ROADWORK EVENT SUMMARY
Daymer Lane, Trebetherick, Wadebridge between 27 Jan and 14 Feb 2025

Works Description for Daymer Lane, Trebetherick, Wadebridge

This is a PAA (Provisional Advance Authorisation) permit that has been granted before final details of an activity have been finalised. A full permit will be required before activities can commence.


Western Power Distribution (South West) are proposing to carry out Utility asset works on Daymer Lane, Trebetherick, Wadebridge.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 27 January 2025 and could run through until 14 February 2025. The works will impact the carriageway only.

The information for these works was last updated by Western Power Distribution (South West) on 21 October 2024 at 09:48.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Daymer Lane, Trebetherick, Wadebridge

Works Details

WORKS PLANNED
Major (PAA)
Western Power Distribution (South West) logo
These works are handled by:
Western Power Distribution (South West)
Cornwall Council logo
Local Authority:
Cornwall Council
Works Reference LN0342476095
Permit Number 01
Place Name Daymer Lane
Trebetherick
Wadebridge
Proposed Start 27 Jan 2025
Proposed End 14 Feb 2025
Actual Start
Actual End
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
50.563067
-4.922646
Last Updated 21 Oct 2024 09:48
Works History for Activity LN0342476095 (Daymer Lane, Trebetherick, Wadebridge)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Oct 2024
17:00
Permit Submitted
27 Jan 2025
08:00
14 Feb 2025
17:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Oct 2024
10:48
Permit Granted
27 Jan 2025
08:00
14 Feb 2025
17:00
Planned

Works Permits for Daymer Lane, Trebetherick, Wadebridge

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.