ROADWORK EVENT SUMMARY
South Coast Road, Peacehaven between 18 and 27 Nov 2024

Works Description for South Coast Road, Peacehaven

Southern Gas Networks were proposing to carry out Utility repair and maintenance works on South Coast Road, Peacehaven.

These works were categorised as Emergency Works with an immediate start.

Two-way signals were planned to be in use for some or all of the period. However, the required permit was refused.

The works were originally planned to start 18 November 2024 and run through until 27 November 2024. The works were due to impact the carriageway only.

The information for these works was last updated by Southern Gas Networks on 19 November 2024 at 08:48.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for South Coast Road, Peacehaven

Works Details

PERMIT REFUSED
Immediate - emergency
Southern Gas Networks logo
These works are handled by:
Southern Gas Networks
East Sussex County Council logo
Local Authority:
East Sussex County Council
Works Reference XW061W120806984-01472
Permit Number 01
Place Name South Coast Road
Peacehaven
Proposed Start 18 Nov 2024
Proposed End 27 Nov 2024
Actual Start 18 Nov 2024 21:40
Actual End
Traffic Management Two-way signals
Impact Carriageway
Coordinates
Lat, Lon
50.792148
-0.004695
Last Updated 19 Nov 2024 08:48
Works History for Activity XW061W120806984-01472 (South Coast Road, Peacehaven)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Nov 2024
08:41
Permit Submitted
18 Nov 2024
21:40
27 Nov 2024
00:00
18 Nov 2024
21:40
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Nov 2024
08:48
Permit Refused
18 Nov 2024
21:40
27 Nov 2024
00:00
18 Nov 2024
21:40
In Progress

Works Permits for South Coast Road, Peacehaven

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT08a (Traffic management request)

For the activities hereby permitted, it is a condition of this permit that works, or the relevant part of the activity, shall only take place when the following traffic management is deployed by use of x (where x determines type of control i.e. portable signals, stop/go boards etc.)

+
NCT08b (Manual control of traffic management)

For the activities hereby permitted, it is a condition of this permit that, for the traffic management deployed (state type), it is manually operated between (x hours and y hours).

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.