Works Description for West Gate, Ealing

HS2 are carrying out Utility asset works on West Gate, Ealing.

These works are categorised as Major.

Multi-way signals are to be in place for some or all of the period and could cause delays to journeys.

The works started on 25 March 2024 at 00:01 and could run through until 16 June 2024. The works will impact the footway, carriageway and parking place.

The information for these works was last updated by HS2 on 18 April 2024 at 16:03.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for West Gate, Ealing

Works Details

WORKS IN PROGRESS
Major
HS2 logo
These works are handled by:
HS2
London Borough Of Ealing logo
Local Authority:
London Borough Of Ealing
Works Reference TA012THW-LBE-SCS-4786
Permit Number 02
Place Name West Gate
Ealing
Proposed Start 25 Mar 2024
Proposed End 16 Jun 2024
Actual Start 25 Mar 2024 00:01
Actual End
Traffic Management Multi-way signals
Impact Footway, Carriageway, Parking place
Coordinates
Lat, Lon
51.531913
-0.295318
Last Updated 18 Apr 2024 16:03
Works History for Activity TA012THW-LBE-SCS-4786 (West Gate, Ealing)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
13 Feb 2024
14:03
Permit Submitted
14 Feb 2024
08:00
12 Jul 2024
19:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
18 Apr 2024
17:02
Permit Alteration Granted
25 Mar 2024
00:01
17 Jun 2024
00:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
18 Apr 2024
17:03
Work Started
25 Mar 2024
00:01
17 Jun 2024
00:59
25 Mar 2024
00:01
In Progress
Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.