ROADWORK EVENT SUMMARY
Fulwell Lane, Mixbury between 3 Jan and 4 Oct 2023

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Fulwell Lane, Mixbury

HS2 carried out Works for Rail Purposes on Fulwell Lane, Mixbury.

The works did not impact the carriageway.

The works were originally planned between 3 Jan 2023 and 29 Nov 2024 and were actually completed between 3 Jan 2023 (08:00) and 4 Oct 2023 (09:30). The works impacted the footpath only.

The information for these works was last updated by HS2 on 4 October 2023 at 08:34.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Fulwell Lane, Mixbury

Works Details

WORKS COMPLETED
HS2 (Highway)
HS2 logo
These works are handled by:
HS2
Oxfordshire County Council logo
Local Authority:
Oxfordshire County Council
Works Reference TA014-AC-OCC-EKFB-3112
Permit Number 01
Place Name Fulwell Lane
Mixbury
Proposed Start 3 Jan 2023
Proposed End 29 Nov 2024
Actual Start 3 Jan 2023 08:00
Actual End 4 Oct 2023 09:30
Traffic Management No carriageway incursion
Impact Footpath
Coordinates
Lat, Lon
51.999332
-1.101997
Last Updated 4 Oct 2023 08:34
Works History for Activity TA014-AC-OCC-EKFB-3112 (Fulwell Lane, Mixbury)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
24 Feb 2023
17:16
Permit Alteration Granted
3 Jan 2023
08:00
29 Nov 2024
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Oct 2023
09:33
Work Started
3 Jan 2023
08:00
29 Nov 2024
23:59
3 Jan 2023
08:00
4 Oct 2023
10:30
Completed
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Oct 2023
09:34
Work Stopped
3 Jan 2023
08:00
29 Nov 2024
23:59
3 Jan 2023
08:00
4 Oct 2023
10:30
Completed
Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.