ROADWORK EVENT SUMMARY
Blackwall Tunnel Approach, London between 8 and 10 Jun 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Blackwall Tunnel Approach, London

This is a PAA (Provisional Advance Authorisation) permit that has been granted before final details of an activity have been finalised. A full permit will be required before activities can commence.


Transport for London (TfL) are proposing to carry out Highway improvement works on Blackwall Tunnel Approach, London.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 8 June 2024 and could run through until 10 June 2024. The works will impact the carriageway only.

The information for these works was last updated by Transport for London (TfL) on 25 March 2024 at 11:51.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Blackwall Tunnel Approach, London

Works Details

WORKS PLANNED
Major (PAA)
Transport for London (TfL) logo
These works are handled by:
Transport for London (TfL)
Transport for London (TfL) logo
Local Authority:
Transport for London (TfL)
Works Reference YG66099046477
Permit Number 01
Place Name Blackwall Tunnel Approach
London
Proposed Start 8 Jun 2024
Proposed End 10 Jun 2024
Actual Start
Actual End
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
51.509396
-0.006766
Last Updated 25 Mar 2024 11:51
Contact Details for Activity YG66099046477 (Blackwall Tunnel Approach, London)

In the event that you have an issue with these works, please contact Transport for London (TfL), the works operator.

It would assist the organisation if you quote the work reference number of YG66099046477.

Transport for London (TfL)
Websitehttps://tfl.gov.uk/help-and-contact/contact-us-about-streets-and-other-road-issues
TelephoneTraffic signals faults 020 7941 2010
TelephoneRed Route Issues 020 7343 5000
Works History for Activity YG66099046477 (Blackwall Tunnel Approach, London)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 Mar 2024
10:27
Permit Submitted
8 Jun 2024
01:01
10 Jun 2024
06:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
25 Mar 2024
11:51
Permit Granted
8 Jun 2024
01:01
10 Jun 2024
06:00
Planned

Works Permits for Blackwall Tunnel Approach, London

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT05a (Width and/or length of road space that can be occupied)

For the activities hereby permitted, it is a condition of this permit that the activity shall occur only within the area [insert description of area or provide traffic management plan reference] including the relevant and required signing, lighting and guarding excluding advance warning, advance communication and diversionary signs.

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT09a (Changes to traffic management arrangements)

For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.