ROADWORK EVENT SUMMARY
The Street, Frensham, Farnham between 27 Jan and 7 Feb 2025

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for The Street, Frensham, Farnham

This is a PAA (Provisional Advance Authorisation) permit that has been granted before final details of an activity have been finalised. A full permit will be required before activities can commence.


Thames Water were proposing to carry out Utility repair and maintenance works on The Street, Frensham, Farnham.

These works were categorised as Major.

The road was planned to be closed for some or all of the period. However, the required permit was refused.

The works were originally planned to start 27 January 2025 and run through until 7 February 2025. The works were due to impact the carriageway only.

The information for these works was last updated by Thames Water on 26 October 2024 at 09:12.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for The Street, Frensham, Farnham

Works Details

PERMIT REFUSED
Major (PAA)
Thames Water logo
These works are handled by:
Thames Water
Surrey County Council logo
Local Authority:
Surrey County Council
Works Reference MU113SA-1487079
Permit Number 01
Place Name The Street
Frensham
Farnham
Proposed Start 27 Jan 2025
Proposed End 7 Feb 2025
Actual Start
Actual End
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
51.16711
-0.789768
Last Updated 26 Oct 2024 09:12
Contact Details for Activity MU113SA-1487079 (The Street, Frensham, Farnham)

In the event that you have an issue with these works, please contact Thames Water, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, Surrey County Council that authorised the works.

It would assist the organisations if you quote the work reference number of MU113SA-1487079.

Thames Water
Telephone0845 920 0800
Works History for Activity MU113SA-1487079 (The Street, Frensham, Farnham)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
25 Oct 2024
10:21
Permit Submitted
27 Jan 2025
00:00
7 Feb 2025
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
26 Oct 2024
10:12
Permit Refused
27 Jan 2025
00:00
7 Feb 2025
00:00
Planned

Works Permits for The Street, Frensham, Farnham

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02b (Working hours)

For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).

+
NCT04b (Storage of surplus materials/plant)

For the activities hereby permitted, it is a condition of this permit that no materials and/or plant that will not be utilised within the working day are to be stored within or outside of the defined working space from (insert date) until (insert date) due to (stipulate reason for application of condition).

+
NCT07a (Road closed to traffic)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place when [insert road name] or [insert description of the relevant section of the road] is closed to traffic.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.