ROADWORK EVENT SUMMARY
Purbeck Close, Wigston, Oadby And Wigston between 22 and 26 Nov 2024

Works Description for Purbeck Close, Wigston, Oadby And Wigston

Cityfibre Metro Networks carried out Remedial works on Purbeck Close, Wigston, Oadby And Wigston.

There were no traffic signals or road closures necessary for these works and traffic operated on a give-and-take basis.

The works were originally planned between 21 Nov 2024 and 26 Nov 2024 and were actually completed between 22 Nov 2024 (08:00) and 26 Nov 2024 (14:30). The works impacted the footway only.

The information for these works was last updated by Cityfibre Metro Networks on 26 November 2024 at 14:48.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Purbeck Close, Wigston, Oadby And Wigston

Works Details

WORKS COMPLETED
Cityfibre Metro Networks logo
These works are handled by:
Cityfibre Metro Networks
Leicestershire County Council logo
Local Authority:
Leicestershire County Council
Works Reference KG015LEC3-PN352-06
Permit Number 02
Place Name Purbeck Close
Wigston
Oadby And Wigston
Proposed Start 21 Nov 2024
Proposed End 26 Nov 2024
Actual Start 22 Nov 2024 08:00
Actual End 26 Nov 2024 14:30
Traffic Management Give and take
Impact Footway
Coordinates
Lat, Lon
52.575015
-1.107205
Last Updated 26 Nov 2024 14:48
Works History for Activity KG015LEC3-PN352-06 (Purbeck Close, Wigston, Oadby And Wigston)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
18 Nov 2024
09:30
Permit Submitted
21 Nov 2024
00:00
25 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Nov 2024
14:46
Permit Granted
21 Nov 2024
00:00
25 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
22 Nov 2024
08:24
Work Started
21 Nov 2024
00:00
26 Nov 2024
00:00
22 Nov 2024
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
26 Nov 2024
14:48
Work Stopped
21 Nov 2024
00:00
26 Nov 2024
00:00
22 Nov 2024
08:00
26 Nov 2024
14:30
Completed

Works Permits for Purbeck Close, Wigston, Oadby And Wigston

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT04a (Removal of surplus materials/plant)

For the activities hereby permitted, it is a condition of this permit that all remaining excavated or stored backfill materials and/or any unemployed plant must be removed from the public highway within (x hours e.g. 24) or by the stipulated time (e.g. at the end of the working day or prior to the site being un-occupied) due to (stipulate reason for application of condition).

+
NCT04b (Storage of surplus materials/plant)

For the activities hereby permitted, it is a condition of this permit that no materials and/or plant that will not be utilised within the working day are to be stored within or outside of the defined working space from (insert date) until (insert date) due to (stipulate reason for application of condition).

+
NCT05a (Width and/or length of road space that can be occupied)

For the activities hereby permitted, it is a condition of this permit that the activity shall occur only within the area [insert description of area or provide traffic management plan reference] including the relevant and required signing, lighting and guarding excluding advance warning, advance communication and diversionary signs.

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.