ROADWORK EVENT SUMMARY
Surrey Street, Sheffield between 14 Mar and 25 Nov 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Surrey Street, Sheffield

Sheffield City Council are carrying out Utility asset works on Surrey Street, Sheffield.

These works are categorised as Emergency Works with an immediate start.

The works should not impact the carriageway.

The works started on 14 March 2024 at 01:00 and could run through until 25 November 2024. The works will impact the footway only.

The information for these works was last updated by Sheffield City Council on 18 November 2024 at 11:21.


Share
Follow

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Surrey Street, Sheffield

Works Details

WORKS IN PROGRESS
Immediate - emergency
Sheffield City Council logo
These works are handled by:
Sheffield City Council
Sheffield City Council logo
Local Authority:
Sheffield City Council
Works Reference LC20520902264
Permit Number 01
Place Name Surrey Street
Sheffield
Proposed Start 14 Mar 2024
Proposed End 25 Nov 2024
Actual Start 14 Mar 2024 01:00
Actual End
Traffic Management No carriageway incursion
Impact Footway
Coordinates
Lat, Lon
53.380099
-1.467377
Last Updated 18 Nov 2024 11:21
Works History for Activity LC20520902264 (Surrey Street, Sheffield)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
14 Mar 2024
10:48
Permit Submitted
14 Mar 2024
01:00
21 Mar 2024
23:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
14 Mar 2024
11:14
Permit Granted
14 Mar 2024
01:00
21 Mar 2024
23:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
20 Mar 2024
09:44
Permit Alteration Granted
14 Mar 2024
01:00
2 Apr 2024
00:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
2 Apr 2024
11:22
Permit Alteration Granted
14 Mar 2024
01:00
16 Apr 2024
00:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Apr 2024
08:57
Permit Alteration Granted
14 Mar 2024
01:00
29 Apr 2024
23:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
29 Apr 2024
07:57
Permit Alteration Granted
14 Mar 2024
01:00
14 May 2024
00:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
13 May 2024
10:54
Permit Alteration Granted
14 Mar 2024
01:00
28 May 2024
00:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
28 May 2024
08:27
Permit Alteration Granted
14 Mar 2024
01:00
4 Jun 2024
00:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
3 Jun 2024
08:34
Permit Alteration Granted
14 Mar 2024
01:00
18 Jun 2024
00:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
17 Jun 2024
15:00
Permit Alteration Granted
14 Mar 2024
01:00
2 Jul 2024
00:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
1 Jul 2024
12:51
Permit Alteration Granted
14 Mar 2024
01:00
16 Jul 2024
00:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Jul 2024
11:11
Permit Alteration Granted
14 Mar 2024
01:00
30 Jul 2024
00:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
12 Aug 2024
11:21
Permit Alteration Granted
14 Mar 2024
01:00
27 Aug 2024
00:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
27 Aug 2024
08:56
Permit Alteration Granted
14 Mar 2024
01:00
10 Sep 2024
00:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
9 Sep 2024
12:32
Permit Alteration Granted
14 Mar 2024
01:00
24 Sep 2024
00:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
23 Sep 2024
08:29
Permit Alteration Granted
14 Mar 2024
01:00
8 Oct 2024
00:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
7 Oct 2024
15:33
Permit Alteration Granted
14 Mar 2024
01:00
22 Oct 2024
00:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Oct 2024
10:31
Permit Alteration Granted
14 Mar 2024
01:00
4 Nov 2024
23:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
4 Nov 2024
09:22
Permit Alteration Granted
14 Mar 2024
01:00
18 Nov 2024
23:59
14 Mar 2024
01:00
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
18 Nov 2024
11:21
Permit Alteration Granted
14 Mar 2024
01:00
25 Nov 2024
23:59
14 Mar 2024
01:00
In Progress

Works Permits for Surrey Street, Sheffield

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT02a (Limit the days and times of day within the permit duration)

For the activities hereby permitted, it is a condition of this permit that activities shall only take place between [start time] and [end time] on weekdays and [start time] and [end time] on Saturdays and [start time] and [end time] on Sundays or Bank Holiday.

+
NCT05a (Width and/or length of road space that can be occupied)

For the activities hereby permitted, it is a condition of this permit that the activity shall occur only within the area [insert description of area or provide traffic management plan reference] including the relevant and required signing, lighting and guarding excluding advance warning, advance communication and diversionary signs.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

+
NCT11b (Publicity for proposed works)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence unless the promoter has publicised and/or advised all individual properties and businesses [on x roads] setting out where the works will take place; the nature of the works; the duration of the works; the intended start date [etc.] and contact details of a representative of the promoter.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.