ROADWORK EVENT SUMMARY
Road From Town Farm To Cheznous, Monkleigh between 7 and 9 Oct 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Road From Town Farm To Cheznous, Monkleigh

South West Water carried out Utility repair and maintenance works on Road From Town Farm To Cheznous, Monkleigh.

These works were categorised as Major.

The road was closed for some or all of the period.

The works were originally planned between 7 Oct 2024 and 11 Oct 2024 and were actually completed between 7 Oct 2024 (08:39) and 9 Oct 2024 (07:29). The works impacted the footway and carriageway.

The information for these works was last updated by South West Water on 9 October 2024 at 13:49.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Road From Town Farm To Cheznous, Monkleigh

Works Details

WORKS COMPLETED
Major
South West Water logo
These works are handled by:
South West Water
Devon County Council logo
Local Authority:
Devon County Council
Works Reference LM501NC10962134
Permit Number 02
Place Name Road From Town Farm To Cheznous
Monkleigh
Proposed Start 7 Oct 2024
Proposed End 11 Oct 2024
Actual Start 7 Oct 2024 08:39
Actual End 9 Oct 2024 07:29
Traffic Management Road closure
Impact Footway, Carriageway
Coordinates
Lat, Lon
50.965356
-4.202717
Last Updated 9 Oct 2024 13:49
Contact Details for Activity LM501NC10962134 (Road From Town Farm To Cheznous, Monkleigh)

In the event that you have an issue with these works, please contact South West Water, the works operator in the first instance if details are available, as they are most likely to be able to assist and resolve the issue more quickly.

Should the issue remain, you may also contact the local authority, Devon County Council that authorised the works.

It would assist the organisations if you quote the work reference number of LM501NC10962134.

South West Water
Telephone0844 346 2020
Works History for Activity LM501NC10962134 (Road From Town Farm To Cheznous, Monkleigh)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
10 Jul 2024
11:01
Permit Submitted
7 Oct 2024
01:00
11 Oct 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
10 Jul 2024
12:24
Permit Granted
7 Oct 2024
01:00
11 Oct 2024
01:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
7 Oct 2024
09:40
Work Started
7 Oct 2024
01:00
11 Oct 2024
01:00
7 Oct 2024
09:39
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
9 Oct 2024
14:49
Work Stopped
7 Oct 2024
01:00
11 Oct 2024
01:00
7 Oct 2024
09:39
9 Oct 2024
08:29
Completed

Works Permits for Road From Town Farm To Cheznous, Monkleigh

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT07a (Road closed to traffic)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place when [insert road name] or [insert description of the relevant section of the road] is closed to traffic.

+
NCT09d (Changes to traffic management arrangements)
For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.