ROADWORK EVENT SUMMARY
Cross Lane, Stocksmoor, Huddersfield between 18 Mar and 11 Apr 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Cross Lane, Stocksmoor, Huddersfield

Northern Gas Networks carried out Utility repair and maintenance works on Cross Lane, Stocksmoor, Huddersfield.

These works were categorised as Major.

Multi-way signals were in place for some or all of the period.

The works were originally planned between 18 Mar 2024 and 23 Apr 2024 and were actually completed between 18 Mar 2024 (14:30) and 11 Apr 2024 (13:30). The works impacted the carriageway only.

The information for these works was last updated by Northern Gas Networks on 11 April 2024 at 13:44.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Cross Lane, Stocksmoor, Huddersfield

Works Details

WORKS COMPLETED
Major
Northern Gas Networks logo
These works are handled by:
Northern Gas Networks
Local Authority:
Kirklees Council
Works Reference XX077003900131269
Permit Number 02
Place Name Cross Lane
Stocksmoor
Huddersfield
Proposed Start 18 Mar 2024
Proposed End 23 Apr 2024
Actual Start 18 Mar 2024 14:30
Actual End 11 Apr 2024 13:30
Traffic Management Multi-way signals
Impact Carriageway
Coordinates
Lat, Lon
53.593075
-1.725475
Last Updated 11 Apr 2024 13:44
Works History for Activity XX077003900131269 (Cross Lane, Stocksmoor, Huddersfield)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
24 Jan 2024
08:22
Permit Submitted
11 Mar 2024
08:00
17 Apr 2024
00:55
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
24 Jan 2024
08:22
Permit Alteration Granted
11 Mar 2024
08:00
17 Apr 2024
00:55
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
24 Jan 2024
11:36
Permit Granted
11 Mar 2024
08:00
17 Apr 2024
00:55
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
27 Feb 2024
07:36
Permit Alteration Granted
18 Mar 2024
08:00
24 Apr 2024
00:55
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
8 Mar 2024
07:30
Permit Alteration Granted
25 Mar 2024
08:00
1 May 2024
00:55
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
18 Mar 2024
14:37
Work Started
25 Mar 2024
08:00
1 May 2024
00:55
18 Mar 2024
14:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Mar 2024
07:11
Permit Alteration Granted
18 Mar 2024
08:00
24 Apr 2024
00:55
18 Mar 2024
14:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Apr 2024
14:44
Work Stopped
18 Mar 2024
08:00
23 Apr 2024
23:55
18 Mar 2024
14:30
11 Apr 2024
14:30
Completed

Works Permits for Cross Lane, Stocksmoor, Huddersfield

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT05a (Width and/or length of road space that can be occupied)

For the activities hereby permitted, it is a condition of this permit that the activity shall occur only within the area [insert description of area or provide traffic management plan reference] including the relevant and required signing, lighting and guarding excluding advance warning, advance communication and diversionary signs.

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT08a (Traffic management request)

For the activities hereby permitted, it is a condition of this permit that works, or the relevant part of the activity, shall only take place when the following traffic management is deployed by use of x (where x determines type of control i.e. portable signals, stop/go boards etc.)

+
NCT09a (Changes to traffic management arrangements)

For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.