ROADWORK EVENT SUMMARY
B5062 From Sundorne Road To Wrekin Distr, Shrewsbury between 21 and 22 Nov 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for B5062 From Sundorne Road To Wrekin Distr, Shrewsbury

Severn Trent Water carried out Utility repair and maintenance works on B5062 From Sundorne Road To Wrekin Distr, Shrewsbury.

Two-way signals were in place for some or all of the period.

The works were originally planned between 21 Nov 2024 and 22 Nov 2024 and were actually completed between 21 Nov 2024 (09:35) and 22 Nov 2024 (15:30). The works impacted the verge only.

The information for these works was last updated by Severn Trent Water on 22 November 2024 at 15:41.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for B5062 From Sundorne Road To Wrekin Distr, Shrewsbury

Works Details

WORKS COMPLETED
Severn Trent Water logo
These works are handled by:
Severn Trent Water
Shropshire Council logo
Local Authority:
Shropshire Council
Works Reference LB9141201-000060618533A
Permit Number 01
Place Name B5062 From Sundorne Road To Wrekin Distr
Shrewsbury
Proposed Start 21 Nov 2024
Proposed End 22 Nov 2024
Actual Start 21 Nov 2024 09:35
Actual End 22 Nov 2024 15:30
Traffic Management Two-way signals
Impact Verge
Coordinates
Lat, Lon
52.726956
-2.700044
Last Updated 22 Nov 2024 15:41
Works History for Activity LB9141201-000060618533A (B5062 From Sundorne Road To Wrekin Distr, Shrewsbury)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
15 Oct 2024
16:19
Permit Submitted
21 Nov 2024
08:00
25 Nov 2024
17:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
16 Oct 2024
14:49
Permit Alteration Granted
21 Nov 2024
08:00
22 Nov 2024
17:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
16 Oct 2024
15:37
Permit Granted
21 Nov 2024
08:00
22 Nov 2024
17:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
21 Nov 2024
09:35
Work Started
21 Nov 2024
08:00
22 Nov 2024
17:00
21 Nov 2024
09:35
In Progress
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
22 Nov 2024
15:41
Work Stopped
21 Nov 2024
08:00
22 Nov 2024
17:00
21 Nov 2024
09:35
22 Nov 2024
15:30
Completed

Works Permits for B5062 From Sundorne Road To Wrekin Distr, Shrewsbury

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT05a (Width and/or length of road space that can be occupied)

For the activities hereby permitted, it is a condition of this permit that the activity shall occur only within the area [insert description of area or provide traffic management plan reference] including the relevant and required signing, lighting and guarding excluding advance warning, advance communication and diversionary signs.

+
NCT06a (Road space to be available to traffic/pedestrians at certain times of day)

For the activities hereby permitted, it is a condition of this permit that [x]m must be maintained for pedestrians and/or [y]m must be maintained for vehicles at the specified times.

+
NCT08a (Traffic management request)

For the activities hereby permitted, it is a condition of this permit that works, or the relevant part of the activity, shall only take place when the following traffic management is deployed by use of x (where x determines type of control i.e. portable signals, stop/go boards etc.)

+
NCT08b (Manual control of traffic management)

For the activities hereby permitted, it is a condition of this permit that, for the traffic management deployed (state type), it is manually operated between (x hours and y hours).

+
NCT10a (Employment (as agreed) of appropriate methodology)

For the activities hereby permitted, it is a condition of this permit that, for the activities on this site, as agreed, the works methodology employed will be A, B, C [describe agreed methodology] throughout the duration of the works activity.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.