ROADWORK EVENT SUMMARY
Bridge Road, Charmouth between 16 Sep and 25 Oct 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Bridge Road, Charmouth

This is a PAA (Provisional Advance Authorisation) permit that has been granted before final details of an activity have been finalised. A full permit will be required before activities can commence.


Wessex Water are proposing to carry out Utility repair and maintenance works on Bridge Road, Charmouth.

These works are categorised as Major.

Multi-way signals will be in place for some or all of the period and could cause delays to journeys.

The works will start on or after 16 September 2024 and could run through until 25 October 2024. The works will impact the footway and carriageway.

*These works were due to commence more than a month ago. It is possible that the works may still commence but it should also be considered that the works may have been cancelled and the roadworks data has not been updated to reflect this.

The information for these works was last updated by Wessex Water on 13 August 2024 at 15:55.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Bridge Road, Charmouth

Works Details

WORKS PLANNED
Major (PAA)
Wessex Water logo
These works are handled by:
Wessex Water
Dorset Council logo
Local Authority:
Dorset Council
Works Reference PG201BS0127_DOR_01
Permit Number 03
Place Name Bridge Road
Charmouth
Proposed Start 16 Sep 2024
Proposed End 25 Oct 2024
Actual Start
Actual End
Traffic Management Multi-way signals
Impact Footway, Carriageway
Coordinates
Lat, Lon
50.738491
-2.897322
Last Updated 13 Aug 2024 15:55
Contact Details for Activity PG201BS0127_DOR_01 (Bridge Road, Charmouth)

In the event that you have an issue with these works, please contact Wessex Water, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, Dorset Council that authorised the works.

It would assist the organisations if you quote the work reference number of PG201BS0127_DOR_01.

Wessex Water
Telephone0345 600 4600
Dorset Council
Telephone01305 221020
Works History for Activity PG201BS0127_DOR_01 (Bridge Road, Charmouth)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
16 Jul 2024
13:47
Permit Submitted
16 Sep 2024
01:00
25 Oct 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
13 Aug 2024
16:55
Permit Granted
16 Sep 2024
01:00
25 Oct 2024
01:00
Planned

Works Permits for Bridge Road, Charmouth

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT03 (Activities ancillary to those permitted - supplementary information)

For the activities hereby permitted, it is a condition of this permit that, if there are changes to ancillary activities, either in the street to which the application relates or in an adjacent street that become known about within the duration of the permit, the authority must be notified.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.