ROADWORK EVENT SUMMARY
Dacre To Summerbridge, Dacre Banks between 10 Oct and 26 Nov 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Dacre To Summerbridge, Dacre Banks

Northern Gas Networks are carrying out Utility repair and maintenance works on Dacre To Summerbridge, Dacre Banks.

These works are categorised as Emergency Works with an immediate start.

The works started on 10 October 2024 at 13:32 and could run through until 26 November 2024. The works will impact the footway and carriageway.

The information for these works was last updated by Northern Gas Networks on 19 November 2024 at 15:18.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Dacre To Summerbridge, Dacre Banks

Works Details

WORKS IN PROGRESS
Immediate - emergency
Northern Gas Networks logo
These works are handled by:
Northern Gas Networks
North Yorkshire County Council logo
Local Authority:
North Yorkshire County Council
Works Reference XX055005100503416
Permit Number 01
Place Name Dacre To Summerbridge
Dacre Banks
Proposed Start 10 Oct 2024
Proposed End 26 Nov 2024
Actual Start 10 Oct 2024 13:32
Actual End
Traffic Management Some carriageway incursion
Impact Footway, Carriageway
Coordinates
Lat, Lon
54.0525
-1.701685
Last Updated 19 Nov 2024 15:18
Works History for Activity XX055005100503416 (Dacre To Summerbridge, Dacre Banks)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
10 Oct 2024
15:10
Work Started
10 Oct 2024
14:32
18 Oct 2024
01:00
10 Oct 2024
14:32
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Oct 2024
15:09
Permit Granted
10 Oct 2024
14:32
18 Oct 2024
01:00
10 Oct 2024
14:32
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Oct 2024
09:48
Permit Alteration Granted
10 Oct 2024
14:32
25 Oct 2024
01:00
10 Oct 2024
14:32
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Oct 2024
09:50
Permit Alteration Granted
10 Oct 2024
14:32
25 Oct 2024
01:00
10 Oct 2024
14:32
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
24 Oct 2024
17:17
Permit Alteration Granted
10 Oct 2024
14:32
1 Nov 2024
00:00
10 Oct 2024
14:32
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
5 Nov 2024
15:30
Permit Alteration Granted
10 Oct 2024
14:32
15 Nov 2024
00:00
10 Oct 2024
14:32
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
14 Nov 2024
10:48
Permit Alteration Granted
10 Oct 2024
14:32
20 Nov 2024
00:00
10 Oct 2024
14:32
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Nov 2024
15:18
Permit Alteration Granted
10 Oct 2024
14:32
26 Nov 2024
00:00
10 Oct 2024
14:32
In Progress

Works Permits for Dacre To Summerbridge, Dacre Banks

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT04a (Removal of surplus materials/plant)

For the activities hereby permitted, it is a condition of this permit that all remaining excavated or stored backfill materials and/or any unemployed plant must be removed from the public highway within (x hours e.g. 24) or by the stipulated time (e.g. at the end of the working day or prior to the site being un-occupied) due to (stipulate reason for application of condition).

+
NCT05a (Width and/or length of road space that can be occupied)

For the activities hereby permitted, it is a condition of this permit that the activity shall occur only within the area [insert description of area or provide traffic management plan reference] including the relevant and required signing, lighting and guarding excluding advance warning, advance communication and diversionary signs.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.