ROADWORK EVENT SUMMARY
Hanger Lane, Ealing between 10 Sep 2020 and 31 Jan 2025

Works Description for Hanger Lane, Ealing

Transport for London (TfL) are carrying out Highway improvement works on Hanger Lane, Ealing.

These works are categorised as Major.

The works should not impact the carriageway.

The works started on 10 September 2020 at 00:00 and could run through until 31 January 2025. The works will impact the footway only.

The information for these works was last updated by Transport for London (TfL) on 21 November 2024 at 10:23.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Hanger Lane, Ealing

Works Details

WORKS IN PROGRESS
Major
Transport for London (TfL) logo
These works are handled by:
Transport for London (TfL)
Transport for London (TfL) logo
Local Authority:
Transport for London (TfL)
Works Reference YG42932983568
Permit Number 02
Place Name Hanger Lane
Ealing
Proposed Start 10 Sep 2020
Proposed End 31 Jan 2025
Actual Start 10 Sep 2020 00:00
Actual End
Traffic Management No carriageway incursion
Impact Footway
Coordinates
Lat, Lon
51.518067
-0.291356
Last Updated 21 Nov 2024 10:23
Contact Details for Activity YG42932983568 (Hanger Lane, Ealing)

In the event that you have an issue with these works, please contact Transport for London (TfL), the works operator.

It would assist the organisation if you quote the work reference number of YG42932983568.

Transport for London (TfL)
Websitehttps://tfl.gov.uk/help-and-contact/contact-us-about-streets-and-other-road-issues
TelephoneTraffic signals faults 020 7941 2010
TelephoneRed Route Issues 020 7343 5000
Works History for Activity YG42932983568 (Hanger Lane, Ealing)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Sep 2020
13:07
Permit Submitted
10 Sep 2020
00:00
30 Oct 2020
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Sep 2020
14:46
Permit Granted
10 Sep 2020
00:00
30 Oct 2020
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Sep 2020
08:11
Work Started
10 Sep 2020
00:00
30 Oct 2020
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
2 Nov 2020
09:33
Work Stopped
10 Sep 2020
00:00
30 Oct 2020
23:59
10 Sep 2020
00:00
30 Oct 2020
23:59
Completed
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Nov 2020
11:53
Work Stopped (Reverted)
10 Sep 2020
00:00
30 Oct 2020
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Nov 2020
12:58
Permit Alteration Granted
10 Sep 2020
00:00
31 Jan 2021
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
1 Feb 2021
09:36
Work Stopped
10 Sep 2020
00:00
31 Jan 2021
23:59
10 Sep 2020
00:00
31 Jan 2021
23:59
Completed
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
1 Feb 2021
10:28
Work Stopped (Reverted)
10 Sep 2020
00:00
31 Jan 2021
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
1 Feb 2021
10:58
Permit Alteration Granted
10 Sep 2020
00:00
28 Feb 2021
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
5 Mar 2021
15:54
Permit Alteration Granted
10 Sep 2020
00:00
31 Mar 2021
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
31 Mar 2021
23:52
Work Stopped
10 Sep 2020
00:00
31 Mar 2021
23:59
10 Sep 2020
00:00
31 Mar 2021
23:59
Completed
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
13 Apr 2021
08:30
Work Stopped (Reverted)
10 Sep 2020
00:00
31 Mar 2021
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
13 Apr 2021
09:53
Permit Alteration Granted
10 Sep 2020
00:00
31 May 2021
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 May 2021
08:47
Permit Alteration Granted
10 Sep 2020
00:00
30 Jun 2021
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
30 Jun 2021
23:02
Work Stopped
10 Sep 2020
00:00
30 Jun 2021
23:59
10 Sep 2020
00:00
30 Jun 2021
23:59
Completed
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
6 Aug 2021
08:16
Work Stopped (Reverted)
10 Sep 2020
00:00
30 Jun 2021
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
6 Aug 2021
09:39
Permit Alteration Granted
10 Sep 2020
00:00
31 Oct 2021
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
12 Oct 2021
09:14
Permit Alteration Granted
10 Sep 2020
00:00
31 Jan 2022
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Dec 2021
13:10
Permit Alteration Granted
10 Sep 2020
00:00
30 Apr 2022
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
27 Jan 2023
09:49
Permit Alteration Granted
10 Sep 2020
00:00
31 Aug 2023
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Aug 2023
10:54
Permit Alteration Granted
10 Sep 2020
00:00
30 Sep 2023
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
30 Sep 2023
23:27
Work Stopped
10 Sep 2020
00:00
30 Sep 2023
23:59
10 Sep 2020
00:00
30 Sep 2023
23:59
Completed
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Oct 2023
12:44
Work Stopped (Reverted)
10 Sep 2020
00:00
30 Sep 2023
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Oct 2023
13:06
Permit Alteration Granted
10 Sep 2020
00:00
31 Dec 2023
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
14 Dec 2023
12:59
Permit Alteration Granted
10 Sep 2020
00:00
29 Feb 2024
23:59
10 Sep 2020
00:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Feb 2024
11:11
Permit Alteration Granted
10 Sep 2020
01:00
1 May 2024
00:59
10 Sep 2020
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
1 May 2024
12:54
Permit Alteration Granted
10 Sep 2020
01:00
1 Jul 2024
00:59
10 Sep 2020
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
24 Jun 2024
11:45
Permit Alteration Granted
10 Sep 2020
01:00
1 Aug 2024
00:59
10 Sep 2020
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
30 Jul 2024
12:21
Permit Alteration Granted
10 Sep 2020
01:00
1 Oct 2024
00:59
10 Sep 2020
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
26 Sep 2024
13:41
Permit Alteration Granted
10 Sep 2020
01:00
30 Nov 2024
23:59
10 Sep 2020
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Nov 2024
10:23
Permit Alteration Granted
10 Sep 2020
01:00
31 Jan 2025
23:59
10 Sep 2020
01:00
In Progress

Works Permits for Hanger Lane, Ealing

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT05a (Width and/or length of road space that can be occupied)

For the activities hereby permitted, it is a condition of this permit that the activity shall occur only within the area [insert description of area or provide traffic management plan reference] including the relevant and required signing, lighting and guarding excluding advance warning, advance communication and diversionary signs.

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.