ROADWORK EVENT SUMMARY
Jcn Of Private Road To Jcn A76t From C125n At Eliock Bridge To Castle Street between 1 Sep 2024 and 6 Mar 2026

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Jcn Of Private Road To Jcn A76t From C125n At Eliock Bridge To Castle Street

Scottish Water are proposing to carry out roadworks on Jcn Of Private Road To Jcn A76t From C125n At Eliock Bridge To Castle Street.

These works are categorised as Major.

The works will start on or after 1 September 2024 and could run through until 6 March 2026. The works will impact the not yet available only.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

The information for these works was last updated by Scottish Water on 27 February 2024 at 10:31.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Jcn Of Private Road To Jcn A76t From C125n At Eliock Bridge To Castle Street

Works Details

WORKS PLANNED
Major
Scottish Water logo
These works are handled by:
Scottish Water
Dumfries & Galloway Council logo
Local Authority:
Dumfries & Galloway Council
Works Reference SW700-CWA-527262-0001C001
Permit Number 01
Place Name Jcn Of Private Road To Jcn A76t From C125n At Eliock Bridge To Castle Street
Proposed Start 1 Sep 2024
Proposed End 6 Mar 2026
Actual Start
Actual End
Traffic Management Not Yet Known
Impact Not Yet Available
Coordinates
Lat, Lon
55.350689
-3.90695
Last Updated 27 Feb 2024 10:31
Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.