ROADWORK EVENT SUMMARY
Pound Lane, Windlesham between 5 and 17 Apr 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Pound Lane, Windlesham

Surrey County Council carried out Highway repair and maintenance works on Pound Lane, Windlesham.

These works were categorised as Major.

The road was closed for some or all of the period.

The works were originally planned between 2 Apr 2024 and 16 Apr 2024 and were actually completed between 5 Apr 2024 (19:00) and 17 Apr 2024 (05:00). The works impacted the carriageway only.

The information for these works was last updated by Surrey County Council on 17 April 2024 at 06:59.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Pound Lane, Windlesham

Works Details

WORKS COMPLETED
Major
Surrey County Council logo
These works are handled by:
Surrey County Council
Surrey County Council logo
Local Authority:
Surrey County Council
Works Reference MA900MM24-25-S58-047-D
Permit Number 04
Place Name Pound Lane
Windlesham
Proposed Start 2 Apr 2024
Proposed End 16 Apr 2024
Actual Start 5 Apr 2024 19:00
Actual End 17 Apr 2024 05:00
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
51.366464
-0.657946
Last Updated 17 Apr 2024 06:59
Contact Details for Activity MA900MM24-25-S58-047-D (Pound Lane, Windlesham)

In the event that you have an issue with these works, please contact Surrey County Council, the works operator.

It would assist the organisation if you quote the work reference number of MA900MM24-25-S58-047-D.

Works History for Activity MA900MM24-25-S58-047-D (Pound Lane, Windlesham)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Mar 2024
10:57
Permit Submitted
2 Apr 2024
21:00
12 Apr 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Mar 2024
07:27
Permit Granted
2 Apr 2024
21:00
12 Apr 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
8 Apr 2024
09:55
Work Started
2 Apr 2024
21:00
17 Apr 2024
01:00
5 Apr 2024
21:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Apr 2024
07:59
Work Stopped
2 Apr 2024
20:00
17 Apr 2024
00:00
5 Apr 2024
20:00
17 Apr 2024
06:00
Completed

Works Permits for Pound Lane, Windlesham

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.