ROADWORK EVENT SUMMARY
Welsford Street, London between 19 Jul 2023 and 27 Sep 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Welsford Street, London

Thames Water carried out roadworks on Welsford Street, London.

These works were categorised as Major.

The road was closed for some or all of the period.

The works were originally planned between 17 Jul 2023 and 23 Apr 2025 and were actually completed between 19 Jul 2023 (15:30) and 27 Sep 2024 (15:00). The works impacted the carriageway only.

The information for these works was last updated by Thames Water on 27 September 2024 at 15:21.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Welsford Street, London

Works Details

WORKS COMPLETED
Major
Thames Water logo
These works are handled by:
Thames Water
London Borough Of Southwark logo
Local Authority:
London Borough Of Southwark
Works Reference MU054BER-COMP-01-01
Permit Number 02
Place Name Welsford Street
London
Proposed Start 17 Jul 2023
Proposed End 23 Apr 2025
Actual Start 19 Jul 2023 15:30
Actual End 27 Sep 2024 15:00
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
51.489217
-0.069468
Last Updated 27 Sep 2024 15:21
Contact Details for Activity MU054BER-COMP-01-01 (Welsford Street, London)

In the event that you have an issue with these works, please contact Thames Water, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, London Borough Of Southwark that authorised the works.

It would assist the organisations if you quote the work reference number of MU054BER-COMP-01-01.

Thames Water
Telephone0845 920 0800
Works History for Activity MU054BER-COMP-01-01 (Welsford Street, London)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Jul 2023
08:25
Permit Submitted
17 Jul 2023
08:00
17 Apr 2025
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Jul 2023
08:39
Permit Granted
17 Jul 2023
08:00
17 Apr 2025
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Jul 2023
16:01
Work Started
17 Jul 2023
08:00
23 Apr 2025
18:00
19 Jul 2023
15:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Jul 2024
10:40
Work Stopped
17 Jul 2023
09:00
23 Apr 2025
19:00
19 Jul 2023
16:30
11 Jul 2024
11:35
Completed
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
8 Aug 2024
15:37
Work Stopped (Reverted)
17 Jul 2023
09:00
23 Apr 2025
19:00
19 Jul 2023
16:30
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
27 Sep 2024
16:21
Work Stopped
17 Jul 2023
09:00
23 Apr 2025
19:00
19 Jul 2023
16:30
27 Sep 2024
16:00
Completed

Works Permits for Welsford Street, London

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.