ROADWORK EVENT SUMMARY
Verdun Avenue, Hebburn between 21 and 23 Oct 2024

Works Description for Verdun Avenue, Hebburn

This is a PAA (Provisional Advance Authorisation) permit that has been granted before final details of an activity have been finalised. A full permit will be required before activities can commence.


South Tyneside Council are proposing to carry out Highway repair and maintenance works on Verdun Avenue, Hebburn.

These works are categorised as Major.

The road will be closed for some or all of the period and could cause delays to journeys.

The works will start on or after 21 October 2024 and could run through until 23 October 2024. The works will impact the carriageway only.

The information for these works was last updated by South Tyneside Council on 23 July 2024 at 10:42.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Verdun Avenue, Hebburn

Works Details

WORKS PLANNED
Major (PAA)
South Tyneside Council logo
These works are handled by:
South Tyneside Council
South Tyneside Council logo
Local Authority:
South Tyneside Council
Works Reference LK00107226935
Permit Number 01
Place Name Verdun Avenue
Hebburn
Proposed Start 21 Oct 2024
Proposed End 23 Oct 2024
Actual Start
Actual End
Traffic Management Road closure
Impact Carriageway
Coordinates
Lat, Lon
54.975606
-1.512544
Last Updated 23 Jul 2024 10:42
Works History for Activity LK00107226935 (Verdun Avenue, Hebburn)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 Jul 2024
11:13
Permit Submitted
21 Oct 2024
10:00
23 Oct 2024
18:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 Jul 2024
11:42
Permit Granted
21 Oct 2024
10:00
23 Oct 2024
18:00
Planned

Works Permits for Verdun Avenue, Hebburn

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT07a (Road closed to traffic)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place when [insert road name] or [insert description of the relevant section of the road] is closed to traffic.

+
NCT10a (Employment (as agreed) of appropriate methodology)

For the activities hereby permitted, it is a condition of this permit that, for the activities on this site, as agreed, the works methodology employed will be A, B, C [describe agreed methodology] throughout the duration of the works activity.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.