire Council
North East Lincolnshire Council logo
Local Authority:
North East Lincolnshire Council
Works Reference RN011HD005-25-TOPDECK
Permit Number 02
Place Name A180 From Lock Hill Roundabout To Pyewipe Roundabout
Grimsby
Proposed Start 7 Apr 2026
Proposed End 2 Nov 2026
Actual Start 13 Apr 2026 08:30
Actual End
Traffic Management Road closure
Impact Carriageway, Verge, Footpath
Coordinates
Lat, Lon
53.574689
-0.080709
Last Updated 18 Aug 2026 16:04
Works History for Activity RN011HD005-25-TOPDECK (A180 From Lock Hill Roundabout To Pyewipe Roundabout, Grimsby)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
27 Jun 2025
15:55
Permit Submitted
1 Oct 2025
01:00
31 Jan 2026
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
27 Jun 2025
15:58
Permit Granted
1 Oct 2025
01:00
31 Jan 2026
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
27 Jun 2025
16:05
Permit Alteration Granted
1 Oct 2025
01:00
28 Mar 2026
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Aug 2025
14:16
Permit Alteration Granted
17 Nov 2025
00:00
17 Jul 2026
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
7 Oct 2025
17:06
Permit Alteration Granted
12 Jan 2026
00:00
12 Jul 2026
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
7 Jan 2026
12:23
Permit Alteration Granted
12 Jan 2026
00:00
25 Sep 2026
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
22 Jan 2026
16:04
Permit Alteration Granted
16 Feb 2026
00:00
30 Oct 2026
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
16 Feb 2026
08:40
Permit Alteration Granted
9 Mar 2026
00:00
20 Nov 2026
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Mar 2026
16:48
Permit Alteration Granted
7 Apr 2026
01:00
17 Dec 2026
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
13 Apr 2026
15:54
Work Started
7 Apr 2026
01:00
17 Dec 2026
00:00
13 Apr 2026
09:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
6 May 2026
16:22
Permit Alteration Granted
7 Apr 2026
01:00
2 Oct 2026
01:00
13 Apr 2026
09:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
18 Aug 2026
17:04
Permit Alteration Granted
7 Apr 2026
01:00
2 Nov 2026
00:00
13 Apr 2026
09:30
In Progress

Works Permits for A180 From Lock Hill Roundabout To Pyewipe Roundabout, Grimsby

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.