ROADWORKS SUMMARY
The Street, BISHOP'S STORTFORD, CM22 6QT

Introduction

Image of petrol pumps

View current and future planned roadworks and road closures for The Street, CM22 6QT and the surrounding area.

Our roadwork details are constantly updated and reflect the current situation and we offer both a map view and a listing. We also highlight the major and significant roadworks occuring near to you help you avoid the worst of the delays to your journey.

The roadworks shown below show all current and proposed works during the next 90 days and historical data is recorded since July 2020.

Please note that we re-publish this data and cannot provide any additional information pertaining to a roadwork event. If you require more information, please contact the organisation carrying out the work.

Data are provided by the Department for Transport.

Have we helped today?

If we have helped you today, please consider buying us a quick coffee to keep us going!

Transport for London Traffic cameras are currently unavailable whilst TfL resolve a data security issue.

Major Roadworks near to The Street, BISHOP'S STORTFORD, CM22 6QT

Details of major roadworks, currently in progress or starting soon and resulting in road closures and/or traffic signal management for The Street are shown here covering a 5 mile radius. See further down for details of all roadworks in your area.

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Affinity Water logo
LONG TERM
Between
26 Sep 2024 and 30 Jan 2025
Details
View Map
Share
Follow
Woodside Way

Affinity Water are proposing to carry out Utility asset works on Woodside Way, Great Dunmow.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 26 September 2024 and could run through until 30 January 2025. The works will impact the footway, carriageway and verge.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Affinity Water on 17 Jul 2024 at 15:19.

Affinity Water logo
LONG TERM
Between
7 Oct 2024 and 10 Feb 2025
Details
View Map
Share
Follow
Woodside Way

Affinity Water are proposing to carry out Utility asset works on Woodside Way, Great Dunmow.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 7 October 2024 and could run through until 10 February 2025. The works will impact the footway, carriageway and verge.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Affinity Water on 4 Oct 2024 at 15:55.

Affinity Water logo
LONG TERM
Between
8 Oct 2024 and 11 Feb 2025
Details
View Map
Share
Woodside Way

Affinity Water were proposing to carry out Utility asset works on Woodside Way, Great Dunmow.

These works were categorised as Major.

Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.

The works were originally planned to start 8 October 2024 and run through until 11 February 2025. The works were due to impact the footway, carriageway and verge.

This roadwork event was last updated by Affinity Water on 23 Sep 2024 at 09:33.

Affinity Water logo
LONG TERM
Between
23 Oct 2024 and 26 Feb 2025
Details
View Map
Share
Follow
Woodside Way

Affinity Water are proposing to carry out Utility asset works on Woodside Way, Great Dunmow.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 23 October 2024 and could run through until 26 February 2025. The works will impact the footway, carriageway and verge.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

This roadwork event was last updated by Affinity Water on 8 Oct 2024 at 12:42.

Affinity Water logo
LONG TERM
Until
26 Feb 2025
Details
View Map
Share
Follow
Woodside Way

Affinity Water are carrying out Utility asset works on Woodside Way, Great Dunmow.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 23 October 2024 at 10:00 and could run through until 26 February 2025. The works will impact the footway, carriageway and verge.

This roadwork event was last updated by Affinity Water on 25 Oct 2024 at 10:56.

Cadent Gas logo
LONG TERM
Finishing
Sunday
Details
View Map
Share
London Road

Cadent Gas were proposing to carry out Utility asset works on London Road, Spellbrook.

These works were categorised as Major.

Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.

The works were originally planned to start 18 November 2024 and run through until 22 December 2024. The works were due to impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 24 Oct 2024 at 10:15.

Cadent Gas logo
LONG TERM
Between
2 Dec 2024 and 31 Mar 2025
Details
View Map
Share
Cambridge Road

Cadent Gas were proposing to carry out Utility asset works on Cambridge Road, Sawbridgeworth.

These works were categorised as Major.

Multi-way signals were planned to be in use for some or all of the period. However, the works were cancelled.

The works were originally planned to start 2 December 2024 and run through until 31 March 2025. The works were due to impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 24 Oct 2024 at 10:14.

Affinity Water logo
LONG TERM
Between
2 Dec 2024 and 28 Feb 2025
Details
View Map
Share
Follow
Woodlands Park Drive

Affinity Water are proposing to carry out Utility asset works on Woodlands Park Drive, Great Dunmow.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 2 December 2024 and could run through until 28 February 2025. The works will impact the footway, carriageway and verge.

This roadwork event was last updated by Affinity Water on 5 Aug 2024 at 16:36.

Electricity Network Company logo
Finishing
Monday
Details
View Map
Share
Follow
Forest Hall Road

Electricity Network Company are carrying out Utility asset works on Forest Hall Road, Birchanger.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 9 December 2024 at 09:00 and could run through until 23 December 2024. The works will impact the carriageway, verge and footpath.

This roadwork event was last updated by Electricity Network Company on 13 Dec 2024 at 15:37.

Hertfordshire County Council logo
Finishing
Monday
Details
View Map
Share
Follow
Farnham Road

Hertfordshire County Council are proposing to carry out Highway improvement works on Farnham Road, Bishop's Stortford.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 9 December 2024 and could run through until 23 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Hertfordshire County Council on 8 Nov 2024 at 15:07.

Hertfordshire County Council logo
Finishing
Friday
Details
View Map
Share
Follow
Farnham Road

Hertfordshire County Council are carrying out Highway improvement works on Farnham Road, Bishop's Stortford.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 9 December 2024 at 09:00 and could run through until 20 December 2024. The works will impact the footway and carriageway.

This roadwork event was last updated by Hertfordshire County Council on 11 Dec 2024 at 21:53.

Affinity Water logo
Finishing
Tomorrow
Details
View Map
Share
Follow
Hallingbury Road

Affinity Water are carrying out Utility repair and maintenance works on Hallingbury Road, Sawbridgeworth.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 14 December 2024 at 08:00 and could run through until 19 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Affinity Water on 16 Dec 2024 at 08:32.

UK Power Networks Eastern & London logo
Finishing
Friday
Details
View Map
Share
Follow
Spellbrook Lane West

UK Power Networks Eastern & London are proposing to carry out New service connection on Spellbrook Lane West, Sawbridgeworth.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 16 December 2024 and could run through until 20 December 2024. The works will impact the verge only.

This roadwork event was last updated by UK Power Networks Eastern & London on 7 Oct 2024 at 12:06.

UK Power Networks Eastern & London logo
Finishing
Today
Details
View Map
Share
Follow
Spellbrook Lane West

UK Power Networks Eastern & London are carrying out New service connection on Spellbrook Lane West, Sawbridgeworth.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 16 December 2024 at 10:13 and could run through until 18 December 2024. The works will impact the verge only.

This roadwork event was last updated by UK Power Networks Eastern & London on 16 Dec 2024 at 10:13.

Essex County Council logo
Finishing
Friday
Details
View Map
Share
Follow
Church Road

Essex County Council are proposing to carry out Highway improvement works on Church Road, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 18 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 20 Nov 2024 at 16:16.

Essex County Council logo
Finishing
Friday
Details
View Map
Share
Follow
Church Road

Essex County Council are proposing to carry out Highway improvement works on Church Road, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 18 December 2024 and could run through until 20 December 2024. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 27 Nov 2024 at 11:11.

Affinity Water logo
Finishing
Monday
Details
View Map
Share
Woodlands Park Drive

Affinity Water were proposing to carry out Utility repair and maintenance works on Woodlands Park Drive, Great Dunmow.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 19 December 2024 and run through until 23 December 2024. The works were due to impact the carriageway only.

This roadwork event was last updated by Affinity Water on 4 Oct 2024 at 12:26.

Affinity Water logo
Between
30 Dec 2024 and 2 Jan 2025
Details
View Map
Share
South Street

Affinity Water were proposing to carry out Utility repair and maintenance works on South Street, Bishop's Stortford.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 30 December 2024 and run through until 2 January 2025. The works were due to impact the carriageway only.

This roadwork event was last updated by Affinity Water on 8 Oct 2024 at 15:02.

Electricity Network Company logo
Between
3 and 31 Jan 2025
Details
View Map
Share
Follow
Gipsy Lane

Electricity Network Company are proposing to carry out Utility asset works on Gipsy Lane, Birchanger.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 January 2025 and could run through until 31 January 2025. The works will impact the carriageway and verge.

This roadwork event was last updated by Electricity Network Company on 25 Sep 2024 at 10:36.

Electricity Network Company logo
Between
3 and 31 Jan 2025
Details
View Map
Share
Follow
Gipsy Lane

Electricity Network Company are proposing to carry out Utility asset works on Gipsy Lane, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 January 2025 and could run through until 31 January 2025. The works will impact the carriageway and verge.

This roadwork event was last updated by Electricity Network Company on 16 Sep 2024 at 07:55.

Electricity Network Company logo
Between
3 and 31 Jan 2025
Details
View Map
Share
Follow
Gipsy Lane

Electricity Network Company are proposing to carry out Utility asset works on Gipsy Lane, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 January 2025 and could run through until 31 January 2025. The works will impact the carriageway and verge.

This roadwork event was last updated by Electricity Network Company on 17 Sep 2024 at 07:22.

Hertfordshire County Council logo
Between
6 and 31 Jan 2025
Details
View Map
Share
Follow
Farnham Road

Hertfordshire County Council are proposing to carry out Works for road purposes on Farnham Road, Bishop's Stortford.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Hertfordshire County Council on 19 Jul 2024 at 09:04.

Hertfordshire County Council logo
Between
6 and 31 Jan 2025
Details
View Map
Share
Follow
Farnham Road

Hertfordshire County Council are proposing to carry out Highway improvement works on Farnham Road, Bishop's Stortford.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Hertfordshire County Council on 8 Nov 2024 at 15:07.

Hertfordshire County Council logo
Between
6 and 31 Jan 2025
Details
View Map
Share
Follow
Farnham Road

Hertfordshire County Council are proposing to carry out Highway improvement works on Farnham Road, Bishop's Stortford.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Hertfordshire County Council on 8 Nov 2024 at 15:15.

Cadent Gas logo
Between
6 and 31 Jan 2025
Details
View Map
Share
Follow
Grove Hill

Cadent Gas are proposing to carry out Utility asset works on Grove Hill, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 15 Oct 2024 at 14:59.

Cadent Gas logo
Between
6 and 31 Jan 2025
Details
View Map
Share
Grove Hill

Cadent Gas were proposing to carry out Utility asset works on Grove Hill, Stansted.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 6 January 2025 and run through until 31 January 2025. The works were due to impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 25 Sep 2024 at 15:02.

Affinity Water logo
Between
6 and 9 Jan 2025
Details
View Map
Share
Follow
Green Street

Affinity Water are proposing to carry out Utility asset works on Green Street, Elsenham.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 9 January 2025. The works will impact the carriageway and verge.

This roadwork event was last updated by Affinity Water on 15 Oct 2024 at 14:18.

Affinity Water logo
Between
6 and 9 Jan 2025
Details
View Map
Share
Follow
Green Street

Affinity Water are proposing to carry out Utility asset works on Green Street, Elsenham.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 9 January 2025. The works will impact the carriageway and verge.

This roadwork event was last updated by Affinity Water on 4 Nov 2024 at 09:46.

Cadent Gas logo
Between
6 and 31 Jan 2025
Details
View Map
Share
Follow
Stansted Road

Cadent Gas are proposing to carry out Utility asset works on Stansted Road, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 31 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 23 Oct 2024 at 10:38.

Cadent Gas logo
Between
6 and 31 Jan 2025
Details
View Map
Share
Stansted Road

Cadent Gas were proposing to carry out Utility asset works on Stansted Road, Stansted.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 6 January 2025 and run through until 31 January 2025. The works were due to impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 25 Sep 2024 at 15:12.

Cadent Gas logo
Between
6 Jan and 3 Feb 2025
Details
View Map
Share
Follow
Lower Street

Cadent Gas are proposing to carry out Utility asset works on Lower Street, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 3 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 21 Oct 2024 at 14:02.

Affinity Water logo
Between
7 and 9 Jan 2025
Details
View Map
Share
Church Road

Affinity Water were proposing to carry out Utility repair and maintenance works on Church Road, Great Hallingbury.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 7 January 2025 and run through until 9 January 2025. The works were due to impact the verge only.

This roadwork event was last updated by Affinity Water on 8 Oct 2024 at 08:25.

Affinity Water logo
Between
7 and 9 Jan 2025
Details
View Map
Share
Church Road

Affinity Water were proposing to carry out Utility repair and maintenance works on Church Road, Great Hallingbury.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 7 January 2025 and run through until 9 January 2025. The works were due to impact the verge only.

This roadwork event was last updated by Affinity Water on 8 Oct 2024 at 08:34.

Affinity Water logo
Between
7 and 9 Jan 2025
Details
View Map
Share
Follow
Church Road

Affinity Water are proposing to carry out Utility repair and maintenance works on Church Road, Great Hallingbury.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 January 2025 and could run through until 9 January 2025. The works will impact the verge only.

This roadwork event was last updated by Affinity Water on 18 Oct 2024 at 17:50.

Affinity Water logo
Between
7 and 9 Jan 2025
Details
View Map
Share
Follow
Church Road

Affinity Water are proposing to carry out Utility repair and maintenance works on Church Road, Great Hallingbury.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 January 2025 and could run through until 9 January 2025. The works will impact the verge only.

This roadwork event was last updated by Affinity Water on 4 Nov 2024 at 10:23.

Affinity Water logo
Between
7 and 9 Jan 2025
Details
View Map
Share
Follow
Church Road

Affinity Water are proposing to carry out Utility repair and maintenance works on Church Road, Great Hallingbury.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 January 2025 and could run through until 9 January 2025. The works will impact the verge only.

This roadwork event was last updated by Affinity Water on 5 Dec 2024 at 14:59.

Affinity Water logo
Between
7 and 9 Jan 2025
Details
View Map
Share
Follow
Birchanger Lane

Affinity Water are proposing to carry out Utility repair and maintenance works on Birchanger Lane, Birchanger.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 January 2025 and could run through until 9 January 2025. The works will impact the verge only.

This roadwork event was last updated by Affinity Water on 15 Oct 2024 at 13:10.

Affinity Water logo
Between
7 and 9 Jan 2025
Details
View Map
Share
Follow
Birchanger Lane

Affinity Water are proposing to carry out Utility repair and maintenance works on Birchanger Lane, Birchanger.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 January 2025 and could run through until 9 January 2025. The works will impact the verge only.

This roadwork event was last updated by Affinity Water on 1 Nov 2024 at 10:38.

Essex County Council logo
Between
13 Jan and 7 Feb 2025
Details
View Map
Share
Follow
Stane Street

Essex County Council are proposing to carry out Highway improvement works on Stane Street, Great Hallingbury.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 13 January 2025 and could run through until 7 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 14 Nov 2024 at 10:52.

BT logo
Between
13 and 17 Jan 2025
Details
View Map
Share
Brick End Lane

BT were proposing to carry out Utility asset works on Brick End Lane, Broxted.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 13 January 2025 and run through until 17 January 2025. The works were due to impact the footway, carriageway and verge.

This roadwork event was last updated by BT on 17 Dec 2024 at 15:10.

UK Power Networks Eastern & London logo
Between
15 and 18 Jan 2025
Details
View Map
Share
Follow
Burton End Road

UK Power Networks Eastern & London are proposing to carry out Disconnection or alteration of supply on Burton End Road, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 15 January 2025 and could run through until 18 January 2025. The works will impact the carriageway and verge.

This roadwork event was last updated by UK Power Networks Eastern & London on 26 Nov 2024 at 16:24.

Cadent Gas logo
Between
20 and 23 Jan 2025
Details
View Map
Share
Follow
Market Street

Cadent Gas are proposing to carry out New service connection on Market Street, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 20 January 2025 and could run through until 23 January 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 31 Oct 2024 at 13:23.

Essex County Council logo
Between
20 and 24 Jan 2025
Details
View Map
Share
Follow
Parsonage Road

Essex County Council are proposing to carry out Remedial works on Parsonage Road, Takeley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 20 January 2025 and could run through until 24 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 11 Dec 2024 at 15:59.

Electricity Network Company logo
Between
20 Jan and 14 Feb 2025
Details
View Map
Share
Follow
Gipsy Lane

Electricity Network Company are proposing to carry out Utility asset works on Gipsy Lane, Birchanger.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 20 January 2025 and could run through until 14 February 2025. The works will impact the carriageway and verge.

This roadwork event was last updated by Electricity Network Company on 19 Aug 2024 at 16:16.

Electricity Network Company logo
Between
20 Jan and 14 Feb 2025
Details
View Map
Share
Follow
Gipsy Lane

Electricity Network Company are proposing to carry out Utility asset works on Gipsy Lane, Birchanger.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 20 January 2025 and could run through until 14 February 2025. The works will impact the carriageway and verge.

This roadwork event was last updated by Electricity Network Company on 16 Sep 2024 at 14:40.

Electricity Network Company logo
Between
20 Jan and 14 Feb 2025
Details
View Map
Share
Follow
Gipsy Lane

Electricity Network Company are proposing to carry out Utility asset works on Gipsy Lane, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 20 January 2025 and could run through until 14 February 2025. The works will impact the carriageway and verge.

This roadwork event was last updated by Electricity Network Company on 20 Aug 2024 at 14:45.

Essex County Council logo
Between
24 and 28 Jan 2025
Details
View Map
Share
Follow
Cambridge Road

Essex County Council are proposing to carry out Highway improvement works on Cambridge Road, Ugley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 January 2025 and could run through until 28 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 10 Dec 2024 at 10:56.

Essex County Council logo
Between
24 and 28 Jan 2025
Details
View Map
Share
Follow
London Road

Essex County Council are proposing to carry out Highway improvement works on London Road, Ugley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 January 2025 and could run through until 28 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 10 Dec 2024 at 10:56.

Gigaclear logo
Between
28 and 31 Jan 2025
Details
View Map
Share
Follow
Wrights Green Lane

Gigaclear are proposing to carry out Remedial works on Wrights Green Lane, Little Hallingbury.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 January 2025 and could run through until 31 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Gigaclear on 3 Dec 2024 at 08:57.

Gigaclear logo
Between
28 and 31 Jan 2025
Details
View Map
Share
Follow
Wrights Green Lane

Gigaclear are proposing to carry out Remedial works on Wrights Green Lane, Little Hallingbury.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 28 January 2025 and could run through until 31 January 2025. The works will impact the carriageway only.

This roadwork event was last updated by Gigaclear on 9 Dec 2024 at 14:20.

Hertfordshire County Council logo
Between
28 Jan and 4 Feb 2025
Details
View Map
Share
Obrey Way

Hertfordshire County Council were proposing to carry out Highway repair and maintenance works on Obrey Way, Bishop's Stortford.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 28 January 2025 and run through until 4 February 2025. The works were due to impact the footway and carriageway.

This roadwork event was last updated by Hertfordshire County Council on 26 Nov 2024 at 09:12.

Hertfordshire County Council logo
Between
30 Jan and 3 Feb 2025
Details
View Map
Share
Follow
Gilbey Avenue

Hertfordshire County Council are proposing to carry out Highway improvement works on Gilbey Avenue, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 30 January 2025 and could run through until 3 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 21 Nov 2024 at 14:14.

Hertfordshire County Council logo
Between
30 Jan and 3 Feb 2025
Details
View Map
Share
Follow
Gilbey Avenue

Hertfordshire County Council are proposing to carry out Highway improvement works on Gilbey Avenue, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 30 January 2025 and could run through until 3 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 11 Dec 2024 at 20:48.

Gigaclear logo
Between
30 Jan and 3 Feb 2025
Details
View Map
Share
Bentfield Green

Gigaclear were proposing to carry out Utility asset works on Bentfield Green, Stansted.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 30 January 2025 and run through until 3 February 2025. The works were due to impact the footway, carriageway and verge.

This roadwork event was last updated by Gigaclear on 2 Oct 2024 at 15:35.

Gigaclear logo
Between
30 Jan and 3 Feb 2025
Details
View Map
Share
Follow
Bentfield Green

Gigaclear are proposing to carry out Utility asset works on Bentfield Green, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 30 January 2025 and could run through until 3 February 2025. The works will impact the footway, carriageway and verge.

This roadwork event was last updated by Gigaclear on 11 Nov 2024 at 14:00.

Hertfordshire County Council logo
Between
31 Jan and 4 Feb 2025
Details
View Map
Share
Follow
Urban Road

Hertfordshire County Council are proposing to carry out Highway repair and maintenance works on Urban Road, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 31 January 2025 and could run through until 4 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 21 Nov 2024 at 15:12.

Hertfordshire County Council logo
Between
31 Jan and 4 Feb 2025
Details
View Map
Share
Follow
Urban Road

Hertfordshire County Council are proposing to carry out Highway repair and maintenance works on Urban Road, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 31 January 2025 and could run through until 4 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 6 Dec 2024 at 14:51.

Affinity Water logo
Between
3 and 6 Feb 2025
Details
View Map
Share
Follow
Poplars Lane

Affinity Water are proposing to carry out Utility asset works on Poplars Lane, White Roding.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 6 February 2025. The works will impact the carriageway and verge.

This roadwork event was last updated by Affinity Water on 14 Nov 2024 at 10:19.

Affinity Water logo
Between
3 and 6 Feb 2025
Details
View Map
Share
Follow
Poplars Lane

Affinity Water are proposing to carry out Utility asset works on Poplars Lane, White Roding.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 6 February 2025. The works will impact the carriageway and verge.

This roadwork event was last updated by Affinity Water on 22 Nov 2024 at 16:01.

Essex County Council logo
Between
3 and 11 Feb 2025
Details
View Map
Share
Follow
Old Street Hill

Essex County Council are proposing to carry out Highway improvement works on Old Street Hill, Hatfield Heath.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 11 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 10 Dec 2024 at 13:02.

Essex County Council logo
Between
3 and 11 Feb 2025
Details
View Map
Share
Follow
Old Street Hill

Essex County Council are proposing to carry out Highway improvement works on Old Street Hill, Hatfield Broad Oak.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 11 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 10 Dec 2024 at 13:12.

Essex County Council logo
Between
3 and 11 Feb 2025
Details
View Map
Share
Follow
Feathers Hill

Essex County Council are proposing to carry out Highway improvement works on Feathers Hill, Hatfield Broad Oak.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 11 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 10 Dec 2024 at 13:12.

Essex County Council logo
Between
3 and 11 Feb 2025
Details
View Map
Share
Follow
High Street

Essex County Council are proposing to carry out Highway improvement works on High Street, Hatfield Broad Oak.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 11 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 10 Dec 2024 at 13:24.

Essex County Council logo
Between
3 and 11 Feb 2025
Details
View Map
Share
Follow
Dunmow Road

Essex County Council are proposing to carry out Highway improvement works on Dunmow Road, Hatfield Broad Oak.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 11 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 10 Dec 2024 at 13:37.

Hertfordshire County Council logo
Between
3 and 5 Feb 2025
Details
View Map
Share
Follow
Mayfield Park

Hertfordshire County Council are proposing to carry out Highway repair and maintenance works on Mayfield Park, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 5 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 21 Nov 2024 at 14:52.

Hertfordshire County Council logo
Between
3 and 5 Feb 2025
Details
View Map
Share
Follow
Mayfield Park

Hertfordshire County Council are proposing to carry out Highway repair and maintenance works on Mayfield Park, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 5 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 10 Dec 2024 at 12:55.

Essex County Council logo
Between
3 and 11 Feb 2025
Details
View Map
Share
Follow
Station Road

Essex County Council are proposing to carry out Highway improvement works on Station Road, Takeley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 11 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 10 Dec 2024 at 13:51.

Hertfordshire County Council logo
Between
3 and 5 Feb 2025
Details
View Map
Share
Follow
North Terrace

Hertfordshire County Council are proposing to carry out Highway repair and maintenance works on North Terrace, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 5 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 21 Nov 2024 at 15:13.

Hertfordshire County Council logo
Between
3 and 5 Feb 2025
Details
View Map
Share
Follow
North Terrace

Hertfordshire County Council are proposing to carry out Highway repair and maintenance works on North Terrace, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 5 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 10 Dec 2024 at 12:55.

Hertfordshire County Council logo
Between
3 and 5 Feb 2025
Details
View Map
Share
Follow
Alconbury

Hertfordshire County Council are proposing to carry out Highway repair and maintenance works on Alconbury, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 5 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 21 Nov 2024 at 15:08.

Hertfordshire County Council logo
Between
3 and 5 Feb 2025
Details
View Map
Share
Follow
Alconbury

Hertfordshire County Council are proposing to carry out Highway repair and maintenance works on Alconbury, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 5 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 9 Dec 2024 at 15:25.

Affinity Water logo
Between
3 and 5 Feb 2025
Details
View Map
Share
Follow
Farnham Road

Affinity Water are proposing to carry out Utility repair and maintenance works on Farnham Road, Farnham.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 February 2025 and could run through until 5 February 2025. The works will impact the verge only.

This roadwork event was last updated by Affinity Water on 12 Dec 2024 at 10:49.

Hertfordshire County Council logo
Between
4 and 6 Feb 2025
Details
View Map
Share
Follow
Waytemore Road

Hertfordshire County Council are proposing to carry out Highway repair and maintenance works on Waytemore Road, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 February 2025 and could run through until 6 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 21 Nov 2024 at 13:34.

Hertfordshire County Council logo
Between
4 and 6 Feb 2025
Details
View Map
Share
Follow
Waytemore Road

Hertfordshire County Council are proposing to carry out Highway repair and maintenance works on Waytemore Road, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 4 February 2025 and could run through until 6 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 9 Dec 2024 at 16:00.

Essex County Council logo
Between
6 and 8 Feb 2025
Details
View Map
Share
Follow
Chapel Hill

Essex County Council are proposing to carry out Highway improvement works on Chapel Hill, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 6 February 2025 and could run through until 8 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 13 Dec 2024 at 12:44.

Hertfordshire County Council logo
Between
10 and 12 Feb 2025
Details
View Map
Share
Follow
Obrey Way

Hertfordshire County Council are proposing to carry out Highway repair and maintenance works on Obrey Way, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 February 2025 and could run through until 12 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 10 Dec 2024 at 13:24.

Hertfordshire County Council logo
Between
10 and 16 Feb 2025
Details
View Map
Share
Follow
Obrey Way

Hertfordshire County Council are proposing to carry out Highway repair and maintenance works on Obrey Way, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 February 2025 and could run through until 16 February 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Hertfordshire County Council on 3 Dec 2024 at 10:52.

Cadent Gas logo
Between
10 Feb and 7 Mar 2025
Details
View Map
Share
Follow
Grove Hill

Cadent Gas are proposing to carry out Utility asset works on Grove Hill, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 February 2025 and could run through until 7 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 14 Nov 2024 at 16:05.

Cadent Gas logo
Between
10 Feb and 7 Mar 2025
Details
View Map
Share
Follow
Grove Hill

Cadent Gas are proposing to carry out Utility asset works on Grove Hill, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 February 2025 and could run through until 7 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 27 Nov 2024 at 14:54.

Cadent Gas logo
Between
10 Feb and 7 Mar 2025
Details
View Map
Share
Follow
Stansted Road

Cadent Gas are proposing to carry out Utility asset works on Stansted Road, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 February 2025 and could run through until 7 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 15 Nov 2024 at 11:55.

Cadent Gas logo
Between
10 Feb and 7 Mar 2025
Details
View Map
Share
Follow
Stansted Road

Cadent Gas are proposing to carry out Utility asset works on Stansted Road, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 February 2025 and could run through until 7 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 27 Nov 2024 at 14:48.

UK Power Networks Eastern & London logo
Between
11 and 14 Feb 2025
Details
View Map
Share
Follow
Dunmow Road

UK Power Networks Eastern & London are proposing to carry out New service connection on Dunmow Road, High Roding.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 11 February 2025 and could run through until 14 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by UK Power Networks Eastern & London on 19 Nov 2024 at 12:58.

UK Power Networks Eastern & London logo
Between
11 and 14 Feb 2025
Details
View Map
Share
Follow
Dunmow Road

UK Power Networks Eastern & London are proposing to carry out New service connection on Dunmow Road, High Roding.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 11 February 2025 and could run through until 14 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by UK Power Networks Eastern & London on 28 Nov 2024 at 08:05.

UK Power Networks Eastern & London logo
Between
11 and 14 Feb 2025
Details
View Map
Share
Follow
Burton End Road

UK Power Networks Eastern & London are proposing to carry out Disconnection or alteration of supply on Burton End Road, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 11 February 2025 and could run through until 14 February 2025. The works will impact the carriageway and verge.

This roadwork event was last updated by UK Power Networks Eastern & London on 25 Nov 2024 at 12:46.

Hertfordshire County Council logo
Between
17 and 25 Feb 2025
Details
View Map
Share
Stortford Hall Park

Hertfordshire County Council were proposing to carry out Highway repair and maintenance works on Stortford Hall Park, Bishop's Stortford.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 17 February 2025 and run through until 25 February 2025. The works were due to impact the footway and carriageway.

This roadwork event was last updated by Hertfordshire County Council on 12 Dec 2024 at 09:57.

Hertfordshire County Council logo
Between
17 and 21 Feb 2025
Details
View Map
Share
Follow
Rye Street

Hertfordshire County Council are proposing to carry out Highway repair and maintenance works on Rye Street, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 February 2025 and could run through until 21 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 8 Aug 2024 at 14:10.

Hertfordshire County Council logo
Between
17 and 21 Feb 2025
Details
View Map
Share
Follow
Rye Street

Hertfordshire County Council are proposing to carry out Highway repair and maintenance works on Rye Street, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 February 2025 and could run through until 21 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 15 Aug 2024 at 14:05.

Hertfordshire County Council logo
Between
17 and 21 Feb 2025
Details
View Map
Share
Follow
Rye Street

Hertfordshire County Council are proposing to carry out Highway repair and maintenance works on Rye Street, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 17 February 2025 and could run through until 21 February 2025. The works will impact the carriageway only.

This roadwork event was last updated by Hertfordshire County Council on 8 Aug 2024 at 11:59.

Affinity Water logo
Between
24 Feb and 17 Mar 2025
Details
View Map
Share
Follow
Bambers Green Road

Affinity Water are proposing to carry out Utility asset works on Bambers Green Road, Takeley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 February 2025 and could run through until 17 March 2025. The works will impact the carriageway only.

This roadwork event was last updated by Affinity Water on 2 Dec 2024 at 11:21.

Affinity Water logo
Between
24 Feb and 17 Mar 2025
Details
View Map
Share
Follow
Bambers Green Road

Affinity Water are proposing to carry out Utility asset works on Bambers Green Road, Takeley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 February 2025 and could run through until 17 March 2025. The works will impact the carriageway only.

This roadwork event was last updated by Affinity Water on 11 Dec 2024 at 12:37.

Affinity Water logo
Between
24 Feb and 17 Mar 2025
Details
View Map
Share
Follow
Cobbs Lane

Affinity Water are proposing to carry out Utility asset works on Cobbs Lane, Takeley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 February 2025 and could run through until 17 March 2025. The works will impact the carriageway only.

This roadwork event was last updated by Affinity Water on 2 Dec 2024 at 11:11.

Affinity Water logo
Between
24 Feb and 17 Mar 2025
Details
View Map
Share
Follow
Cobbs Lane

Affinity Water are proposing to carry out Utility asset works on Cobbs Lane, Takeley.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 24 February 2025 and could run through until 17 March 2025. The works will impact the carriageway only.

This roadwork event was last updated by Affinity Water on 12 Dec 2024 at 11:17.

Essex County Council logo
Between
3 and 11 Mar 2025
Details
View Map
Share
Follow
Dunmow Road

Essex County Council are proposing to carry out Highway improvement works on Dunmow Road, Hatfield Heath.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 March 2025 and could run through until 11 March 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 10 Dec 2024 at 12:52.

Hertfordshire County Council logo
Between
3 and 30 Mar 2025
Details
View Map
Share
Follow
Farnham Road

Hertfordshire County Council are proposing to carry out Highway improvement works on Farnham Road, Bishop's Stortford.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 3 March 2025 and could run through until 30 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Hertfordshire County Council on 8 Nov 2024 at 15:07.

Hertfordshire County Council logo
LONG TERM
Between
3 Mar and 12 Apr 2025
Details
View Map
Share
Follow
Farnham Road

Hertfordshire County Council are proposing to carry out Highway improvement works on Farnham Road, Bishop's Stortford.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 3 March 2025 and could run through until 12 April 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Hertfordshire County Council on 8 Nov 2024 at 15:16.

Cadent Gas logo
Between
3 and 28 Mar 2025
Details
View Map
Share
Follow
Lower Street

Cadent Gas are proposing to carry out Utility asset works on Lower Street, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 March 2025 and could run through until 28 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 2 Dec 2024 at 12:13.

Cadent Gas logo
Between
3 and 28 Mar 2025
Details
View Map
Share
Follow
Lower Street

Cadent Gas are proposing to carry out Utility asset works on Lower Street, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 March 2025 and could run through until 28 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 17 Dec 2024 at 09:08.

Cadent Gas logo
Between
3 and 28 Mar 2025
Details
View Map
Share
Follow
High Lane

Cadent Gas are proposing to carry out Utility asset works on High Lane, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 March 2025 and could run through until 28 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 2 Dec 2024 at 11:55.

Cadent Gas logo
Between
3 and 28 Mar 2025
Details
View Map
Share
Follow
High Lane

Cadent Gas are proposing to carry out Utility asset works on High Lane, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 3 March 2025 and could run through until 28 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Cadent Gas on 17 Dec 2024 at 09:00.

Essex County Council logo
Between
7 and 9 Mar 2025
Details
View Map
Share
Follow
Grove Hill

Essex County Council are proposing to carry out Highway improvement works on Grove Hill, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 March 2025 and could run through until 9 March 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 4 Dec 2024 at 09:38.

Essex County Council logo
Between
7 and 9 Mar 2025
Details
View Map
Share
Follow
Stansted Road

Essex County Council are proposing to carry out Highway improvement works on Stansted Road, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 7 March 2025 and could run through until 9 March 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 4 Dec 2024 at 09:38.

Essex County Council logo
Between
8 and 23 Mar 2025
Details
View Map
Share
Follow
Church Road

Essex County Council are proposing to carry out Highway improvement works on Church Road, Stansted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 8 March 2025 and could run through until 23 March 2025. The works will impact the carriageway and verge.

This roadwork event was last updated by Essex County Council on 2 Dec 2024 at 12:24.

Hertfordshire County Council logo
Between
10 and 13 Mar 2025
Details
View Map
Share
Follow
Farnham Road

Hertfordshire County Council are proposing to carry out Highway improvement works on Farnham Road, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 March 2025 and could run through until 13 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Hertfordshire County Council on 8 Nov 2024 at 15:08.

Hertfordshire County Council logo
Between
10 and 13 Mar 2025
Details
View Map
Share
Follow
Farnham Road

Hertfordshire County Council are proposing to carry out Highway improvement works on Farnham Road, Bishop's Stortford.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 March 2025 and could run through until 13 March 2025. The works will impact the footway and carriageway.

This roadwork event was last updated by Hertfordshire County Council on 8 Nov 2024 at 15:16.

Essex County Council logo
Between
10 and 12 Mar 2025
Details
View Map
Share
Follow
Church End

Essex County Council are proposing to carry out Highway improvement works on Church End, Broxted.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 10 March 2025 and could run through until 12 March 2025. The works will impact the carriageway only.

This roadwork event was last updated by Essex County Council on 5 Dec 2024 at 13:21.


Roadworks Map near to The Street, BISHOP'S STORTFORD, CM22 6QT

Colour Codes
Planned
In Progress
Completed
Cancelled
Last Updated: 18 Dec 2024 03:56
Notes

  • Any red lines indicate the extent of the works.
  • Clicking on the map will re-centre to the selected point.
  • Within 1 mile, all roadworks are displayed.
  • Within 2-3 miles, standard, urgent and major roadworks are displayed.
  • For 3-5 miles, only major roadworks are shown.
  • The higher the marker number, the further away the roadworks are from the centre of the postcode.
  • Where traffic camera videos or images are shown, no historical versions are retained. Once a new image or video becomes available it overwrites the previous version.

Roadworks Listing near to The Street, BISHOP'S STORTFORD, CM22 6QT (2 Events)

Works Location and Details
Actual Work Date
(Scheduled Dates)
Status
Distance
(miles)
1
Gigaclear logo
HATFIELD FOREST ROAD 
(0.2 miles)
Gigaclear
Utility asset works - Carriageway - Two-way signals
Planned
Scheduled: 16 Dec 2024 - 18 Dec 2024
0.2
Details
Share
Follow
2
Gigaclear logo
NORTH ROAD 
(1.0 miles)
Gigaclear
Utility asset works - Footway - Some carriageway incursion
Planned
Scheduled: 19 Dec 2024 - 20 Dec 2024
1.0
Details