ROADWORK EVENT SUMMARY
Delamere Road, Plymouth between 7 Aug and 16 Sep 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Delamere Road, Plymouth

Wales And West Utilities carried out Utility repair and maintenance works on Delamere Road, Plymouth.

These works were categorised as Major.

Multi-way signals were in place for some or all of the period.

The works were originally planned between 7 Aug 2024 and 23 Sep 2024 and were actually completed between 7 Aug 2024 (15:35) and 16 Sep 2024 (09:00). The works impacted the footway, carriageway and verge.

The information for these works was last updated by Wales And West Utilities on 16 September 2024 at 09:30.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Delamere Road, Plymouth

Works Details

WORKS COMPLETED
Major
Wales And West Utilities logo
These works are handled by:
Wales And West Utilities
Local Authority:
Plymouth City Council
Works Reference XY233003001254603
Permit Number 02
Place Name Delamere Road
Plymouth
Proposed Start 7 Aug 2024
Proposed End 23 Sep 2024
Actual Start 7 Aug 2024 15:35
Actual End 16 Sep 2024 09:00
Traffic Management Multi-way signals
Impact Footway, Carriageway, Verge
Coordinates
Lat, Lon
50.395844
-4.104496
Last Updated 16 Sep 2024 09:30
Contact Details for Activity XY233003001254603 (Delamere Road, Plymouth)

In the event that you have an issue with these works, please contact Wales And West Utilities, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, Plymouth City Council that authorised the works.

It would assist the organisations if you quote the work reference number of XY233003001254603.

Wales And West Utilities
Telephone0800 111 999
Works History for Activity XY233003001254603 (Delamere Road, Plymouth)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Jul 2024
11:18
Permit Submitted
12 Aug 2024
09:00
2 Sep 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Jul 2024
13:35
Permit Granted
12 Aug 2024
09:00
2 Sep 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
7 Aug 2024
14:11
Permit Alteration Granted
7 Aug 2024
09:00
23 Sep 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
7 Aug 2024
16:26
Permit Alteration Granted
7 Aug 2024
09:00
23 Sep 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
7 Aug 2024
16:38
Work Started
7 Aug 2024
09:00
23 Sep 2024
01:00
7 Aug 2024
16:35
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
29 Aug 2024
10:47
Permit Alteration Granted
7 Aug 2024
09:00
23 Sep 2024
01:00
7 Aug 2024
16:35
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
16 Sep 2024
10:30
Work Stopped
7 Aug 2024
09:00
23 Sep 2024
01:00
7 Aug 2024
16:35
16 Sep 2024
10:00
Completed

Works Permits for Delamere Road, Plymouth

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT03 (Activities ancillary to those permitted - supplementary information)

For the activities hereby permitted, it is a condition of this permit that, if there are changes to ancillary activities, either in the street to which the application relates or in an adjacent street that become known about within the duration of the permit, the authority must be notified.

+
NCT08a (Traffic management request)

For the activities hereby permitted, it is a condition of this permit that works, or the relevant part of the activity, shall only take place when the following traffic management is deployed by use of x (where x determines type of control i.e. portable signals, stop/go boards etc.)

+
NCT08b (Manual control of traffic management)

For the activities hereby permitted, it is a condition of this permit that, for the traffic management deployed (state type), it is manually operated between (x hours and y hours).

+
NCT09b (Traffic management arrangements to be in place)

For the activities hereby permitted, it is a condition of this permit that the works comprised in [specified part A/B] of the activities hereby permitted shall be subject to and shall occur only when the following traffic management measures are in place [or as attached in schedule.].

+
NCT09c (Signal removal from operation when no longer required)

This condition is attached to permits in cases where temporary traffic signals are used. For the activities hereby permitted, it is a condition of this permit that activities using portable traffic signals must have the signals (whether manually operated or not) removed from use as soon as possible and no later than four hours after completion of works irrespective of day of completion.

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.