ROADWORK EVENT SUMMARY
Footpath From 5-6 Brunswick Road To Opposite 1a Lynwood Road, Ealing between 2 Apr and 4 Dec 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Footpath From 5-6 Brunswick Road To Opposite 1a Lynwood Road, Ealing

HS2 are carrying out Utility asset works on Footpath From 5-6 Brunswick Road To Opposite 1a Lynwood Road, Ealing.

These works are categorised as Major.

The works should not impact the carriageway.

The works started on 2 April 2024 at 07:00 and could run through until 4 December 2024. The works will impact the footway only.

The information for these works was last updated by HS2 on 20 November 2024 at 14:54.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Footpath From 5-6 Brunswick Road To Opposite 1a Lynwood Road, Ealing

Works Details

WORKS IN PROGRESS
Major
HS2 logo
These works are handled by:
HS2
London Borough Of Ealing logo
Local Authority:
London Borough Of Ealing
Works Reference TA012THW-LBE-SCS-4671
Permit Number 02
Place Name Footpath From 5-6 Brunswick Road To Opposite 1a Lynwood Road
Ealing
Proposed Start 2 Apr 2024
Proposed End 4 Dec 2024
Actual Start 2 Apr 2024 07:00
Actual End
Traffic Management No carriageway incursion
Impact Footway
Coordinates
Lat, Lon
51.530212
-0.302024
Last Updated 20 Nov 2024 14:54
Works History for Activity TA012THW-LBE-SCS-4671 (Footpath From 5-6 Brunswick Road To Opposite 1a Lynwood Road, Ealing)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
6 Dec 2023
11:42
Permit Submitted
18 Mar 2024
07:00
7 Jun 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
18 Dec 2023
10:06
Permit Granted
18 Mar 2024
07:00
7 Jun 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
7 Feb 2024
15:08
Permit Alteration Granted
18 Mar 2024
07:00
7 Jun 2024
19:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
8 Mar 2024
13:47
Permit Alteration Granted
2 Apr 2024
08:00
29 May 2024
19:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Apr 2024
17:30
Work Started
2 Apr 2024
08:00
29 May 2024
19:00
2 Apr 2024
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
30 May 2024
14:28
Permit Alteration Granted
2 Apr 2024
08:00
19 Jul 2024
19:00
2 Apr 2024
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
28 Jun 2024
15:25
Permit Alteration Granted
2 Apr 2024
08:00
13 Aug 2024
19:00
2 Apr 2024
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Jul 2024
12:08
Permit Alteration Granted
2 Apr 2024
08:00
13 Sep 2024
19:00
2 Apr 2024
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
14 Aug 2024
17:33
Permit Alteration Granted
2 Apr 2024
08:00
15 Oct 2024
19:00
2 Apr 2024
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
28 Aug 2024
12:24
Permit Alteration Granted
2 Apr 2024
08:00
23 Oct 2024
19:00
2 Apr 2024
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
5 Sep 2024
15:42
Permit Alteration Granted
2 Apr 2024
08:00
28 Oct 2024
18:00
2 Apr 2024
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
25 Sep 2024
16:30
Permit Alteration Granted
2 Apr 2024
08:00
30 Oct 2024
18:00
2 Apr 2024
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
30 Sep 2024
12:30
Permit Alteration Granted
2 Apr 2024
08:00
5 Nov 2024
18:00
2 Apr 2024
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
8 Oct 2024
14:07
Permit Alteration Granted
2 Apr 2024
08:00
11 Nov 2024
18:00
2 Apr 2024
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 Oct 2024
13:01
Permit Alteration Granted
2 Apr 2024
08:00
11 Nov 2024
18:00
2 Apr 2024
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
7 Nov 2024
14:44
Permit Alteration Granted
2 Apr 2024
08:00
13 Nov 2024
18:00
2 Apr 2024
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Nov 2024
16:12
Permit Alteration Granted
2 Apr 2024
08:00
4 Dec 2024
18:00
2 Apr 2024
08:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Nov 2024
14:54
Permit Alteration Granted
2 Apr 2024
08:00
4 Dec 2024
18:00
2 Apr 2024
08:00
In Progress

Works Permits for Footpath From 5-6 Brunswick Road To Opposite 1a Lynwood Road, Ealing

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.