ROADWORK EVENT SUMMARY
Furness Road, London between 15 and 28 Sep 2026

Works Description for Furness Road, London

G2 Energy IDNO are carrying out New service connection on Furness Road, London.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 15 September 2026 at 10:30 and could run through until 28 September 2026. The works will impact the carriageway only.

The information for these works was last updated by G2 Energy IDNO on 15 September 2026 at 12:08.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Furness Road, London

Works Details

WORKS IN PROGRESS
G2 Energy IDNO logo
These works are handled by:
G2 Energy IDNO
London Borough Of Brent logo
Local Authority:
London Borough Of Brent
Works Reference TR040N001FURNESSRDTTRO
Permit Number 01
Place Name Furness Road
London
Proposed Start 14 Sep 2026
Proposed End 28 Sep 2026
Actual Start 15 Sep 2026 10:30
Actual End
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
51.534994
-0.237144
Last Updated 15 Sep 2026 12:08
Works History for Activity TR040N001FURNESSRDTTRO (Furness Road, London)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
6 Sep 2026
21:41
Permit Submitted
30 Nov 2026
08:00
10 Dec 2026
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Sep 2026
15:01
Permit Granted
30 Nov 2026
08:00
10 Dec 2026
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
14 Sep 2026
13:50
Permit Alteration Granted
14 Sep 2026
09:00
27 Sep 2026
19:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Sep 2026
13:08
Work Started
14 Sep 2026
09:00
28 Sep 2026
19:00
15 Sep 2026
11:30
In Progress

Works Permits for Furness Road, London

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.