ROADWORK EVENT SUMMARY
Houndsditch, London between 20 and 23 Nov 2024

Works Description for Houndsditch, London

Thames Water carried out New service connection on Houndsditch, London.

The works were originally planned between 20 Nov 2024 and 25 Nov 2024 and were actually completed between 20 Nov 2024 (10:17) and 23 Nov 2024 (13:18). The works impacted the footway and carriageway.

The information for these works was last updated by Thames Water on 23 November 2024 at 13:28.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Houndsditch, London

Works Details

WORKS COMPLETED
Thames Water logo
These works are handled by:
Thames Water
City Of London Corporation logo
Local Authority:
City Of London Corporation
Works Reference MU091NLS00081317810-0045
Permit Number 01
Place Name Houndsditch
London
Proposed Start 20 Nov 2024
Proposed End 25 Nov 2024
Actual Start 20 Nov 2024 10:17
Actual End 23 Nov 2024 13:18
Traffic Management Some carriageway incursion
Impact Footway, Carriageway
Coordinates
Lat, Lon
51.516154
-0.079884
Last Updated 23 Nov 2024 13:28
Contact Details for Activity MU091NLS00081317810-0045 (Houndsditch, London)

In the event that you have an issue with these works, please contact Thames Water, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, City Of London Corporation that authorised the works.

It would assist the organisations if you quote the work reference number of MU091NLS00081317810-0045.

Thames Water
Telephone0845 920 0800
Works History for Activity MU091NLS00081317810-0045 (Houndsditch, London)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
24 Oct 2024
15:40
Permit Submitted
20 Nov 2024
00:00
25 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
30 Oct 2024
08:14
Permit Granted
20 Nov 2024
00:00
25 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Nov 2024
10:22
Work Started
20 Nov 2024
00:00
25 Nov 2024
00:00
20 Nov 2024
10:17
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 Nov 2024
13:28
Work Stopped
20 Nov 2024
00:00
25 Nov 2024
00:00
20 Nov 2024
10:17
23 Nov 2024
13:18
Completed

Works Permits for Houndsditch, London

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT05a (Width and/or length of road space that can be occupied)

For the activities hereby permitted, it is a condition of this permit that the activity shall occur only within the area [insert description of area or provide traffic management plan reference] including the relevant and required signing, lighting and guarding excluding advance warning, advance communication and diversionary signs.

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT09b (Traffic management arrangements to be in place)

For the activities hereby permitted, it is a condition of this permit that the works comprised in [specified part A/B] of the activities hereby permitted shall be subject to and shall occur only when the following traffic management measures are in place [or as attached in schedule.].

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.