ROADWORK EVENT SUMMARY
Eastern Esplanade, Margate between 3 and 24 Dec 2024

Works Description for Eastern Esplanade, Margate

Southern Gas Networks are carrying out Utility repair and maintenance works on Eastern Esplanade, Margate.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 3 December 2024 at 16:35 and could run through until 24 December 2024. The works will impact the carriageway only.

The information for these works was last updated by Southern Gas Networks on 4 December 2024 at 08:10.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Eastern Esplanade, Margate

Works Details

WORKS IN PROGRESS
Major
Southern Gas Networks logo
These works are handled by:
Southern Gas Networks
Kent County Council logo
Local Authority:
Kent County Council
Works Reference XW200W120850162-00445
Permit Number 02
Place Name Eastern Esplanade
Margate
Proposed Start 3 Dec 2024
Proposed End 24 Dec 2024
Actual Start 3 Dec 2024 16:35
Actual End
Traffic Management Multi-way signals
Impact Carriageway
Coordinates
Lat, Lon
51.390844
1.399702
Last Updated 4 Dec 2024 08:10
Contact Details for Activity XW200W120850162-00445 (Eastern Esplanade, Margate)

In the event that you have an issue with these works, please contact Southern Gas Networks, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, Kent County Council that authorised the works.

It would assist the organisations if you quote the work reference number of XW200W120850162-00445.

Kent County Council
Telephone03000 418 181
Works History for Activity XW200W120850162-00445 (Eastern Esplanade, Margate)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Dec 2024
10:24
Permit Submitted
3 Dec 2024
00:00
24 Dec 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Dec 2024
10:51
Permit Granted
3 Dec 2024
00:00
24 Dec 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Dec 2024
08:10
Work Started
3 Dec 2024
00:00
24 Dec 2024
00:00
3 Dec 2024
16:35
In Progress

Works Permits for Eastern Esplanade, Margate

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT08a (Traffic management request)

For the activities hereby permitted, it is a condition of this permit that works, or the relevant part of the activity, shall only take place when the following traffic management is deployed by use of x (where x determines type of control i.e. portable signals, stop/go boards etc.)

+
NCT08b (Manual control of traffic management)

For the activities hereby permitted, it is a condition of this permit that, for the traffic management deployed (state type), it is manually operated between (x hours and y hours).

+
NCT09c (Signal removal from operation when no longer required)

This condition is attached to permits in cases where temporary traffic signals are used. For the activities hereby permitted, it is a condition of this permit that activities using portable traffic signals must have the signals (whether manually operated or not) removed from use as soon as possible and no later than four hours after completion of works irrespective of day of completion.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.