The Environment Agency’s 6 year capital investment programme for flood and coastal erosion risk management will reduce the flood risk for at least 300,000 homes between 2015/16 and 2021.

Efficiency savings in the capital programme have been identified in the following categories:

  • innovation and value engineering - where innovative solutions, methods or materials have been used to achieve the same result at reduced cost

  • packaging and programming - where similar projects have been delivered together more efficiently

  • controlling project scope - for example, by maintaining focus on original project outcomes

  • contracting approach - for example, where contracts encourage consultants and contractors to deliver more efficiently

  • streamlining - for example where co-located teams or systems improvements have led to reduced costs

  • standardisation and building information modelling (BIM) - where existing designs, documents and best practice have been used

  • operational productivity

  • bulk buying and economies of scale