Works Description for Atlas Road, New Southgate, London
Thames Water are carrying out Utility asset works on Atlas Road, New Southgate, London.
These works are categorised as Major.
A lane is closed for some or all of the period and could cause delays to journeys.
The works started on 20 October 2023 at 10:20 and could run through until 23 March 2025. The works will impact the footway, carriageway, verge and cycleway.
The information for these works was last updated by Thames Water on 2 July 2024 at 08:13.
Works Map for Atlas Road, New Southgate, London
Works Details
Thames Water
London Borough Of Barnet
Works Reference | MU056TWG0004ATLAS |
Permit Number | 02 |
Place Name |
Atlas Road New Southgate London |
Proposed Start | 17 Oct 2023 |
Proposed End | 23 Mar 2025 |
Actual Start | 20 Oct 2023 10:20 |
Actual End |
Traffic Management | Lane closure |
Impact | Footway, Carriageway, Verge, Cycleway |
Coordinates Lat, Lon |
51.609248 -0.143809 |
Last Updated | 2 Jul 2024 08:13 |
In the event that you have an issue with these works, please contact Thames Water, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.
Should the issue remain, you may also contact the local authority, London Borough Of Barnet that authorised the works.
It would assist the organisations if you quote the work reference number of MU056TWG0004ATLAS.
Telephone | 0845 920 0800 |
Works Permits for Atlas Road, New Southgate, London
For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.
Applies to all permits.
For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.
Applies to all permits.
For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.
For the activities hereby permitted, it is a condition of this permit that, as agreed, the following [extended] working hours will apply at this site from [start time] until [end time] on weekdays and [start time] and [end time] on (Saturday/Sunday/Bank Holiday).
For the activities hereby permitted, it is a condition of this permit that no materials and/or plant that will not be utilised within the working day are to be stored within or outside of the defined working space from (insert date) until (insert date) due to (stipulate reason for application of condition).
For the activities hereby permitted, it is a condition of this permit that the activity shall occur only within the area [insert description of area or provide traffic management plan reference] including the relevant and required signing, lighting and guarding excluding advance warning, advance communication and diversionary signs.
For the activities hereby permitted, it is a condition of this permit that works, or the relevant part of the activity, shall only take place when the following traffic management is deployed by use of x (where x determines type of control i.e. portable signals, stop/go boards etc.)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority before these changes are made.
For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.
Applies to all permits.
For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.
Proposed Work Dates
Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.
Problems with roadworks?
On rare occasions, issues may occur during or after the completion of roadworks, such as:
- Poor reinstatement of the footpath or the carriageway.
- Rubbish and mess remaining after the works have completed.
- Traffic management issues during the works.
- Equipment left behind after the works have completed.
- Any other issues or disruption that the works may be causing.
In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.
In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.
Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.
Contains public sector information licensed under the Open Government Licence v3.0.