ROADWORK EVENT SUMMARY
Victoria Road, Park Royal between 21 Jun 2023 and 31 Dec 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Victoria Road, Park Royal

HS2 are carrying out Works for Rail Purposes on Victoria Road, Park Royal.

The works should not impact the carriageway.

The works started on 21 June 2023 at 17:00 and could run through until 31 December 2024. The works will impact the footway only.

The information for these works was last updated by HS2 on 23 November 2023 at 11:53.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Victoria Road, Park Royal

Works Details

WORKS IN PROGRESS
HS2 (Highway)
HS2 logo
These works are handled by:
HS2
London Borough Of Ealing logo
Local Authority:
London Borough Of Ealing
Works Reference TA012THW-LBE-SCS-4615
Permit Number 01
Place Name Victoria Road
Park Royal
Proposed Start 23 Jun 2023
Proposed End 31 Dec 2024
Actual Start 21 Jun 2023 17:00
Actual End
Traffic Management No carriageway incursion
Impact Footway
Coordinates
Lat, Lon
51.524389
-0.257129
Last Updated 23 Nov 2023 11:53
Works History for Activity TA012THW-LBE-SCS-4615 (Victoria Road, Park Royal)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Jun 2023
09:54
Permit Submitted
23 Jun 2023
07:00
23 Jun 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
22 Jun 2023
09:09
Permit Alteration Granted
23 Jun 2023
07:00
23 Jun 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
22 Jun 2023
12:51
Work Started
23 Jun 2023
07:00
23 Jun 2024
18:00
21 Jun 2023
18:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 Nov 2023
11:53
Permit Alteration Granted
23 Jun 2023
07:00
31 Dec 2024
18:00
21 Jun 2023
18:00
In Progress
Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.