ROADWORK EVENT SUMMARY
Magna Road, Poole between 6 Sep and 1 Nov 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Magna Road, Poole

Southern Gas Networks carried out Utility repair and maintenance works on Magna Road, Poole.

These works were categorised as Major.

The works were originally planned between 6 Sep 2024 and 25 Oct 2024 and were actually completed between 6 Sep 2024 (16:00) and 1 Nov 2024 (16:00). The works impacted the footway and carriageway.

The information for these works was last updated by Southern Gas Networks on 5 November 2024 at 15:33.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Magna Road, Poole

Works Details

WORKS COMPLETED
Major
Southern Gas Networks logo
These works are handled by:
Southern Gas Networks
Bournemouth, Christchurch And Poole Council logo
Local Authority:
Bournemouth, Christchurch And Poole Council
Works Reference XW014SOE14299-01018-P3
Permit Number 02
Place Name Magna Road
Poole
Proposed Start 6 Sep 2024
Proposed End 25 Oct 2024
Actual Start 6 Sep 2024 16:00
Actual End 1 Nov 2024 16:00
Traffic Management Some carriageway incursion
Impact Footway, Carriageway
Coordinates
Lat, Lon
50.771295
-1.929904
Last Updated 5 Nov 2024 15:33
Works History for Activity XW014SOE14299-01018-P3 (Magna Road, Poole)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
8 Jul 2024
15:49
Permit Submitted
9 Sep 2024
01:00
4 Oct 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
9 Jul 2024
10:42
Permit Granted
9 Sep 2024
01:00
4 Oct 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
6 Sep 2024
16:06
Permit Alteration Granted
6 Sep 2024
01:00
4 Oct 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
9 Sep 2024
14:47
Work Started
6 Sep 2024
01:00
4 Oct 2024
01:00
6 Sep 2024
17:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
30 Sep 2024
17:01
Permit Alteration Granted
6 Sep 2024
01:00
18 Oct 2024
01:00
6 Sep 2024
17:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Oct 2024
16:30
Permit Alteration Granted
6 Sep 2024
01:00
23 Oct 2024
01:00
6 Sep 2024
17:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
22 Oct 2024
16:44
Traffic Management Updated
6 Sep 2024
01:00
23 Oct 2024
01:00
6 Sep 2024
17:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
22 Oct 2024
16:58
Permit Alteration Granted
6 Sep 2024
01:00
25 Oct 2024
01:00
6 Sep 2024
17:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
5 Nov 2024
15:33
Work Stopped
6 Sep 2024
01:00
25 Oct 2024
01:00
6 Sep 2024
17:00
1 Nov 2024
16:00
Completed

Works Permits for Magna Road, Poole

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.