ROADWORK EVENT SUMMARY
Gawcott Road, Buckingham between 6 Apr 2021 and 31 Dec 2025

Works Description for Gawcott Road, Buckingham

HS2 were proposing to carry out Works for Rail Purposes on Gawcott Road, Buckingham.

The works were not intending to impact the carriageway. However, therequired permit was refused.

The works were originally planned to start 6 April 2021 and run through until 31 December 2025. The works were due to impact the verge only.

The information for these works was last updated by HS2 on 1 April 2021 at 12:56.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Gawcott Road, Buckingham

Works Details

PERMIT REFUSED
HS2 (Highway)
HS2 logo
These works are handled by:
HS2
Buckinghamshire Council logo
Local Authority:
Buckinghamshire Council
Works Reference TA014-AC-BC-EKFB-2006
Permit Number 01
Place Name Gawcott Road
Buckingham
Proposed Start 6 Apr 2021
Proposed End 31 Dec 2025
Actual Start
Actual End
Traffic Management No carriageway incursion
Impact Verge
Coordinates
Lat, Lon
51.992005
-0.996647
Last Updated 1 Apr 2021 12:56
Works History for Activity TA014-AC-BC-EKFB-2006 (Gawcott Road, Buckingham)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
31 Mar 2021
15:32
Permit Submitted
6 Apr 2021
08:00
31 Dec 2025
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
1 Apr 2021
13:56
Permit Refused
6 Apr 2021
08:00
31 Dec 2025
18:00
Planned
Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.