ROADWORK EVENT SUMMARY
Shire Lane, Chalfont St Peter between 6 Jul 2023 and 30 Dec 2025

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Shire Lane, Chalfont St Peter

HS2 are carrying out Works for road purposes on Shire Lane, Chalfont St Peter.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 6 July 2023 at 23:01 and could run through until 30 December 2025. The works will impact the footway, carriageway, verge, cycleway and footpath.

The information for these works was last updated by HS2 on 9 January 2024 at 13:02.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Shire Lane, Chalfont St Peter

Works Details

WORKS IN PROGRESS
HS2 (Highway)
HS2 logo
These works are handled by:
HS2
Buckinghamshire Council logo
Local Authority:
Buckinghamshire Council
Works Reference TA01318853405
Permit Number 01
Place Name Shire Lane
Chalfont St Peter
Proposed Start 6 Jul 2023
Proposed End 30 Dec 2025
Actual Start 6 Jul 2023 23:01
Actual End
Traffic Management Road closure
Impact Footway, Carriageway, Verge, Cycleway, Footpath
Coordinates
Lat, Lon
51.614412
-0.527938
Last Updated 9 Jan 2024 13:02
Works History for Activity TA01318853405 (Shire Lane, Chalfont St Peter)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
7 Jul 2023
12:56
Permit Submitted
7 Jul 2023
00:01
30 Dec 2025
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
9 Jan 2024
13:02
Work Started
7 Jul 2023
00:01
30 Dec 2025
23:59
7 Jul 2023
00:01
In Progress
Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.