ROADWORK EVENT SUMMARY
Temple Way, Redcliff, Bristol between 1 Dec 2025 and 30 Nov 2026

Works Description for Temple Way, Redcliff, Bristol

Bristol City Council are carrying out Highway improvement works on Temple Way, Redcliff, Bristol.

These works are categorised as Major.

The road is closed for some or all of the period and could cause delays to journeys.

The works started on 1 December 2025 at 11:00 and could run through until 30 November 2026. The works will impact the footway, carriageway, verge and cycleway.

The information for these works was last updated by Bristol City Council on 17 July 2026 at 13:31.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Temple Way, Redcliff, Bristol

Works Details

WORKS IN PROGRESS
Major
Bristol City Council logo
These works are handled by:
Bristol City Council
Bristol City Council logo
Local Authority:
Bristol City Council
Works Reference QF00420725159
Permit Number 02
Place Name Temple Way
Redcliff
Bristol
Proposed Start 1 Dec 2025
Proposed End 30 Nov 2026
Actual Start 1 Dec 2025 11:00
Actual End
Traffic Management Road closure
Impact Footway, Carriageway, Verge, Cycleway
Coordinates
Lat, Lon
51.45022
-2.584904
Last Updated 17 Jul 2026 13:31
Contact Details for Activity QF00420725159 (Temple Way, Redcliff, Bristol)

In the event that you have an issue with these works, please contact Bristol City Council, the works operator.

It would assist the organisation if you quote the work reference number of QF00420725159.

Bristol City Council
Telephone0117 922 2100
Email[email protected]
Works History for Activity QF00420725159 (Temple Way, Redcliff, Bristol)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
6 Nov 2025
11:41
Permit Submitted
1 Dec 2025
00:00
30 Nov 2026
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
28 Nov 2025
14:45
Permit Alteration Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
2 Dec 2025
12:07
Permit Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
2 Dec 2025
12:08
Permit Alteration Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Dec 2025
14:20
Work Started
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Dec 2025
14:21
Traffic Management Updated
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
16 Jan 2026
18:06
Traffic Management Updated
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Jan 2026
16:49
Traffic Management Updated
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Jan 2026
09:05
Permit Alteration Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
2 Feb 2026
09:56
Permit Alteration Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Mar 2026
09:33
Permit Alteration Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
16 Mar 2026
11:37
Permit Alteration Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
7 Apr 2026
11:09
Permit Alteration Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Apr 2026
16:19
Permit Alteration Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 May 2026
13:58
Permit Alteration Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
18 May 2026
09:55
Permit Alteration Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Jun 2026
13:36
Permit Alteration Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
2 Jul 2026
13:40
Permit Alteration Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Jul 2026
20:38
Permit Alteration Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
9 Jul 2026
11:40
Permit Alteration Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Jul 2026
14:31
Permit Alteration Granted
1 Dec 2025
00:00
30 Nov 2026
00:00
1 Dec 2025
11:00
In Progress

Works Permits for Temple Way, Redcliff, Bristol

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT05a (Width and/or length of road space that can be occupied)

For the activities hereby permitted, it is a condition of this permit that the activity shall occur only within the area [insert description of area or provide traffic management plan reference] including the relevant and required signing, lighting and guarding excluding advance warning, advance communication and diversionary signs.

+
NCT09b (Traffic management arrangements to be in place)

For the activities hereby permitted, it is a condition of this permit that the works comprised in [specified part A/B] of the activities hereby permitted shall be subject to and shall occur only when the following traffic management measures are in place [or as attached in schedule.].

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.