Works Description for Lynton Road, Cheney Manor Industrial Estate, Swindon

Thames Water are carrying out Utility repair and maintenance works on Lynton Road, Cheney Manor Industrial Estate, Swindon.

These works are categorised as Urgent Works with an immediate start.

There are no traffic signals or road closures necessary for these works and traffic will operate on a give-and-take basis.

The works started on 18 November 2024 at 18:17 and could run through until 24 November 2024. The works will impact the carriageway only.

The information for these works was last updated by Thames Water on 22 November 2024 at 13:59.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Lynton Road, Cheney Manor Industrial Estate, Swindon

Works Details

WORKS IN PROGRESS
Immediate - urgent
Thames Water logo
These works are handled by:
Thames Water
Swindon Borough Council logo
Local Authority:
Swindon Borough Council
Works Reference MU70500701969-001
Permit Number 01
Place Name Lynton Road
Cheney Manor Industrial Estate
Swindon
Proposed Start 18 Nov 2024
Proposed End 24 Nov 2024
Actual Start 18 Nov 2024 18:17
Actual End
Traffic Management Give and take
Impact Carriageway
Coordinates
Lat, Lon
51.576841
-1.807852
Last Updated 22 Nov 2024 13:59
Contact Details for Activity MU70500701969-001 (Lynton Road, Cheney Manor Industrial Estate, Swindon)

In the event that you have an issue with these works, please contact Thames Water, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, Swindon Borough Council that authorised the works.

It would assist the organisations if you quote the work reference number of MU70500701969-001.

Thames Water
Telephone0845 920 0800
Works History for Activity MU70500701969-001 (Lynton Road, Cheney Manor Industrial Estate, Swindon)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
18 Nov 2024
18:17
Work Started
18 Nov 2024
18:17
20 Nov 2024
18:17
18 Nov 2024
18:17
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Nov 2024
08:07
Permit Granted
18 Nov 2024
18:17
20 Nov 2024
18:17
18 Nov 2024
18:17
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Nov 2024
08:20
Permit Alteration Granted
18 Nov 2024
18:17
20 Nov 2024
18:17
18 Nov 2024
18:17
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
19 Nov 2024
15:27
Permit Alteration Granted
18 Nov 2024
18:17
22 Nov 2024
23:59
18 Nov 2024
18:17
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
22 Nov 2024
13:59
Permit Alteration Granted
18 Nov 2024
18:17
24 Nov 2024
23:59
18 Nov 2024
18:17
In Progress

Works Permits for Lynton Road, Cheney Manor Industrial Estate, Swindon

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT04a (Removal of surplus materials/plant)

For the activities hereby permitted, it is a condition of this permit that all remaining excavated or stored backfill materials and/or any unemployed plant must be removed from the public highway within (x hours e.g. 24) or by the stipulated time (e.g. at the end of the working day or prior to the site being un-occupied) due to (stipulate reason for application of condition).

+
NCT04b (Storage of surplus materials/plant)

For the activities hereby permitted, it is a condition of this permit that no materials and/or plant that will not be utilised within the working day are to be stored within or outside of the defined working space from (insert date) until (insert date) due to (stipulate reason for application of condition).

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.