ROADWORK EVENT SUMMARY
Yeoman Street, London between 17 Jul 2020 and 31 Dec 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Yeoman Street, London

Thames Tideway Tunnel are carrying out Statutory Infrastructure Works on Yeoman Street, London.

These works are categorised as Major.

The works started on 17 July 2020 at 09:00 and could run through until 31 December 2024. The works will impact the footway and carriageway.

The information for these works was last updated by Thames Tideway Tunnel on 23 August 2024 at 10:23.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Yeoman Street, London

Works Details

WORKS IN PROGRESS
Major
Thames Tideway Tunnel logo
These works are handled by:
Thames Tideway Tunnel
London Borough Of Lewisham logo
Local Authority:
London Borough Of Lewisham
Works Reference ZE41500000591
Permit Number 02
Place Name Yeoman Street
London
Proposed Start 17 Jul 2020
Proposed End 31 Dec 2024
Actual Start 17 Jul 2020 09:00
Actual End
Traffic Management Priority working
Impact Footway, Carriageway
Coordinates
Lat, Lon
51.491756
-0.039692
Last Updated 23 Aug 2024 10:23
Works History for Activity ZE41500000591 (Yeoman Street, London)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Jul 2020
08:37
Work Started
17 Jul 2020
00:00
22 Dec 2022
00:00
17 Jul 2020
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Nov 2021
13:37
Permit Alteration Granted
17 Jul 2020
00:00
31 Aug 2024
00:00
17 Jul 2020
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 Aug 2024
11:23
Permit Alteration Granted
17 Jul 2020
01:00
31 Dec 2024
00:00
17 Jul 2020
10:00
In Progress

Works Permits for Yeoman Street, London

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.