ROADWORK EVENT SUMMARY
Horsham Road, South Holmwood, Dorking between 4 and 21 Nov 2024

Works Description for Horsham Road, South Holmwood, Dorking

Surrey County Council carried out Highway repair and maintenance works on Horsham Road, South Holmwood, Dorking.

These works were categorised as Major.

A lane was closed for some or all of the period.

The works were originally planned between 4 Nov 2024 and 21 Nov 2024 and were actually completed between 4 Nov 2024 (10:00) and 21 Nov 2024 (14:35). The works impacted the verge only.

The information for these works was last updated by Surrey County Council on 21 November 2024 at 15:03.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Horsham Road, South Holmwood, Dorking

Works Details

WORKS COMPLETED
Major
Surrey County Council logo
These works are handled by:
Surrey County Council
Surrey County Council logo
Local Authority:
Surrey County Council
Works Reference MA900MPW-564929-A
Permit Number 03
Place Name Horsham Road
South Holmwood
Dorking
Proposed Start 4 Nov 2024
Proposed End 21 Nov 2024
Actual Start 4 Nov 2024 10:00
Actual End 21 Nov 2024 14:35
Traffic Management Lane closure
Impact Verge
Coordinates
Lat, Lon
51.195555
-0.326651
Last Updated 21 Nov 2024 15:03
Contact Details for Activity MA900MPW-564929-A (Horsham Road, South Holmwood, Dorking)

In the event that you have an issue with these works, please contact Surrey County Council, the works operator.

It would assist the organisation if you quote the work reference number of MA900MPW-564929-A.

Works History for Activity MA900MPW-564929-A (Horsham Road, South Holmwood, Dorking)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 May 2024
11:13
Permit Submitted
4 Oct 2024
01:00
21 Oct 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 May 2024
11:48
Permit Granted
4 Oct 2024
01:00
21 Oct 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Oct 2024
11:13
Work Started
4 Oct 2024
01:00
21 Oct 2024
01:00
4 Oct 2024
11:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
10 Oct 2024
08:48
Work Started (Reverted)
4 Oct 2024
01:00
21 Oct 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
10 Oct 2024
10:00
Permit Alteration Granted
4 Nov 2024
00:00
21 Nov 2024
00:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Nov 2024
10:06
Work Started
4 Nov 2024
00:00
21 Nov 2024
00:00
4 Nov 2024
10:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Nov 2024
15:03
Work Stopped
4 Nov 2024
00:00
21 Nov 2024
00:00
4 Nov 2024
10:00
21 Nov 2024
14:35
Completed

Works Permits for Horsham Road, South Holmwood, Dorking

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.