ROADWORK EVENT SUMMARY
Tottenham Court Road, Bloomsbury, London between 19 and 21 Nov 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Tottenham Court Road, Bloomsbury, London

This is a PAA (Provisional Advance Authorisation) permit that has been granted before final details of an activity have been finalised. A full permit will be required before activities can commence.


Virgin Media were proposing to carry out Utility asset works on Tottenham Court Road, Bloomsbury, London.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the works were cancelled.

The works were originally planned to start 19 November 2024 and run through until 21 November 2024. The works were due to impact the carriageway only.

The information for these works was last updated by Virgin Media on 4 September 2024 at 15:53.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Tottenham Court Road, Bloomsbury, London

Works Details

WORKS CANCELLED
Major (PAA)
Virgin Media logo
These works are handled by:
Virgin Media
City Of Westminster logo
Local Authority:
City Of Westminster
Works Reference NK102VM_CIP_436247
Permit Number 01
Place Name Tottenham Court Road
Bloomsbury
London
Proposed Start 19 Nov 2024
Proposed End 21 Nov 2024
Actual Start
Actual End
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
51.517116
-0.130875
Last Updated 4 Sep 2024 15:53
Contact Details for Activity NK102VM_CIP_436247 (Tottenham Court Road, Bloomsbury, London)

In the event that you have an issue with these works, please contact Virgin Media, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, City Of Westminster that authorised the works.

It would assist the organisations if you quote the work reference number of NK102VM_CIP_436247.

Virgin Media
Telephone0800 183 0123
Works History for Activity NK102VM_CIP_436247 (Tottenham Court Road, Bloomsbury, London)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
14 Aug 2024
12:14
Permit Submitted
19 Nov 2024
19:00
21 Nov 2024
23:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Sep 2024
16:53
Permit Cancelled
19 Nov 2024
19:00
21 Nov 2024
23:59
Cancelled

Works Permits for Tottenham Court Road, Bloomsbury, London

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT03 (Activities ancillary to those permitted - supplementary information)

For the activities hereby permitted, it is a condition of this permit that, if there are changes to ancillary activities, either in the street to which the application relates or in an adjacent street that become known about within the duration of the permit, the authority must be notified.

+
NCT07a (Road closed to traffic)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place when [insert road name] or [insert description of the relevant section of the road] is closed to traffic.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.