ROADWORK EVENT SUMMARY
Barton Hartshorn Footpath 2, Barton Hartshorn between 1 Feb 2022 and 3 Oct 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Barton Hartshorn Footpath 2, Barton Hartshorn

HS2 carried out Works for Rail Purposes on Barton Hartshorn Footpath 2, Barton Hartshorn.

The works did not impact the carriageway.

The works were originally planned between 1 Feb 2022 and 30 Mar 2025 and were actually completed between 1 Feb 2022 (09:00) and 3 Oct 2024 (13:00). The works impacted the footpath only.

The information for these works was last updated by HS2 on 21 October 2024 at 12:49.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Barton Hartshorn Footpath 2, Barton Hartshorn

Works Details

WORKS COMPLETED
HS2 (Highway)
HS2 logo
These works are handled by:
HS2
Buckinghamshire Council logo
Local Authority:
Buckinghamshire Council
Works Reference TA014-AC-BC-EKFB-1450
Permit Number 02
Place Name Barton Hartshorn Footpath 2
Barton Hartshorn
Proposed Start 1 Feb 2022
Proposed End 30 Mar 2025
Actual Start 1 Feb 2022 09:00
Actual End 3 Oct 2024 13:00
Traffic Management No carriageway incursion
Impact Footpath
Coordinates
Lat, Lon
51.971749
-1.083983
Last Updated 21 Oct 2024 12:49
Works History for Activity TA014-AC-BC-EKFB-1450 (Barton Hartshorn Footpath 2, Barton Hartshorn)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
26 Jan 2022
11:55
Permit Submitted
1 Feb 2022
09:00
30 Mar 2025
17:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Oct 2024
13:48
Work Started
1 Feb 2022
09:00
30 Mar 2025
18:00
1 Feb 2022
09:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Oct 2024
13:49
Work Stopped
1 Feb 2022
09:00
30 Mar 2025
18:00
1 Feb 2022
09:00
3 Oct 2024
14:00
Completed
Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.