ROADWORK EVENT SUMMARY
Hyde Lane, Kinver between 7 and 10 Oct 2024

Works Description for Hyde Lane, Kinver

Staffordshire County Council carried out Highway improvement works on Hyde Lane, Kinver.

These works were categorised as Major.

The road was closed for some or all of the period.

The works were originally planned between 7 Oct 2024 and 10 Oct 2024 and were actually completed between 7 Oct 2024 (09:20) and 10 Oct 2024 (16:00). The works impacted the carriageway only.

The information for these works was last updated by Staffordshire County Council on 16 October 2024 at 10:24.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Hyde Lane, Kinver

Works Details

WORKS COMPLETED
Major
Staffordshire County Council logo
These works are handled by:
Staffordshire County Council
Staffordshire County Council logo
Local Authority:
Staffordshire County Council
Works Reference LV1112243053RCMF
Permit Number 02
Place Name Hyde Lane
Kinver
Proposed Start 7 Oct 2024
Proposed End 10 Oct 2024
Actual Start 7 Oct 2024 09:20
Actual End 10 Oct 2024 16:00
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
52.455623
-2.235083
Last Updated 16 Oct 2024 10:24
Works History for Activity LV1112243053RCMF (Hyde Lane, Kinver)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
5 Jul 2024
13:28
Permit Submitted
29 Aug 2024
01:00
31 Aug 2024
00:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
5 Jul 2024
16:14
Permit Granted
29 Aug 2024
01:00
31 Aug 2024
00:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
2 Sep 2024
12:23
Permit Alteration Granted
25 Sep 2024
01:00
27 Sep 2024
00:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Sep 2024
17:10
Permit Alteration Granted
7 Oct 2024
01:00
10 Oct 2024
00:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
9 Oct 2024
14:45
Permit Alteration Granted
7 Oct 2024
01:00
11 Oct 2024
00:59
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
16 Oct 2024
11:08
Work Started
7 Oct 2024
01:00
11 Oct 2024
00:59
7 Oct 2024
10:20
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
16 Oct 2024
11:24
Work Stopped
7 Oct 2024
01:00
11 Oct 2024
00:59
7 Oct 2024
10:20
10 Oct 2024
17:00
Completed

Works Permits for Hyde Lane, Kinver

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT07a (Road closed to traffic)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place when [insert road name] or [insert description of the relevant section of the road] is closed to traffic.

+
NCT10a (Employment (as agreed) of appropriate methodology)

For the activities hereby permitted, it is a condition of this permit that, for the activities on this site, as agreed, the works methodology employed will be A, B, C [describe agreed methodology] throughout the duration of the works activity.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.