ROADWORK EVENT SUMMARY
Bickington Road, Bickington between 6 Jan and 14 Feb 2025

Works Description for Bickington Road, Bickington

This is a PAA (Provisional Advance Authorisation) permit that has been granted before final details of an activity have been finalised. A full permit will be required before activities can commence.


Last Mile Electricity (formerly Global Utility Connections) are proposing to carry out Utility repair and maintenance works on Bickington Road, Bickington.

These works are categorised as Major.

Two-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 6 January 2025 and could run through until 14 February 2025. The works will impact the carriageway only.

The information for these works was last updated by Last Mile Electricity (formerly Global Utility Connections) on 12 November 2024 at 11:35.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Bickington Road, Bickington

Works Details

WORKS PLANNED
Major (PAA)
These works are handled by:
Last Mile Electricity (formerly Global Utility Connections)
Devon County Council logo
Local Authority:
Devon County Council
Works Reference XV016ABS-UKP12276-2
Permit Number 02
Place Name Bickington Road
Bickington
Proposed Start 6 Jan 2025
Proposed End 14 Feb 2025
Actual Start
Actual End
Traffic Management Two-way signals
Impact Carriageway
Coordinates
Lat, Lon
51.072719
-4.104916
Last Updated 12 Nov 2024 11:35
Works History for Activity XV016ABS-UKP12276-2 (Bickington Road, Bickington)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
25 Oct 2024
11:19
Permit Submitted
6 Jan 2025
00:00
14 Feb 2025
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
12 Nov 2024
11:35
Permit Granted
6 Jan 2025
00:00
14 Feb 2025
00:00
Planned

Works Permits for Bickington Road, Bickington

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT03 (Activities ancillary to those permitted - supplementary information)

For the activities hereby permitted, it is a condition of this permit that, if there are changes to ancillary activities, either in the street to which the application relates or in an adjacent street that become known about within the duration of the permit, the authority must be notified.

+
NCT08b (Manual control of traffic management)

For the activities hereby permitted, it is a condition of this permit that, for the traffic management deployed (state type), it is manually operated between (x hours and y hours).

+
NCT09a (Changes to traffic management arrangements)

For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority before these changes are made.

+
NCT09b (Traffic management arrangements to be in place)

For the activities hereby permitted, it is a condition of this permit that the works comprised in [specified part A/B] of the activities hereby permitted shall be subject to and shall occur only when the following traffic management measures are in place [or as attached in schedule.].

+
NCT09c (Signal removal from operation when no longer required)

This condition is attached to permits in cases where temporary traffic signals are used. For the activities hereby permitted, it is a condition of this permit that activities using portable traffic signals must have the signals (whether manually operated or not) removed from use as soon as possible and no later than four hours after completion of works irrespective of day of completion.

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.