ROADWORK EVENT SUMMARY
Leyson Road, The Reddings, Cheltenham between 17 and 19 Dec 2024

For local roadworks happening in your street and local area, enter your postcode for a detailed report
Type your postcode

Works Description for Leyson Road, The Reddings, Cheltenham

Severn Trent Water were proposing to carry out Utility repair and maintenance works on Leyson Road, The Reddings, Cheltenham.

The works were originally planned to start 17 December 2024 and run through until 19 December 2024. The works were due to impact the footway only.

The information for these works was last updated by Severn Trent Water on 18 December 2024 at 08:55.


Share

New Alerting Facility

We are pleased to announce our free new alerting faciity that will automatically notify you whenever there are future updates to a roadwork event that affects you.

Simply click on the Follow button to opt in and of course, you may cancel them at any time.

Please note that any Follow request only relates to that specific roadwork event and not to any other roadworks at that location.

Click to Dismiss

Works Map for Leyson Road, The Reddings, Cheltenham

Works Details

WORKS CANCELLED
Severn Trent Water logo
These works are handled by:
Severn Trent Water
Gloucestershire County Council logo
Local Authority:
Gloucestershire County Council
Works Reference LB9060000-000042043082
Permit Number 01
Place Name Leyson Road
The Reddings
Cheltenham
Proposed Start 17 Dec 2024
Proposed End 19 Dec 2024
Actual Start
Actual End
Traffic Management Some carriageway incursion
Impact Footway
Coordinates
Lat, Lon
51.887725
-2.131912
Last Updated 18 Dec 2024 08:55
Works History for Activity LB9060000-000042043082 (Leyson Road, The Reddings, Cheltenham)
Proposed
Actual
Date
Activity
Start
End
Start
End
Status
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
10 Dec 2024
09:36
Permit Submitted
17 Dec 2024
08:00
19 Dec 2024
17:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
11 Dec 2024
12:36
Permit Granted
17 Dec 2024
08:00
19 Dec 2024
17:00
Planned
Activity Date
Activity
Proposed Start
Proposed End
Actual Start
Actual End
18 Dec 2024
08:55
Permit Cancelled
17 Dec 2024
08:00
19 Dec 2024
17:00
Cancelled

Works Permits for Leyson Road, The Reddings, Cheltenham

+
NCT01a (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date or, in the case of 'immediate works', the start date contained in the application for immediate works and must end by the estimated end date provided on this permit. The proposed start date, actual start date and estimated end date will be as defined.

Applies to all permits.

+
NCT01b (Duration)

For the activities hereby permitted, it is a condition of this permit that activities shall not commence before the proposed start date and must commence within the valid starting window period or in the case of immediate works by the actual start date contained in the application for immediate works. Once the activities have commenced, the activities must take no more than [x number of] days in total to be completed. The proposed start date, actual start date and estimated end date are as defined.

Applies to all permits.

+
NCT05a (Width and/or length of road space that can be occupied)

For the activities hereby permitted, it is a condition of this permit that the activity shall occur only within the area [insert description of area or provide traffic management plan reference] including the relevant and required signing, lighting and guarding excluding advance warning, advance communication and diversionary signs.

+
NCT10a (Employment (as agreed) of appropriate methodology)

For the activities hereby permitted, it is a condition of this permit that, for the activities on this site, as agreed, the works methodology employed will be A, B, C [describe agreed methodology] throughout the duration of the works activity.

+
NCT11a (Display of Permit Number)

For the activities hereby permitted, it is a condition of this permit that activities shall not be carried out unless a site information board(s) displaying the permit reference number is on the site at all times for the duration of the works. This must be displayed in a prominent place at all times so that it may be read easily by the public, clearly displaying the correct permit reference number. For immediate works, the display of the permit reference number is required by 10.00am on the next working day after the works have started on site.

Applies to all permits.

Notes

Proposed Work Dates

Roadworks are planned in advance and sometimes are proposed to run over a number of days. It may well be that the roadworks start after the proposed start date due to bad weather or other operational delays. Equally, works may complete before the proposed end date as the works may have included a few extra days just in case.

Problems with roadworks?

On rare occasions, issues may occur during or after the completion of roadworks, such as:

  • Poor reinstatement of the footpath or the carriageway.
  • Rubbish and mess remaining after the works have completed.
  • Traffic management issues during the works.
  • Equipment left behind after the works have completed.
  • Any other issues or disruption that the works may be causing.

In such instances, you should try and contact the organisation carrying out the works in the first instance. If we have contact details available they are shown on the detailed roadworks page.

In the event that the organistion cannot help, then the local authority that authorised the works may be able to help and again, if their contact details are published then we have provided their contact information on our detailed roadworks page.

Unfortunately, here at StreetGuide, we are only publishers of the data provided by the organisations and cannot provide information or assistance on individual works.

Contains public sector information licensed under the Open Government Licence v3.0.