ROADWORKS SUMMARY
Turner Mews, COLCHESTER, CO6 1FT

Introduction

Image of petrol pumps

View current and future planned roadworks and road closures for Turner Mews, CO6 1FT and the surrounding area.

Our roadwork details are constantly updated and reflect the current situation and we offer both a map view and a listing. We also highlight the major and significant roadworks occuring near to you help you avoid the worst of the delays to your journey.

The roadworks shown below show all current and proposed works during the next 90 days and historical data is recorded since July 2020.

Please note that we re-publish this data and cannot provide any additional information pertaining to a roadwork event. If you require more information, please contact the organisation carrying out the work.

Data are provided by the Department for Transport.

Have we helped today?

If we have helped you today, please consider buying us a quick coffee to keep us going!

Transport for London Traffic cameras are currently unavailable whilst TfL resolve a data security issue.

Major Roadworks near to Turner Mews, COLCHESTER, CO6 1FT

Details of major roadworks, currently in progress or starting soon and resulting in road closures and/or traffic signal management for Turner Mews are shown here covering a 5 mile radius. See further down for details of all roadworks in your area.

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Essex County Council logo
LONG TERM
Between
27 Oct and 6 Dec 2024
Details
View Map
Share
Follow
London Road

Essex County Council are proposing to carry out Highway improvement works on London Road, Copford.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 27 October 2024 and could run through until 6 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 7 Oct 2024 at 09:31.

Cadent Gas logo
Between
4 Nov and 2 Dec 2024
Details
View Map
Share
Follow
Church Hill

Cadent Gas are proposing to carry out Utility asset works on Church Hill, Earls Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 4 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 1 Aug 2024 at 11:18.

Cadent Gas logo
Between
4 Nov and 2 Dec 2024
Details
View Map
Share
Follow
Church Hill

Cadent Gas are proposing to carry out Utility asset works on Church Hill, Earls Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 4 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 4 Nov 2024 at 09:13.

Essex County Council logo
LONG TERM
Between
4 Nov and 13 Dec 2024
Details
View Map
Share
Follow
London Road

Essex County Council are proposing to carry out Highway improvement works on London Road, Copford.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 4 November 2024 and could run through until 13 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 5 Nov 2024 at 16:38.

Essex County Council logo
LONG TERM
Until
20 Jan 2025
Details
View Map
Share
Follow
Hall Road

Essex County Council are carrying out Highway improvement works on Hall Road, Copford.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 7 November 2024 at 17:03 and could run through until 20 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 7 Nov 2024 at 17:14.

Essex County Council logo
LONG TERM
Between
7 Nov 2024 and 20 Jan 2025
Details
View Map
Share
Follow
Hall Road

Essex County Council are proposing to carry out Highway improvement works on Hall Road, Copford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 November 2024 and could run through until 20 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 21 Oct 2024 at 10:28.

Cadent Gas logo
Until
29 Nov 2024
Details
View Map
Share
Follow
High Street

Cadent Gas are carrying out Utility asset works on High Street, Earls Colne.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 11 November 2024 at 09:08 and could run through until 29 November 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 11 Nov 2024 at 09:13.

Cadent Gas logo
Between
11 Nov and 2 Dec 2024
Details
View Map
Share
Follow
Upper Holt Street

Cadent Gas are proposing to carry out Utility asset works on Upper Holt Street, Earls Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 11 November 2024 and could run through until 2 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 1 Aug 2024 at 11:20.

Essex County Council logo
Between
11 Nov and 7 Dec 2024
Details
View Map
Share
Follow
Station Road

Essex County Council are proposing to carry out Highway improvement works on Station Road, Earls Colne.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 11 November 2024 and could run through until 7 December 2024. The works will impact the carriageway and verge.

This roadwork event was last updated by Essex County Council on 24 Sep 2024 at 14:27.

Essex County Council logo
Between
11 Nov and 7 Dec 2024
Details
View Map
Share
Follow
Station Road

Essex County Council are proposing to carry out Highway improvement works on Station Road, Earls Colne.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 11 November 2024 and could run through until 7 December 2024. The works will impact the carriageway and verge.

This roadwork event was last updated by Essex County Council on 3 Oct 2024 at 08:06.

Essex County Council logo
LONG TERM
Until
20 Dec 2024
Details
View Map
Share
Follow
London Road

Essex County Council are carrying out Highway improvement works on London Road, Copford.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 12 November 2024 at 16:10 and could run through until 20 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 12 Nov 2024 at 16:17.

Essex County Council logo
LONG TERM
Between
12 Nov and 20 Dec 2024
Details
View Map
Share
Follow
London Road

Essex County Council are proposing to carry out Highway improvement works on London Road, Copford.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 12 November 2024 and could run through until 20 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 6 Nov 2024 at 11:29.

Essex County Council logo
Finishing
Tuesday
Details
View Map
Share
Follow
Cressing Road

Essex County Council are carrying out Highway improvement works on Cressing Road, Cressing.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 19 November 2024 at 00:00 and could run through until 26 November 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 20 Nov 2024 at 08:36.

Cadent Gas logo
Between
18 Nov and 16 Dec 2024
Details
View Map
Share
Follow
Church Hill

Cadent Gas are proposing to carry out Utility asset works on Church Hill, Earls Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 18 November 2024 and could run through until 16 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 13 Nov 2024 at 14:12.

Cadent Gas logo
Between
18 Nov and 9 Dec 2024
Details
View Map
Share
Upper Holt Street

Cadent Gas were proposing to carry out Utility asset works on Upper Holt Street, Earls Colne.

These works were categorised as Major.

Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.

The works were originally planned to start 18 November 2024 and run through until 9 December 2024. The works were due to impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 11 Nov 2024 at 08:44.

Essex County Council logo
Between
18 Nov and 14 Dec 2024
Details
View Map
Share
Factory Lane West

Essex County Council were proposing to carry out Highway improvement works on Factory Lane West, Halstead Urban, Halstead.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 18 November 2024 and run through until 14 December 2024. The works were due to impact the carriageway only.

This roadwork event was last updated by Essex County Council on 30 Aug 2024 at 09:19.

Cadent Gas logo
Between
18 Nov and 9 Dec 2024
Details
View Map
Share
Follow
Upper Holt Street

Cadent Gas are proposing to carry out Utility asset works on Upper Holt Street, Earls Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 18 November 2024 and could run through until 9 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 11 Nov 2024 at 09:30.

Essex County Council logo
Between
22 Nov and 3 Dec 2024
Details
View Map
Share
Follow
Station Road

Essex County Council are proposing to carry out Highway improvement works on Station Road, Wakes Colne.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 22 November 2024 and could run through until 3 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 15 Oct 2024 at 15:13.

Essex County Council logo
Between
25 Nov and 6 Dec 2024
Details
View Map
Share
Follow
Hall Road

Essex County Council are proposing to carry out Highway improvement works on Hall Road, Copford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 25 November 2024 and could run through until 6 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 12 Nov 2024 at 09:56.

Cadent Gas logo
Between
25 Nov and 9 Dec 2024
Details
View Map
Share
Follow
Church Hill

Cadent Gas are proposing to carry out Utility asset works on Church Hill, Earls Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 25 November 2024 and could run through until 9 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 20 Nov 2024 at 11:50.

Cadent Gas logo
Between
25 Nov and 16 Dec 2024
Details
View Map
Share
Follow
Church Hill

Cadent Gas are proposing to carry out Utility asset works on Church Hill, Earls Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 25 November 2024 and could run through until 16 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 20 Nov 2024 at 09:44.

Anglian Water logo
Finishing
Wednesday
Details
View Map
Share
Follow
Gladfen Hall Road

Anglian Water are proposing to carry out Utility repair and maintenance works on Gladfen Hall Road, Greenstead Green.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 25 November 2024 and could run through until 27 November 2024. The works will impact the carriageway only.

This roadwork event was last updated by Anglian Water on 15 Nov 2024 at 08:34.

Anglian Water logo
Finishing
Wednesday
Details
View Map
Share
Follow
Gladfen Hall Road

Anglian Water are proposing to carry out Utility repair and maintenance works on Gladfen Hall Road, Greenstead Green.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 25 November 2024 and could run through until 27 November 2024. The works will impact the carriageway only.

This roadwork event was last updated by Anglian Water on 5 Sep 2024 at 09:07.

Essex County Council logo
LONG TERM
Between
25 Nov 2024 and 20 Jan 2025
Details
View Map
Share
Follow
Hall Road

Essex County Council are proposing to carry out Highway improvement works on Hall Road, Copford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 25 November 2024 and could run through until 20 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 9 Oct 2024 at 11:05.

Essex County Council logo
Between
28 Nov and 20 Dec 2024
Details
View Map
Share
Follow
Station Road

Essex County Council are proposing to carry out Highway improvement works on Station Road, Earls Colne.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 November 2024 and could run through until 20 December 2024. The works will impact the carriageway and verge.

This roadwork event was last updated by Essex County Council on 9 Oct 2024 at 20:11.

Essex County Council logo
Between
28 Nov and 20 Dec 2024
Details
View Map
Share
Follow
Station Road

Essex County Council are proposing to carry out Highway improvement works on Station Road, Earls Colne.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 November 2024 and could run through until 20 December 2024. The works will impact the carriageway and verge.

This roadwork event was last updated by Essex County Council on 3 Oct 2024 at 08:39.

Essex County Council logo
Between
30 Nov and 3 Dec 2024
Details
View Map
Share
Follow
Ronald Road

Essex County Council are proposing to carry out Highway improvement works on Ronald Road, Halstead Urban, Halstead.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 30 November 2024 and could run through until 3 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 5 Nov 2024 at 14:00.

Cadent Gas logo
Between
2 and 20 Dec 2024
Details
View Map
Share
Follow
Upper Holt Street

Cadent Gas are proposing to carry out Utility asset works on Upper Holt Street, Earls Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 December 2024 and could run through until 20 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 20 Nov 2024 at 10:38.

Cadent Gas logo
Between
2 and 30 Dec 2024
Details
View Map
Share
Follow
Lower Holt Street

Cadent Gas are proposing to carry out Utility asset works on Lower Holt Street, Earls Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 December 2024 and could run through until 30 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 1 Aug 2024 at 11:22.

Cadent Gas logo
Between
2 and 30 Dec 2024
Details
View Map
Share
Follow
Lower Holt Street

Cadent Gas are proposing to carry out Utility asset works on Lower Holt Street, Earls Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 December 2024 and could run through until 30 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 7 Nov 2024 at 11:28.

Cadent Gas logo
Between
2 and 20 Jan 2025
Details
View Map
Share
Follow
Colneford Hill

Cadent Gas are proposing to carry out Utility asset works on Colneford Hill, White Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 January 2025 and could run through until 20 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 7 Nov 2024 at 11:22.

Cadent Gas logo
Between
2 and 20 Jan 2025
Details
View Map
Share
Follow
Colneford Hill

Cadent Gas are proposing to carry out Utility asset works on Colneford Hill, White Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 January 2025 and could run through until 20 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 1 Aug 2024 at 11:24.

Cadent Gas logo
Between
2 and 20 Jan 2025
Details
View Map
Share
Follow
Colneford Hill

Cadent Gas are proposing to carry out Utility asset works on Colneford Hill, White Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 January 2025 and could run through until 20 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 15 Nov 2024 at 08:48.

Cadent Gas logo
Between
2 and 20 Jan 2025
Details
View Map
Share
Follow
Colne Park Road

Cadent Gas are proposing to carry out Utility asset works on Colne Park Road, White Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 January 2025 and could run through until 20 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 1 Aug 2024 at 10:29.

Cadent Gas logo
Between
2 and 20 Jan 2025
Details
View Map
Share
Follow
Colne Park Road

Cadent Gas are proposing to carry out Utility asset works on Colne Park Road, White Colne.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 January 2025 and could run through until 20 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 5 Nov 2024 at 09:55.

Cadent Gas logo
Between
2 and 20 Jan 2025
Details
View Map
Share
Follow
Colchester Road

Cadent Gas are proposing to carry out Utility asset works on Colchester Road, White Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 January 2025 and could run through until 20 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 1 Aug 2024 at 11:30.

Cadent Gas logo
Between
2 and 20 Jan 2025
Details
View Map
Share
Follow
Colchester Road

Cadent Gas are proposing to carry out Utility asset works on Colchester Road, White Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 2 January 2025 and could run through until 20 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 12 Nov 2024 at 11:20.

Cadent Gas logo
Between
6 and 24 Jan 2025
Details
View Map
Share
Follow
Colchester Road

Cadent Gas are proposing to carry out Utility asset works on Colchester Road, Halstead Urban, Halstead.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 24 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Cadent Gas on 25 Oct 2024 at 10:30.

Cadent Gas logo
Between
6 and 24 Jan 2025
Details
View Map
Share
Follow
Colchester Road

Cadent Gas are proposing to carry out Utility asset works on Colchester Road, Halstead Urban, Halstead.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 24 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Cadent Gas on 15 Nov 2024 at 08:54.

Cadent Gas logo
Between
6 and 24 Jan 2025
Details
View Map
Share
Follow
Fenn Road

Cadent Gas are proposing to carry out Utility asset works on Fenn Road, Halstead Urban, Halstead.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 24 January 2025. The works will impact the footway, carriageway and verge.

This roadwork event was last updated by Cadent Gas on 14 Oct 2024 at 13:58.

Cadent Gas logo
Between
6 and 31 Jan 2025
Details
View Map
Share
Follow
Lower Holt Street

Cadent Gas are proposing to carry out Utility asset works on Lower Holt Street, Earls Colne.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 19 Nov 2024 at 10:40.

Cadent Gas logo
Between
6 and 31 Jan 2025
Details
View Map
Share
Follow
Lower Holt Street

Cadent Gas are proposing to carry out Utility asset works on Lower Holt Street, Earls Colne.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 20 Nov 2024 at 14:21.

Essex County Council logo
Between
6 and 10 Jan 2025
Details
View Map
Share
Follow
Newbarn Road

Essex County Council are proposing to carry out Highway improvement works on Newbarn Road, Great Tey.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 10 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 12 Nov 2024 at 10:33.

Essex County Council logo
Between
6 and 10 Jan 2025
Details
View Map
Share
Follow
Station Road

Essex County Council are proposing to carry out Highway improvement works on Station Road, Wakes Colne.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 10 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 8 Nov 2024 at 11:06.

Cadent Gas logo
Between
13 Jan and 10 Feb 2025
Details
View Map
Share
Follow
Foundry Lane

Cadent Gas are proposing to carry out Utility asset works on Foundry Lane, Earls Colne.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 January 2025 and could run through until 10 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 1 Aug 2024 at 09:01.

Cadent Gas logo
Between
13 Jan and 10 Feb 2025
Details
View Map
Share
Follow
Foundry Lane

Cadent Gas are proposing to carry out Utility asset works on Foundry Lane, Earls Colne.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 January 2025 and could run through until 10 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 21 Oct 2024 at 13:30.

Essex County Council logo
Between
13 Jan and 9 Feb 2025
Details
View Map
Share
Follow
Long Green

Essex County Council are proposing to carry out Highway improvement works on Long Green, Cressing.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 January 2025 and could run through until 9 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 15 Oct 2024 at 11:45.

Essex County Council logo
Between
13 Jan and 9 Feb 2025
Details
View Map
Share
Follow
Long Green

Essex County Council are proposing to carry out Highway improvement works on Long Green, Cressing.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 13 January 2025 and could run through until 9 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 28 Oct 2024 at 09:01.

Essex County Council logo
LONG TERM
Between
20 Jan and 24 Feb 2025
Details
View Map
Share
Follow
Coggeshall Road

Essex County Council are proposing to carry out Highway improvement works on Coggeshall Road, Kelvedon.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 20 January 2025 and could run through until 24 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 23 Oct 2024 at 13:54.

Essex County Council logo
Between
20 and 24 Jan 2025
Details
View Map
Share
Follow
Station Road

Essex County Council are proposing to carry out Highway improvement works on Station Road, Earls Colne.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 20 January 2025 and could run through until 24 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Essex County Council on 11 Nov 2024 at 12:52.

Essex County Council logo
LONG TERM
Between
3 Feb and 14 Mar 2025
Details
View Map
Share
Follow
Kelvedon Road

Essex County Council are proposing to carry out Highway improvement works on Kelvedon Road, Tiptree.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 14 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Essex County Council on 21 Oct 2024 at 14:27.

Anglian Water logo
Between
3 and 7 Feb 2025
Details
View Map
Share
Follow
Maldon Road

Anglian Water are proposing to carry out Utility repair and maintenance works on Maldon Road, Layer Marney.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 7 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Anglian Water on 12 Nov 2024 at 10:31.

Anglian Water logo
Between
3 and 7 Feb 2025
Details
View Map
Share
Follow
Maldon Road

Anglian Water are proposing to carry out Utility repair and maintenance works on Maldon Road, Layer Marney.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 7 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Anglian Water on 15 Nov 2024 at 10:30.

Essex County Council logo
LONG TERM
Between
3 Feb and 14 Mar 2025
Details
View Map
Share
Follow
Kelvedon Road

Essex County Council are proposing to carry out Highway improvement works on Kelvedon Road, Tiptree.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 14 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Essex County Council on 21 Oct 2024 at 15:09.

Cadent Gas logo
Between
10 and 24 Feb 2025
Details
View Map
Share
Follow
Park Lane

Cadent Gas are proposing to carry out Utility asset works on Park Lane, Earls Colne.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 10 February 2025 and could run through until 24 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 1 Aug 2024 at 10:36.

Cadent Gas logo
Between
10 and 24 Feb 2025
Details
View Map
Share
Follow
Park Lane

Cadent Gas are proposing to carry out Utility asset works on Park Lane, Earls Colne.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 10 February 2025 and could run through until 24 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 21 Oct 2024 at 14:22.

Anglian Water logo
Between
17 and 19 Feb 2025
Details
View Map
Share
Follow
Flories Road

Anglian Water are proposing to carry out Utility repair and maintenance works on Flories Road, Great Tey.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 February 2025 and could run through until 19 February 2025. The works will impact the carriageway and verge.

This roadwork event was last updated by Anglian Water on 19 Nov 2024 at 09:20.

Cadent Gas logo
Between
17 Feb and 5 Mar 2025
Details
View Map
Share
Follow
Colne Park Road

Cadent Gas are proposing to carry out Utility asset works on Colne Park Road, White Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 17 February 2025 and could run through until 5 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 20 Nov 2024 at 14:31.

Cadent Gas logo
Between
17 Feb and 5 Mar 2025
Details
View Map
Share
Follow
Colne Park Road

Cadent Gas are proposing to carry out Utility asset works on Colne Park Road, White Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 17 February 2025 and could run through until 5 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 19 Nov 2024 at 09:21.

Cadent Gas logo
Between
17 Feb and 5 Mar 2025
Details
View Map
Share
Follow
Colneford Hill

Cadent Gas are proposing to carry out Utility asset works on Colneford Hill, White Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 17 February 2025 and could run through until 5 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 20 Nov 2024 at 14:09.

Cadent Gas logo
Between
17 Feb and 5 Mar 2025
Details
View Map
Share
Follow
Colneford Hill

Cadent Gas are proposing to carry out Utility asset works on Colneford Hill, White Colne.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 17 February 2025 and could run through until 5 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 20 Nov 2024 at 10:21.

Anglian Water logo
Between
18 and 20 Feb 2025
Details
View Map
Share
Follow
Queen Street

Anglian Water are proposing to carry out Remedial works on Queen Street, Coggeshall.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 18 February 2025 and could run through until 20 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Anglian Water on 15 Nov 2024 at 10:39.


Roadworks Map near to Turner Mews, COLCHESTER, CO6 1FT

Colour Codes
Planned
In Progress
Completed
Cancelled
Last Updated: 22 Nov 2024 05:57
Notes

  • Any red lines indicate the extent of the works.
  • Clicking on the map will re-centre to the selected point.
  • Within 1 mile, all roadworks are displayed.
  • Within 2-3 miles, standard, urgent and major roadworks are displayed.
  • For 3-5 miles, only major roadworks are shown.
  • The higher the marker number, the further away the roadworks are from the centre of the postcode.
  • Where traffic camera videos or images are shown, no historical versions are retained. Once a new image or video becomes available it overwrites the previous version.

Roadworks Listing near to Turner Mews, COLCHESTER, CO6 1FT (2 Events)

Works Location and Details
Actual Work Date
(Scheduled Dates)
Status
Distance
(miles)
1
Essex County Council logo
ST PETERS ROAD 
(0.3 miles)
Essex County Council
Remedial works - Carriageway - Two-way signals
In Progress
Since: 18 Nov 2024 09:43
(Scheduled: 18 Nov 2024 - 22 Nov 2024)
0.3
Details
Share
Follow
2
Anglian Water logo
EMERGENCY
  
BRIDGE STREET 
(0.7 miles)
Anglian Water
Utility repair and maintenance works - Footway - Some carriageway incursion
Complete
19 Nov 2024 10:50 - 20 Nov 2024 12:30
0.7
Details
Share

Contains public sector information licensed under the Open Government Licence v3.0.