ROADWORK EVENT SUMMARY
London Road, Hilsea, Portsmouth between 13 Nov and 20 Dec 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for London Road, Hilsea, Portsmouth

Southern Gas Networks are carrying out Utility repair and maintenance works on London Road, Hilsea, Portsmouth.

These works are categorised as Urgent Works with an immediate start.

A lane is closed for some or all of the period and could cause delays to journeys.

The works started on 13 November 2024 at 09:30 and could run through until 20 December 2024. The works will impact the footway, carriageway and verge.

The information for these works was last updated by Southern Gas Networks on 25 November 2024 at 15:38.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for London Road, Hilsea, Portsmouth

Works Details

WORKS IN PROGRESS
Immediate - urgent
Southern Gas Networks logo
These works are handled by:
Southern Gas Networks
Portsmouth City Council logo
Local Authority:
Portsmouth City Council
Works Reference XW100W120785576-00117
Permit Number 01
Place Name London Road
Hilsea
Portsmouth
Proposed Start 13 Nov 2024
Proposed End 20 Dec 2024
Actual Start 13 Nov 2024 09:30
Actual End
Traffic Management Lane closure
Impact Footway, Carriageway, Verge
Coordinates
Lat, Lon
50.83444
-1.071874
Last Updated 25 Nov 2024 15:38
Works History for Activity XW100W120785576-00117 (London Road, Hilsea, Portsmouth)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
13 Nov 2024
10:46
Work Started
13 Nov 2024
09:30
18 Nov 2024
00:00
13 Nov 2024
09:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
13 Nov 2024
10:52
Permit Granted
13 Nov 2024
09:30
18 Nov 2024
00:00
13 Nov 2024
09:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
14 Nov 2024
09:12
Permit Alteration Granted
13 Nov 2024
09:30
18 Nov 2024
00:00
13 Nov 2024
09:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Nov 2024
08:05
Permit Alteration Granted
13 Nov 2024
09:30
20 Dec 2024
00:00
13 Nov 2024
09:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
25 Nov 2024
15:38
Permit Alteration Granted
13 Nov 2024
09:30
20 Dec 2024
00:00
13 Nov 2024
09:30
In Progress

Works Permits for London Road, Hilsea, Portsmouth

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT04b (Storage of surplus materials/plant)

For the activities hereby permitted, it is a condition of this permit that no materials and/or plant that will not be utilised within the working day are to be stored within or outside of the defined working space from (insert date) until (insert date) due to (stipulate reason for application of condition).

+
NCT07a (Road closed to traffic)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place when [insert road name] or [insert description of the relevant section of the road] is closed to traffic.

+
NCT09a (Changes to traffic management arrangements)

For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority before these changes are made.

+
NCT10a (Employment (as agreed) of appropriate methodology)

For the activities hereby permitted, it is a condition of this permit that, for the activities on this site, as agreed, the works methodology employed will be A, B, C [describe agreed methodology] throughout the duration of the works activity.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.